Home

Reference Manual

image

Contents

1. Q Inverter Cabling PV module 12A 20A 7A 12A eee we TA 12A 20A IA 2b AT 7A Da 12A 20A TA L 12A a 20A 30A o 12A 20A 12A 12A 5i RAL 20A 12A tee 20A 30A 12A 20A 12A ae f Illustration 5 21 Incorrect Parallel Connection 1 Parallel jumper 2 Parallel connection 1 input Current in first input is exceeded thus overloading cable and PV load switch 3 el connection missing All PV power feeds into one t thus risking overload of PV connector cable and PV switch 4 Parallel jumper missing thus risking overload of PV connector cable and PV load switch in the event of inverter failure Table 5 3 Legend to Illustration 5 21 46 L00410320 07_02 i L oS X 150AA027 12 Installation and Start up 5 7 PV Connection AWARNING Do NOT connect PV to earth NOTE Use a suitable voltmeter that can measure up to 1000 V DC PV Connection Procedure 1 First verify the polarity and maximum voltage of the PV arrays by measuring the PV open circuit voltage The PV open circuit voltage must not exceed 1000 V DC 2 Measure the DC voltage between the plus terminal of the PV array and Earth or the green yellow PE cable The voltage measured should approximate zero If the voltage is constant and not zero there is an insulation failure somewhere in the PV array Loc
2. 4 Illustration 11 2 Overview of Inverter with Torque Indications 1 3 150AA007 11 Parameter Tool Tightening Torque 1 Terminal blocks large 3 PE Straight slot 1 0 x 5 5 mm 2 2 Nm 4 5 6 7 Table 11 6 Legend to Illustration 11 2 and Illustration 11 3 Nm Specifications 88 L00410320 07_02 Technical Data 11 6 Mains Circuit Specifications TLX Eai Recommended blow fuse type gL gG Recommended automatic fuse type B Table 11 7 Mains Circuit Specifications 8k 10k 12 5k Maximum inverter 9 0A 119A 14 9A 187A 224A current lacmax 2 15k 5A 32 A 11 7 Auxiliary Interface Specifications Parameter Serial Communication Common cable specification RJ 45 2 pcs connectors Terminal block Max number of inverter nodes Galvanic interface insulation Direct contact protection Short circuit protection Communication Common cable Specification Temperature sensor input Cable specification Sensor specification Direct contact protection Short circuit protection Irradiation sensor input Parameter Details Specification RS 485 Cable type Shielded Twisted Pair STP Cat 5e Cable Characteristic Impedance 100 Q 120 Q Max cable length 1000 m 24 26 AWG depending on mating metallic RJ 45 plug a E S WS SOW SCSC Y 100 m total network length unlimited Shielded Twist
3. In residential installations the domestic circuits and the solar inverters are usually connected to the grid at one common point The installation becomes part of the low voltage LV distribution system Commercial installations are normally larger and therefore connected to the medium voltage MV system Large scale commercial systems such as power plants can be connected to the high voltage HV grid Each of the power systems has individual ancillary service requirements Depending on the location and the DNO some of these services will be mandatory and others are optional Mandatory requirements are automatically configured through the selected grid code Optional services are configured by the installer during commis sioning Grid support can be divided into the following main groups which will be covered in subsequent sections e Dynamic Network Support Active Power Control e Reactive Power Control 9 1 1 Active Reactive Power Theory The principle in generating reactive power is that the phases between the voltage and the current are shifted in a controlled way Reactive power cannot transport consumable energy but it generates losses in power lines and transformers and is normally unwanted Reactive loads can be either capacitive or inductive in nature depending on the current leads or lags in relation to the voltage Utility companies have an interest in controlling reactive power in their grids for e
4. Network Subnet 2 Address NOTE The inverter is pre configured with a unique RS 485 address If the address is changed manually ensure that inverters connected in a network do not have identical addresses 7 3 5 Ethernet Communication Refer to the section Auxiliary Interface Specifications for Ethernet communication configuration details 7 4 Start up and Check of Settings 74 1 Initial Setup The inverter is shipped with a predefined set of settings for different grids All grid specific limits are stored in the inverter and must be selected at installation It is always possible to see the applied grid limits in the display The inverter accounts for daylight saving automatically L00410320 07_02 65 User Interface After installation check all cables and then close the inverter Turn on AC at the mains switch Follow the setup wizard in the display or alternatively set up the inverter via the web interface When prompted by the display select language This selection has no influence on the operating parameters of the inverter and is not a grid code selection Select language Illustration 7 4 Select Language The language is set to English at initial start up To change this setting press the OK button Press Y to scroll down through the languages Select language by pressing OK NOTE To use the default language English simply press the OK button twice to select and accept
5. Correct selection of grid code is essential to comply with local and national standards NOTE If the two grid code selections do not match they will be cancelled and it will be necessary to redo the selections If an incorrect grid code is accidentally accepted at the first selection simply accept the Grid Undefined in the confirm grid code screen This will cancel the country selection and a new selection is possible NOTE If an incorrect grid code is selected twice call service The inverter will start automatically if sufficient solar radiation is available The start up will take a few minutes Mustiala ni7 eee GNA CONE During this period the inverter will carry out a self test The display will now show Select grid The grid code is set to undefined at initial start up To select grid code press OK Press Y to scroll down through the list of countries Select the grid code for the installation by pressing OK It is very important that the correct grid code is chosen L00410320 07_02 67 er User Interface Installed PV power to be mode Network This will show all inverters connected to Actual Configuration programmed the master inverter PV1 PV2 and PV3 are all set into individual mode The nominal PV NOTE installed are a Wi a Only 1 master per network is possible PV 2 6000 W PV 3 3000 W NOTE PV1 and PV2 are set into parallel mode and have a t
6. standard settings Since alteration of parameters can result in violation of legal requirements as well as affect the grid negatively and reduce inverter yield alterations are password protected Depending on parameter type some alterations are restricted to factory changes In case of parameters used for optimisation of the local grid alterations are allowed for installers Alterations of parameters will automatically alter the grid code to Custom 3 2 Change Procedure Follow the procedure described below for each change of grid code either directly or via changes to other functional safety settings For more information refer to International Inverter Procedure for PV plant owner 1 Determine the desired grid code setting The person responsible for the decision to change the grid code accepts full responsibility for any future conflicts 2 Order the change of setting with the authorised technician Procedure for authorised technician 1 Contact the service hotline to obtain a 24 hour level 2 password and username 2 Access and change the grid code setting via the web interface or the display To change settings via the web interface service interface use remote access Inverter level Setup gt Communication gt Remote access The inverter logs the parameter change 22 L00410320 07_02 Requirements for Connection 4 Requirements for Connection 4 1 Pre installation Guidelines Read
7. 1 Deviant from VDE 0126 1 1 section 4 7 1 the isolation resistance measurement limit is set to 200 kQ in accordance with authorities 2 TLX and TLX Pro only 86 L00410320 07_02 Technical Data 11 3 France UTE Requirements Parameter Condition Specification Wal Plate NOTE In France observe the UTE C 15 712 1 and NF C 15 100 requirements Alignment Perpendicular 5 all angles Table 11 5 Wall Plate Specifications For installation in France apply warning label to front of inverter Illustration 11 1 Position of Warning Label 11 4 Installation Parameter Specification Temperature 25 C 60 C gt 45 C derating Environmental class according to IEC ir quality general gt Air quality coastal heavy industrial and agricultural zones Vibration Ingress protection class Max operating IEC60721 3 3 ISA S71 04 1985 Level G2 at 75 RH Must be measured and classified acc to ISA S71 04 1985 3000 m above sea level altitude PELV protection is effective up to 2000 m above sea level only Installation Avoid constant stream of water Avoid direct sunlight Ensure adequate air flow Mount on non flammable surface Mount upright on vertical surface Prevent dust and ammonia gases Table 11 4 Conditions for Installation L00410320 07_02 87 Technical Data 11 5 Torque Specifications for Installation 150AA006 10
8. Functional Safety VDE 0126 1 1 A1 VDE AR N 4105 Made in Denmark Danfoss Solar Inverters A S Illustration 2 1 Product Label 10 The product label on the side of the inverter shows Inverter type e important specifications e Serial number see 1 for identification by Danfoss L00410320 07_02 Description of the Inverter 2 2 Mechanical Overview of inverter 2 i 11 Communication board Table 2 6 Legend to Illustration 2 2 Inverter Components Item Part Name GSM antenna optional pee i L00410320 07_02 11 Description of the Inverter 2 3 Description of the Inverter 2 3 1 Functional Overview The TLX Series comprises transformerless three phase inverters with a high performance 3 level inverter bridge For maximum flexibility the inverter has 2 or 3 separate inputs and equivalent number of MPP trackers The inverter has an integrated residual current monitoring unit insulation test functionality and an integrated PV load switch To support reliable power generation during grid faults the inverter has extended fault ride through capabilities The inverter supports a wide range of interna tional grid requirements Darfi The inverter has a wide range of interfaces e User interface Display Service web interface TLX and TLX web interface TLX Pro and TLX Pro e Communication interface Standard RS 485 Optional GSM modem Ethernet T
9. Inverter relay or transistor has failed assumed open circuit Display Text SELF_TEST_4_7_INVERTER_RELAY_INV_ UPPER_FAILED End user Call the installer Installer Call service Service Exchange the inverter Event ID 360 Description Inverter relay or transistor has failed assumed open circuit Display Text SELF TEST 4 7 INVERTER RELAY INV_ LOWER_FAILED Action End user Call the installer Installer Call service Service Exchange the inverter Event ID 361 Description Grid relay has failed assumed open circuit Display Text SELF_TEST 4 8 GRID_DIF_FAILED Action End user Call the installer Installer Check and or fix the neutral wire Call service Service Exchange the inverter Event ID 362 Description Neutral relay has failed inverter relay assumed welded Action End user Call the installer Installer Check and or fix the neutral wire Call service Service Exchange the inverter Display Text SELF_TEST 4 9 NEUTRAL_INV_RELAY_ FAILED Event ID 363 Description Neutral relay has failed grid relay assumed welded Display Text Action SELF_TEST 4 9 NEUTRAL GRID_RELAY End user _ FAILED Call the installer Installer Check and or fix the neutral wire Call service Service Exchange the inverter Event ID 364 Display Text Description SELF_TEST 4 9 NEUTRAL RELAYS FAI Neutral connection is LED damaged or
10. The Q value is sent to all followers in the network 150AA077 10 Illustration 9 8 Setpoint Curve Q U DE Ethernet l FRI 1 Grid voltage measurement Table 9 6 Configuration To configure variable reactive power security level 1 is required e For TLX Pro via the web interface navigate to ee Plant level Setup gt Grid management e For TLX via the service web interface navigate to Inverter level Setup gt Grid management e Via CLX monitoring and grid management product or third party device see manual from external device supplier 80 L00410320 07_02 Darfi Ancillary Services 9 5 3 Remotely Controlled Adjustment of Danfoss CLX GM is needed as interface device between the Reactive Power DNO signal interface radio receiver and the master inverter The master inverter uses the DNO signal All inverters support remotely controlled adjustment of information to determine the requested reactive power reactive power commanded by the DNO and communicates this to the followers in the network For more information see the TLX Pro Danfoss CLX GM User Manual When using the master functionality of the TLX Pro inverter to manage the control of reactive power the le z S
11. The total length is defined as twice the physical distance between the inverter and the PV array plus the length of the PV cables included in the modules Avoid looping the DC cables as they can act as an antenna of radio noise emitted by the inverter Cables with positive and negative polarity should be placed side by side with as little space between them as possible This also lowers the induced voltage in case of lightning and reduces the risk of damage DC Max 1000 V 12 A Cable length 4 mm 4 8 Q km Cable length 6 mm 3 4 Q km gt 200 300 m Table 4 16 Cable Specifications The distance between inverter and PV array and back plus the cumulative length of PV array cabling 4 3 1 Recommendations and Goals when Dimensioning Optimising the PV Configuration Voltage The output power from the inverter can be optimised by applying the maximum open circuit input voltage Vacmax per input The minimum limit for open circuit voltage is 500 V Examples 1 In a PV system of 75 modules each with an open circuit voltage of 40 V at 10 C and 1000 W m it is possible to connect up to 25 modules in one string 25 40 V 1000 V This allows for three strings and every string reaches the maximum inverter input voltage of 1000 V at 10 C and 1000 W m2 similar to PV system examples 1 and 2 2 Another PV system only has 70 modules of the same type as above Thus only two strings can reach the optimum of 1000 V
12. 1h 0 Communication board 0 Part and serial number 0 123A4567 0 123456A789 0 Software version 1 Operating time 1h 0 Func Safety Processor 0 Software version 0 Display 0 Software version Communication board part number Communication board serial number Communication board software version Functional Safety processor software version Dj o clic a 3 x x ojo z kej ojo gt 2 D Oo a Ss ov aja g n lo 2 oO e S a Z d a M oO es 4 D n D Els e Q 53 2 T o ma Q AE a 9 R 2 2 S 3 D 3 vu Cc O 5 w a w a om D Ss a Display software version N L00410320 07_02 5 User Interface Display Functions 0 Upload status 0 Upload status Off O Signal strength O GSM status None 0 Network 0 Failed uploads 0 0 Last error 0 0 0 Last upload 0 Table 7 4 Menu Structure Status Visible when communication channel is set to GSM 7 1 4 Production Log Description Current upload status Signal strength Should preferably be between 16 31 Indicates no signal Current GSM network status Network to which the modem is connected Number of consecutive failed uploads Last error ID see the GSM Manual for further assistance Time and date of last error Time and date of last successful upload 58 Display Functions 0 Total production 123456 kWh 0 Total operating time 137h
13. 3 Remotely Controlled Adjustment of Output Power Level The inverter supports remotely controlled adjustment of the output power level This is the Power Level Adjustment function PLA The inverter can handle the control of output power or it can be handled by CLX monitoring and grid management products or third party external device L00410320 07_02 77 Darfi Ancillary Services TLX Pro TLX Pro The master inverter uses the DNO signal information to When using the master functionality of TLX Pro and TLX determine the requested output power level PLA Pro to manage the control of the output power level the commanded by the DNO and communicates this to the Danfoss CLX GM is required as interface device between followers in the network the DNO signal interface radio receiver and the inverter 1 6 S M F F O wn ooo X 2 o o o o Ethernet Illustration 9 5 Example Managing Power Using TLX Pro and TLX Pro 1 DNO interface radio receiver external device send PLA commands directly to the Danfoss CLX GM inverter via the RS 485 interface Each inverter then uses this information to determine its output power limit Both Danfoss and third party products are available for external control for more information about relevant products see the supplier manuals Table 9 3 Legend to Illu
14. 43 Installation and Start up 5 5 AC Grid Connection E i 150AA059 10 140mm Illustration 5 18 AC Cable Wire Strip The illustration shows the stripping of insulation of all 5 wires of the AC cable The length of the PE wire must be longer than the mains and neutral wires 150AA002 11 L1 L2 L3 N PE PE Illustration 5 19 AC Connection Area 1 Short circuit bridge L1 L2 3 mains L1 L2 L3 and neutral N terminals L3 N Protective earth wire Table 5 1 Legend to Illustration 5 19 44 L00410320 07_02 9 Darfi Verify the inverter matches the grid voltage Release main circuit breaker and make precautions to prevent reconnection Open the front cover Insert the cable through the AC gland to the terminal blocks The three mains wires L1 L2 L3 and the Neutral wire N are mandatory and must be connected to the 4 pole terminal block with the respective markings The Protective Earth wire PE is mandatory and must be connected directly to the chassis PE terminal Insert the wire and fasten the screw to secure the wire All wires must be properly fastened with the correct torque See 11 5 Torque Specifications for Installation Close the front cover and remember to verify that both front screws are applied with the correct torque 6 8 Nm to
15. Illustration 7 5 Set Time Darfi Set time as prompted by the display Press OK to select number Press a to scroll up through the numbers Select by pressing OK The clock is 24 hour format NOTE It is very important to set the time and date accurately as the inverter uses this for logging If an incorrect time date is accidentally set correct it immediately in the set date and time menu Setup gt Inverter details Set date and time Set date Illustration 7 6 Set Date Set date as prompted by the display Press OK to select Press 4 to scroll up through the numbers Select by pressing OK Enter installed PV power PV input 2 8000 W PV input 3 8000 W Confirm selection Illustration 7 7 Installed PV Power Enter the amount of installed PV power for each of the PV inputs When two or more PV inputs are connected in parallel each PV input in the parallel group must be set to 66 L00410320 07_02 User Interface the total amount of PV power installed to that group divided by the number of parallel inputs See Table 7 8 Illustration 7 10 Confirm Grid Code Selection Illustration 7 8 Select Country Confirm the choice by selecting the grid code again and press OK The settings for the chosen grid code have now been activated Select the country in which the inverter is installed Press v to scroll down the list of countries To select a country ACAUTION press OK i
16. M25 For RS 485 and Ethernet peripheral units which apply RJ 45 plugs Other peripheral units sensors alarm outputs and RS 485 peripheral which interface the terminal block Table 6 2 Legend to Illustration 6 2 6 2 1 RS 485 Peripheral and Ethernet Units which apply RJ 45 1 Unscrew the blind plugs 2 Place the M25 cable gland in the cabinet add the nut and fasten the cable gland 3 Unscrew the cap of the cable gland and slide it over the cable s 4 The special M16 plug provided in the scope of delivery allows one or two cables with pre assembled RJ 45 plugs to be applied Adapt the M16 plug as follows According to the number of RS 485 or Ethernet cables cut one or two rubber knob s and one or two slot s in the side of the sealing insert as indicated with in the Darfi following illustrations This enables the cable s to be inserted from the side Illustration 6 3 Cut a Slot Illustration 6 4 Sealing Insert Side View Illustration 6 5 Cut Rubber Knob 1 Add the adapted plug to the cable s and insert the cable s with RJ 45 plug through the cable gland hole 2 Mount the RJ 45 plug in the RJ 45 socket and fasten the cable gland cap Illustration 6 2 3 Optionally the EMC cable clamp Illustration 6 2 can be used for a mechanical fixation of the cable provided that some of the 6 clamps are free 6 2 2 Other Peripheral Units Sensors alarms and RS 485 peripheral units which are appl
17. Make sure that the inverter is not covered and that the ventilation duct too high TPOWER_HIGH_L3 heat sink is not blocked If not call the installer TPOWER_HIGH_BOOSTER Installer TPCB_CTRL_HIGH Has the inverter derated on temperature Log gt derate security level 1 TPCB_COMM_HIG required TPCB_AUX_HIGH Has the inverter reported event 211 fan TPCB_AUX_POWER e No call service e Yes clean heatsink remove obstruction see description for event 211 Service Exchange the inverter 98 L00410320 07_02 Appendix A Event List Event ID 209 210 Display Text Description UDC_POS_HIGH End user Voltage on DC bus is UDC_NEG_HIGH Reset the inverter by disconnecting DC and AC using the switches If the too high event is repeated call the installer Installer Check whether AC voltage is below max rating or check the event log to see if other errors have occurred If AC voltage is too high wait 10 minutes then try to reconnect Service None Inverter unable to balance DC bus Event ID 211 Display Text Action Description FAN_RPM_LOW End user Fan speed is too low Is the inverter fan blocked e Yes clean the fan e No call the installer Installer Exchange the fan Service None Event ID 212 Display Text Action Description DCBUS_ BALANCE TIMEOUT End user Call the installer Installer Call service Service Exchange the inverter Event ID 213 215 Description I
18. Splitter output output optional Buma po Optional isting isting fisio Table 4 9 Legend to Table 4 8 When total input current exceeds 12 A external splitter is required Example String Connection point Inverter inputs L00410320 07_02 31 Requirements for Connection 2593 Illustration 4 9 PV System Example 3 Table 4 10 PV System Examples 3 4 2593 Illustration 4 9 PV System Example 4 Example String capacity A inclination Connection point orientation Generator and connectio C Internal parallel connection in inverter External parallel connection Inverter inputs 3 different 1 different 2 identical Table 4 11 Legend to Table 4 10 Not permitted 1 string 1 string 1 string Not permitted 1 string 1 string 1 string for string 1 Optional for strings 2 and 3 When total input current exceeds 12 A external splitter is required 32 L00410320 07_02 Requirements for Connection 2593 Illustration 4 9 PV System Example 5 Illustration 4 9 PV System Example 6 Table 4 12 PV System Examples 5 6 Example String Connection point B External C Inverter inputs capacity A Inverter External parallel Internal orientation Generator splitter connection parallel and connectio connection inclination n bo
19. There are two methods for reducing the output power ramp and hysteresis Primary frequency control ramp method The inverter reduces output power if the grid frequency exceeds F1 Reduction occurs at a preconfigured rate which is the ramp R shown in the illustration When the frequency reaches F2 the inverter disconnects from grid When the frequency decreases below F2 the inverter reconnects to grid and ramps up power at the same rate as for the reduction Pnom P i O 1 00 l l l i 0 48 4 l l l 50 2 51 5 f Hz Illustration 9 3 Primary Frequency Control Ramp Method Primary Frequency control hysteresis method To support grid stabilisation the inverter reduces output power if the grid frequency exceeds F1 Reduction occurs at a preconfigured rate which is the ramp R shown in the illustration The reduced output power limit is maintained until the grid frequency has decreased to F2 When the grid frequency has decreased to F2 the inverter output power increases again following a time ramp T When the frequency decreases below F2 the inverter reconnects to grid and ramps up power at the same rate as for the reduction If the grid frequency continues to increase the inverter disconnects at F3 Pnom P l lt 0 1 L N i T S L H L k f2 fl f Hz Illustration 9 4 Primary Frequency Control Hysteresis Method 9 4
20. U Constant reactive power PF CLX Home GM Fixed active power P limit vA Fixed apparent power S 4 limit Closed loop reactive power s6 v Open loop reactive power CLX Home v4 Table 9 1 Grid Management 1 Max 50 inverters per network Zero Current Setting For special requirements from the DNO a zero current 2 Max 3 inverters per network LVRT option is available It provides no current in fault 3 Max 20 inverters per network ride through situations 4 Ethernet max 100 inverters per network The inverter has a high immunity against voltage distur bances as depicted in 9 3 1 Example Germany MV 5 Or by other third party products via RS 485 6 By third party product 9 3 1 Example Germany MV NOTE How FRT works Check local legal requirements before changing settings Illustration 9 2 shows the requirements to be followed by for ancillary services FRT This example is for German medium voltage grids e Above line 1 For voltages above line 1 the inverter must not disconnect from the grid during FRT under any 9 3 Dynamic Network Support The grid voltage usually has a smooth waveform but circumstances occasionally the voltage drops or disappears for several e 36 AreaA milliseconds This is often due to short circuit of overhead The inverter must not disconnect from grid for lines or caused by operation of switchgear or similar in voltages below line 1 and left of line 2 In some the hi
21. Web Server Quick Guide 1 Plant name Displays the current plant name NOTE e Click on the plant name to display the The content of the main menu changes depending on plant view which view is currently selected the plant a group of inverters or an individual inverter The active view is e Change the plant name at Setup Plant indicated by text in red details 2 Group menu Displays groups of inverters e Inverters join group 1 by default e Click on a group name to display the group view and a list of inverters in the group e Change the group name via Setup Inverter details in the inverter view 3 Group members Displays the inverter names in the group currently selected The default inverter name is based on the serial number see 8 3 Access and Initial Setup e Click on an inverter name to display the inverter view e Change the name of the inverter via Setup Inverter details in the inverter view 4 Main menu This menu corresponds to the inverter display main menu 5 Sub menu The sub menu corresponds to the main menu item currently selected All sub menu items belonging to a particular main menu item are displayed here 6 Content area The web interface main menu and sub menus are identical to the menus in the inverter display The sub menu content displayed here corresponds to the sub menu selected Overview On some pages a horizontal menu is provided for improved readability 7 F
22. fallback values can be used in the event of communication failure between the master inverter and the Danfoss CLX GM or between the master inverter and the follower inverter Configuration To configure fallback values access at security level 1 is required e For TLX Pro TLX Pro navigate to Plant level Grid management gt Fallback values 82 L00410320 07_02 Service and Repair 10 Service and Repair NOTE 10 1 Troubleshooting Do not cover the inverter Do not use a water hose aggressive chemicals cleaning To quickly diagnose an error affecting an inverter go to solvents or strong detergents to clean the inverter the Log menu and enter the Eventlog menu The latest event registered by the inverter as well as a list of the 20 most recent events is shown here When the inverter enters On grid mode the most recent event is cleared and is shown as 0 The event code is made up of 2 elements 1 Group classifier describes the general type of the event 2 Event ID identifies the specific event 12 Appendix A Event List contains an overview of all events including suggested actions The status menu contains many useful sensor read outs which may be helpful in diagnosing the exact problem Review the contents of the status menu to obtain an overview of these read outs 10 2 Maintenance Normally the inverter needs no maintenance or calibration Ensure the heatsink at the rear of the inverter i
23. missing Action End user Call the installer Installer Check AC installation for failures on neutral connection Call service Service Verify that the AC installation is correct according to the instal lation manual Verify that the neutral wire is correctly connected The failure is most likely in the installation 104 L00410320 07_02 Appendix A Event List 12 1 5 Communication Events Event ID 1 Label GSM LAN Description Dynamic memory allocation failed eNoMemory Action End user Reset the inverter by disconnection If the event persists call the installer Installer Call service Service Report the error Event ID 3 Label GSM LAN Description eModemBufferInO Incoming data buffer verflow overflowed modem response too long Action End user Reset the inverter by disconnection If the event persists call the installer Installer Call service Service Report the error Event ID 4 Label GSM LAN Description eModemCmdReplyError Current modem command received ERROR response Action End user Reset the inverter by disconnection If the event persists call the installer Installer Call service Service Report the error or it has a serious problem because it did not respond to last AT command Event ID 5 Label GSM LAN Action Description eModemCmdTimeout s End user Current modem Call the installer command timed out Instal
24. name of the group the inverter is part of Max 15 characters Only visible if Master mode is enabled The name of the plant Max 15 characters 1 Set date and time 1 Date dd mm yyyy 30 12 2002 1 Time hh mm ss 13 45 27 0 Calibration 0 PV array 0 PV input 1 6000 W 0 PV 1 area 123 m 0 PV input 2 6000 W 0 PV 2 area 123 m 0 PV input 3 6000 W 0 PV 3 area 123 m 0 Irradiation sensor 0 Scale mV 1000 W m2 75 0 Temp coeff 0 06 C 0 Temp sensor offset 0 PV module temp 2 C 0 Ambient Temp 2 C 0 SO sensor input 0 Scale pulses kWh 1000 0 Environment 0 CO2 emission factor 0 0 5 kg kWh Set the current date Set the current time Not visible if inverter only has 2 PV inputs Not visible if inverter only has 2 PV inputs Sensor calibrati o pe Sensor calibrati S Sensor calibration offset Sensor calibration offset Sensor calibration See note Value to be used for total CO2 saved calculation 0 Remuneration per kWh 0 44 42 ct kWh 0 Yield start count 1000 kWh 0 Communication setup Value to be used for total revenue calculation A value used as an offset from the current production value when calculating the yield 0 RS485 setup 0 Network 15 0 Subnet 15 0 Address 255 0 IP Setup 0 IP config Automatic 0 IP address 0 192 168 1 191 0 Subnet mask 0 255 255 255 0 0
25. obtain PE connection Close main circuit breaker CAUTION For safety check all wiring Connecting a phase wire to the neutral terminal may permanently damage the inverter Do not remove the short circuit bridge at 1 Installation and Start up 5 6 Parallel PV String Configuration For parallel PV string configuration always use the internal parallel jumper together with an external parallel coupling Ei Inverter Cabling PV module S 12A ate 12A g 12A a A 12A 12A TA ae 124 12A re ae 12A ee 20A 30A A 4 20A 7A 12A pa 20A 7A Illustration 5 20 Correct Parallel Connection Parallel jumper 1 Parallel connection 3 inputs Parallel connection 2 inputs Table 5 2 Legend to Illustration 5 20 L00410320 07_02 45 Installation and Start up
26. occur None Event ID 43 Label GSM LAN Action Description elnvalidSerial End user Call the installer Installer Call the service provider Service provider Fix serial number Event ID 44 Label Description elnvalidPIN The SIM PIN code is not valid A PIN code must be 4 8 characters long and consist only of digits No other characters are permitted Action End user A PIN code must be 4 8 characters long and consist only of digits No other characters are permitted Installer None Service None L00410320 07_02 111 Appendix A Event List Event ID 45 Label Description Failed to open FTP file for uploading eModemFileOpenFail GSM LAN Action End user Call the installer Installer Change the FTP server configuration spec defining supported FTP configuration needed Call service Service Report the error Event ID 46 Label Description eModemSendSMSFail Failed to send an SMS This error does not occur when uploading to data warehouse GSM LAN Action End user Move SIM to a phone and try to send SMS Possible cause lack of credit Try different SIM cards Installer Call service Service Report the error Event ID 47 Label Description eModemSendEmailFail Failed to send an email via GSM This error does not occur when uploading to data warehouse 112 GSM LAN Action End user Move SIM to a phone and
27. persists after 24 hours call service Service Exchange the inverter Event ID 255 257 Display Text Description UGRID_ABS_MEAN_HIGH_L1 Islanding event UGRID_ABS_MEAN_HIGH_L2 logged UGRID_ABS_MEAN_HIGH_L3 Action End user Check event log for other grid events 1 55 and follow the instructions for these events If the event persists call the installer Installer If the event persists after 24 hours call service Service Exchange the inverter Event ID 255 257 Display Text DC bus overvoltage Description UDCPROTECT_OVERVOLTAGE Action End user If the event persists for 2 3 days call the installer Installer Check PV installation layout If OK and if event reoccurs after 24 hours call service Service Exchange the inverter L00410320 07_02 101 Appendix A Event List Event ID 259 Description Internal parameter is too low Display Text SELF _TEST 4 4 INTERNAL_PARAMETE R_TOO_LOW End user Call the installer Installer Call service Service Exchange the inverter Event ID 260 Description Unable to change the voltage between ground and neutral during isolation test by less than 10 V Display Text SELF_TEST 4 4 VEN TOO_LOW Action End user Call the installer Installer Check the PV installation for isolation error If OK call service Service Exchange the inverter Event ID 261 Description Short circuited booster
28. reduction PLA disconnects from grid Installer if PLA is below 3 of None nominal power Service None Event ID 54 56 Display Text Action Description IGRID_DC_CURRENT_HIGH_L1S2 End user DC grid current too IGRID_DC_CURRENT_HIGH_L2S2 If this event is reported several times each day contact the installer high stage 2 IGRID_DC_CURRENT_HIGH_L3S2 Installer Perform on site grid analysis Service None 12 1 3 PV Events Event ID 100 102 Display Text Action Description IPV_NEGATIVE_PV1 End user The input current is IPV_NEGATIVE_PV2 Call the installer negative the polarity IPV_NEGATIVE_PV3 Installer of the PV string is e is the polarity of the PV strings reversed e g PV plus wire connected wrong Should only with inverter minus input appear during or immediately after installation or service e f not call service Service Exchange the inverter L00410320 07_02 97 Appendix A Event List Event ID 103 105 Display Text Action Description IPV_HIGH_PV1 End user The input current is IPV_HIGH_PV2 Call the installer too high Too many _ IPV_HIGH_PV3 Installer PV modules Check PV installation connected in parallel e How many strings are in parallel What are their current ratings Has Should only appear on the 12 A input limit been exceeded newly installed e Has the inverter derated on PV current Log gt derate level 1 systems If too many strings are in paral
29. s 0 0 4 L N Z a Illustration 11 4 Communication Board GND DATA DATA GND GND DATA BIAS DATA 8 pole terminal blocks 1 2 Proomodetem Oo 3 Proo0ambienttem o i O 4 Pri000 adiation sensortemp 5 6 7 O OOOS O J S0 Energy meter Relay 1 Table 11 10 Legend to Illustration 11 4 RS 485 Terminate the RS 485 communication bus at both ends To terminate the RS 485 bus e Connect Bias H to RX TX B Connect Bias L to RX TX A The RS 485 address of the inverter is unique and defined at the factory Illustration 11 5 RS 485 Communication Detail Cat 5 T 568A 5e SFTP L00410320 07_02 91 Technical Data 150AA019 10 150AA019 10 Illustration 11 7 RJ 45 Pinout Detail for Ethernet RX TX A Not connected Table 11 11 Legend to Illustration 11 6 Bold Compulsory Cat5 cable contains all 8 wires For Ethernet 10Base TX and 100Base TX auto cross over Ethernet Ethernet connection is available for TLX Pro and TLX Pro variants only Colour Standard Pinout Ethernet Cat5 Cat 5 1 2 3 4 5 6 7 8 Brown Brown Table 11 12 Legend to Illustration 11 7 11 7 1 Network Topology The inverter has two Ethernet RJ 45 connectors enabling the connection of several inverters in a line topology as an alternative to the typical star topology The two ports are similar and may be used interchangeably For RS 485 only linear daisy chai
30. the desired sweep interval in minutes Forced sweep Forced sweep operates independently of the standard sweep functionality and is intended for long term evaluation of the PV panels The recommended procedure is to perform an initial forced sweep after commissioning and save the results in a log file Comparison of future sweeps to the initial sweep will indicate the extent of power loss due to degeneration of the solar panels over time For comparable results ensure similar conditions temperature irradiation etc Procedure Inverter level only e Go to Inverter level Setup PV Sweep Click on Force sweep A forced sweep comprises the following steps 1 Disconnection of inverter from the grid 2 Measurement of open circuit voltage of the PV panels 3 Reconnection of inverter to the grid 4 Resumption completion of PV sweep 5 Resumption of normal production To view the result of the most recent PV sweep performed go to e Inverter level Inverter gt Status gt PV sweep e Plant level Plant gt Status gt PV sweep For further information see the TLX Series Web Server Manual e Chapter 4 PV Sweep Plant Inverter e Chapter 6 PV Sweep Plant inverter L00410320 07_02 17 Description of the Inverter 2 3 7 Efficiency The conversion efficiency has been measured with a Yokogawa WT 3000 precision power analyser over a period of 250 sec at 25 C and 230 V AC grid The eff
31. to initiate a network scan Setup Inverter details M aster 68 L00410320 07_02 Web Server Quick Guide 8 Web Server Quick Guide CAUTION All inverters connected to the internet through Ethernet must be behind a firewall 8 1 Introduction These instructions describe the TLX Pro web interface which facilitates remote access to the inverter The Web Server is available in TLX Pro and TLX Pro inverters only Refer to the download area at www danfoss com solar for the newest instructions 8 2 Supported Characters For all language versions the web interface software supports characters compatible with Unicode For plant group and inverter name only the following characters are supported Letters abcdefghijkimnopqrstuvwxyz Capital letters ABCDEFGHI KLM NOPQRSTUVWXYZ Numbers 012345670 Table 8 1 Supported Characters NOTE No spaces are allowed in inverter name 8 3 Access and Initial Setup 8 3 1 Access via PC Ethernet Interface Setup Sequence 1 Select which inverter will be set up as master usually the one connected to the PC or closest to the router in a daisy chain sensors connected 2 Open the cover of this inverter Refer to the TLX Series Installation Manual for instructions 3 Connect the inverter RJ 45 interface to the PC Ethernet interface using a patch cable network cable cat5e crossed or straight through 4 On the PC wait until Windows reports limited connect
32. v a ooo 2 Ethernet TTT Illustration 9 9 Example Managing Power Using TLX Pro and TLX Pro 1 DNO interface radio receiver the inverter via the RS 485 interface Each inverter then Danfoss CLX GM uses this information to determine its reactive power level Both Danfoss and third party products are available for Table 9 7 Legend to Illustration 9 9 external control For more information about relevant products see the supplier manuals TLX with CLX monitoring and grid management product or third party device Based on the input from a DNO signal interface an external device sends reactive power commands directly to Oo 1 a lt a ooo o N EE T ae a Illustration 9 10 Example Managing Power Using External Device RS485 L00410320 07_02 81 Ancillary Services 1 DNO interface radio receiver CLX monitoring and grid management product or third party device Table 9 8 Legend to Illustration 9 10 Configuration Remotely controlled reactive power is configured in the CLX monitoring and grid management product or third party device see manual for CLX monitoring and grid management product or third party device Access at security level 1 is required e For TLX Pro via the web interface navigate to Inverter level Setup Grid Management 9 6 Fallback Values When remotely controlled active power or reactive power is selected as reference value for the inverter fixed
33. 0 Production log 0 This week 0 Monday 37 kWh Description Total production since installation of inverter Total operating time since installation of inverter Production from this week Production from one day shown in kWh 0 Tuesday 67 kWh 0 Wednesday 47 kWh 0 Thursday 21 kWh 0 Friday 32 kWh 0 Saturday 38 kWh 0 Sunday 34 kWh 0 Past 4 weeks 0 This week 250 kWh 0 Last Week 251 kWh 0 2 Weeks ago 254 kWh 0 3 Weeks ago 458 kWh 0 4 Weeks ago 254 kWh 0 This year 0 January 1000 kWh 0 February 1252 kWh 0 March 1254 kWh 0 April 1654 kWh 0 May 1584 kWh 0 June 1587 kWh 0 July 1687 kWh 0 August 1685 kWh Production from this week shown in kWh Production from one month shown in kWh 0 September 1587 kWh 0 October 1698 kWh 0 November 1247 kWh 0 December 1247 kWh 0 Past years 0 This year 10000 kWh 0 Last year 10000 kWh 0 2 years ago 10000 kWh Yearly production up to 20 years back Production from this year shown in kWh L00410320 07_02 User Interface Display Functions 0 20 years ago 10000 kWh 0 Irradiation log 0 This week 0 Monday 37 kWh m 0 Tuesday 45 kWh m 0 Wednesday 79 kWh m 0 Thursday 65 kWh m 0 Friday 88 kWh m 0 Saturday 76 kWh m Description Only visible if it contains non zero values Irradiation from this week Irradiation from one day shown in kWh m 0 Sund
34. 0 temperature sensor input x 3 e irradiation sensor input e Energy meter S0 input Alarm Output 4 e Potential free relay output Except for the GSM modem which has an externally mounted antenna all auxiliary interfaces are located internally in the inverter For setup instructions refer to 7 User Interface or see the Web Server User Manual An N PLSD W yA Cz g f A 150AA004 11 eS q INY Yw ate a WW My Ue L JA a y7 Pe I MA i DA APU AINN T Illustration 6 1 Auxiliary Connection Area 1 4 Communication board Cable glands EMC clamps Table 6 1 Legend to Illustration 6 1 48 L00410320 07_02 Connection of Peripheral Un 6 2 Installation of Peripheral Cables ACAUTION To ensure fulfilment of the IP enclosure rating correctly mounted cable glands are essential for all peripheral cables Hole for cable gland The base plate of the inverter is prepared for cable glands M16 6 pcs and M25 2 pcs Holes and threads are pre drilled and shipped with blind plugs M25 M16 150AA005 11 Illustration 6 2 Auxiliary Connection Area Cable Glands 2 x M25 and 6 x M16
35. 004 108 EC IEC 62109 1 IEC 62109 2 VDE 0100 712 EN 61000 6 1 EN 61000 6 2 EN 61000 6 3 EN 61000 6 4 EN 61000 3 2 3 EN 61000 3 11 12 Yes IEC 61727 EN 50160 EN62053 31 Annex D For transformerless inverter VDE 0126 1 1 A1 VDE AR N 4105 August 2011 Technical requirements for the connection of independent generation to the grid Public Power Corporation PPC CEI 0 21 2012 06 Terna Guida Tecnica Allegato A 702 RD1699 2011 RD661 2007 VDE 0126 1 1 ISO IEC Guide 67 2004 System No 5 f G59 2 1 G83 1 1 G59 2 1 TLX Series TLX and TLX Pro TOR Hauptabschnitt D4 TOR Hauptabschnitt D2 Synergrid C10 11 Revisie 2012 06 Synergrid C10 17 revisie 8 mei 2009 Czech Energy Act Act No 458 2000 Article 24 Paragraph 10 part I II III rev09 2009 France Germany Spain UTE NF C 15 712 1 UNION TECHNIQUE DE L ELECTRICITE GUIDE PRATIQUE Installations photovoltaiques raccord es au r seau public de distribution NF C 15 100 Installations lectriques a basse tension Journal Officiel D cret n 2008 386 du 23 avril 2008 relatif aux prescriptions techniques g n rales de conception et de fonctionnement pour le raccordement d installations de production aux r seaux publics d lectricit BDEW Technische Richtlinie Erzeugungsanlagen am Mittelspannungsnetz Ausgabe J uni 2008 und Erg nzungen von 01 2009 07 2010 02 20112 REE BOE num 254 Table 11 3 Norms and Standards
36. 5 0 A 1 Power 10000 W 1 PV input 2 1 Voltage 1000 V 1 Current 15 0 A 1 Power 10000 W Description Power detected at PV input 1 Not visible if inverter only has 2 PV inputs 1 PV input 3 1 Voltage 1000 V 1 Current 15 0 A 1 Power 10000 W 0 Insulation Resistance 0 Resistance 45 MQ 1 Minimum 45 MQ 1 Maximum 45 MQ Not visible if inverter only has 2 PV inputs PV insulation resistance at start up 0 PV Input Energy 0 Total 1234567 kWh 0 PV1 123434 kWh 0 PV2 123346 kWh 0 PV3 123345 kWh 0 PV Configuration 0 PV input 1 0 PV input 2 0 PV input 3 0 AC grid 0 Present Values 0 Phase 1 0 Voltage 250 V 1 10 min mean 248 V 1 L1 L2 433 V 0 Current 11 5 A 1 DC cont of current 125 mA 0 Frequency 50 Hz 0 Power 4997 W 1 Apparent P S 4999 VA 1 Reactive P Q 150 VAr Daily production of all PV input Daily production of PV input 1 Daily production of PV input 2 Daily production of PV input 3 Not visible if inverter only has 2 PV inputs Configuration of PV input 1 The configuration is only shown when the inverter is in Connecting or On grid mode Not visible if inverter only has 2 PV inputs Voltage on phase 1 Average voltage sampled over 10 min on phase 1 Phase to phase voltage Current on phase 1 DC content of AC grid current on phase 1 Frequency on phase 1 Power on phase 1 Apparent power S on
37. 6 4 974 974 Table 2 11 Efficiencies TLX Series 10k TLX Series 12 5k and TLX Series 15k 20 L00410320 07_02 Description of the Inverter 2 3 8 Internal Overvoltage Protection PV Overvoltage Protection PV overvoltage protection is a feature that actively protects the inverter and PV modules against overvoltage The function is independent of grid connection and remains active as long as the inverter is fully functional During normal operation the MPP voltage will be in the 250 800 V range and the PV overvoltage protection remains inactive If the inverter is disconnected from grid the PV voltage will be in an open circuit scenario no MPP tracking Under these conditions and with high irradiation and low module temperature the voltage may rise and exceed 860 V At this point overvoltage protection activates When the PV overvoltage protection activates the input voltage is virtually short circuited forced to reduce to approximately 5 V leaving just enough power to supply the internal circuits The input voltage reduction is performed within 1 5 ms When normal grid condition is re established the inverter will exit the PV overvoltage protection returning MPP voltage to a level in the 250 800 V range Intermediate Overvoltage Protection During start up before the inverter is connected to grid and while PV is charging the intermediate circuit the overvoltage protection may be activated to prevent overvolt
38. Buttons and Functionality F1 View 1 View 2 Screen F2 Status Menu F3 Production Log Menu F4 Setup Menu When an F key is selected the LED above it will light up Home Return to View Screen OK Enter select Arrow Down Arrow Right Arow Left Back Return de select On Green LED Alarm Red LED On flashing 0n grid Connecting Flashing Fail safe m The inverter is configured as master Icons can be found in the top right corner H The inverter is connected to a master Icons can be found in the top right corner Table 7 1 Legend to Illustration 7 1 TLX Pro and TLX Pro only NOTE The contrast level of the display can be altered by pressing the arrow up down button while holding down the F1 button The menu structure is divided into four main sections 1 View presents a short list of information read only 2 Status shows inverter parameter readings read only 3 Production log shows logged data 4 Setup shows configurable parameters read write See the following sections for more detailed information Three predefined security levels filter user access to menus and options Security levels e Level 0 End user no password is needed e Level 1 Installer service technician e Level 2 Installer service technician extended L00410320 07_02 53 Darfi User Interface When logged on as Admin via the web interface access is e When the service task is compl
39. C using the switches If the event persists call the installer Installer Call service Service Exchange board or inverter L00410320 07_02 Appendix A Event List Event ID 245 Display Text Description EVT_COVER_OPEN Cannot be displayed after software version 2 01 new communi cation boards introduced week 37 2010 Action End user Installer Service Event ID 246 Display Text Description FSP_GRID_EVENT Functional safety processor detected grid event Action End user Check event log for other grid events 1 55 and follow the instructions for these events If the event persists call the installer Installer If the event persists after 24 hours call service Service Exchange the inverter Event ID 247 Display Text A plausibility fault has occurred in the functional safety processor Description FSP_PLAUSIBILITY_ FAULT Action End user Check event log for other grid events 1 55 and follow the instructions for these events If the event persists call the installer Installer If the event persists after 24 hours call service Service Exchange the inverter Event ID 248 251 Display Text The self test has failed Description SELF TEST FAILED FSP_FAIL SAFE Action End user Check event log for other grid events 1 55 and follow the instructions for these events If the event persists call the installer Installer If the event
40. Default gateway raat L00410320 07_02 6 User Interface i Display Functions 0 192 168 1 1 0 DNS server 0 123 123 123 123 0 GPRS connection setup 0 SIM PIN code 0000 0 Access point name name 0 User name user 0 Password password 0 Roaming Disabled 0 Data warehouse service 0 Start log upload 0 Upload internal 0 D W FTP server address www inverterdata com 0 D W server port 21 Description 4 8 characters Max 24 characters Max 24 characters Max 24 characters Requires data from at least 10 min of energy production Never Hourly Daily Weekly Monthly 0 D W server user name user 0 D W server password password 0 Communication channel 0 Communication channel GSM 0 Autotest 0 Status Off 0 Ugrid 234 V 0 Utest 234 V 0 Fgrid 50 03 Hz 0 Ftest 50 03 Hz 0 Disconnection time 53 ms 0 Logging 0 Interval 10 min 0 Logging capacity 0 10 Days 1 Delete event log 1 Delete production log 1 Delete irradiation log 1 Delete data log Default serial number of the inverter User name for Data warehouse account max 20 chars Password for Data warehouse account max 20 chars Initiate autotest only applicable with grid code Italy Only visible during voltage tests Only visible during voltage tests Only visible during frequency tests Only visible during frequency tests Not visible in Off and Completed OK stat
41. ELF_TEST 4 5 STEP_FAILED Action End user Call the installer Installer Call service Service Exchange the inverter Event ID 353 Description Short circuited inverter transistor AC Display Text SELF_TEST 4 6 CURRENT AT OPEN GRID_FAILED Action End user Call the installer Installer Call service Service Exchange the inverter measurements cannot be performed Event ID 354 Display Text Action Description SELF_TEST_4 6 CURRENT AT OPEN_ End user Short circuited inverter GRID_AVG_FAILED Call the installer transistor AC Installer average Call service Service Exchange the inverter Event ID 356 Display Text Action Description SELF_TEST 4 7_INVERTER_BIAS FAILE End user Test of inverter relay D Call the installer and voltage Installer Call service Service Exchange the inverter Event ID 357 Description Inverter relay has failed contact assumed welded Display Text SELF _TEST 4 7 INVERTER RELAY FAIL ED Action End user Call the installer Installer Call service Service Exchange the inverter Event ID 358 Description Inverter relay has failed contact assumed welded Display Text SELF_TEST 4 7_INVERTER_INV_VOLTA GE_FAILED Action End user Call the installer Installer Call service Service Exchange the inverter L00410320 07_02 103 Appendix A Event List Event ID 359 Description
42. Faults or inappropriate use may lead to electric arcing AWARNING Do not work on the inverter while disconnecting DC and AC The short circuit current of the photovoltaic panels is only slightly higher than the maximum operating current and depends on the level of solar irradiation PV Load Switch 150AA008 10 The PV load switch 1 enables safe disconnection of DC current Conformity Go to the download area at www danfoss com solar Approvals and Certifications for information CE marking This certifies the conformity of the equipment with the regulations which apply in accordance with the directives 2004 108 EC and 2006 95 EC Table 1 1 L00410320 07_02 Contents Contents 1 Introduction 5 L00410320 07_02 Contents 5 3 Removing the Inverter 42 2 L00410320 07_02 Contents 8 Web Server Quick Guide 69 L00410320 07_02 Contents 12 Appendix A Event List mn 94 12 1 1 How to Read the Event List sme 94 12 1 2 Grid Events carat eran orci auetcte pastas dae hanes Aedes we 94 1213 PVEVENIS o a a sa cast sheds Ratna iMate be Sahat Oeil Setacatlin 97 12 1 4 Internal Events idee Raa ae oe de ee te ee 98 12 1 5 Communication Events 105 4 L00410320 07_02 Introduction 1 Introduction 1 1 Introduction This manual describes planning installation and basic operation of the TLX Series solar inverters Illustration 1 1 Solar Inverter Chap
43. IDUAL_STEP_S2_HIGH DC and AC and observe if the event reoccurs If the event reoccurs call the RCMU has measured IRESIDUAL_STEP_S1_HIGH installer an excessive current Installer Check the PV installation If OK call service Service Exchange the inverter 96 L00410320 07_02 Appendix A Event List Event ID 40 Display Text Description GRID_DURING_CONNECT End user AC grid out of spec Call the installer and inform about for more than 10 e Frequency minutes frequency isplay Status gt Inverter gt AC grid gt Present value and or voltage D Voltage Display Status gt Inverter gt AC grid gt Present value S W version isplay Status gt Inverter gt Serial no and SW version gt Inverter D Grid code setting eg Germany LV 1 Display Status Inverter Installer If SW version is 2 15 or older an update is needed Check the log for other events Check the AC installation Service None Event ID 41 43 Display Text Action Description FAULT_RIDE_THROUGH_L1 End user The inverter has FAULT_RIDE_THROUGH_L2 If this event is reported several times each day contact the installer detected that grid FAULT_RIDE_THROUGH_L3 Installer voltage was below a Perform on site grid analysis certain level Service None Event ID 47 48 Display Text Action Description PLA_BELOW_THRESHOLD End user The inverter Contact the DNO and obtain status on active power
44. L 150AA075 10 12 667 10 800 V dc max V dc min Illustration 4 7 Operating Range per MPP Tracker 1 Operating Range per MPP Tracker Table 4 5 Legend to Illustration 4 7 Maximum Open circuit Voltage The open circuit voltage from the PV strings must not exceed the maximum open circuit voltage limit of the inverter Check the specification of the open circuit voltage at the lowest PV module operating temperature Also check that the maximum system voltage of the PV modules is not exceeded During installation verify the voltage before connecting the PV modules to the inverter use a category IlI voltmeter that can measure DC values up to 1000 V Special requirements apply to thin film modules See 4 3 2 Thin Film MPP Voltage The string MPP voltage must be within the operational range of the MPPT of the inverter defined by minimum voltage operation MPP 250 V and maximum voltage operating MPP 800 V for the temperature range of the PV modules Short circuit Current The maximum short circuit current Isc must not exceed the absolute maximum that the inverter is able to E V dcmpptmax U V withstand Check the specification of the short circuit current at the highest PV module operating temperature Observe the power limits for individual PV inputs However the converted input power will be limited by maximum converted PV input power total Zmpptmax and not the sum of maxi
45. LX Pro and TLX Pro e Sensor inputs SO metering input Irradiation sensor input reference cell 3 x Temperature inputs PT1000 e Alarm outputs 1 x potential free relay r O Q O 150AA001 10 A ibs eee i p al Illustration 2 3 Overview of Connection Area 1 AC connection area see 5 5 AC Grid Connection Communication see 6 Connection of Peripheral Units DC connection area see 5 7 PV Connection Table 2 7 Legend to Illustration 2 3 12 L00410320 07_02 Description of the Inverter 2 3 2 Functional Safety The inverters are designed for international use with functional safety circuit design meeting a wide range of international requirements see 2 3 3 International Inverter Single fault Immunity The functional safety circuit is designed with two independent monitoring units each having control of a set of grid separation relays to guarantee single fault immunity All functional safety circuits are tested during start up to ensure safe operation If a circuit fails more than once out of three times during the self test the inverter goes into fail safe mode If the measured grid voltages grid frequencies or residual current during normal operation differ too much between the
46. MAKING MODERN LIVING POSSIBLE TLX Reference Manual Three phase 6k 8k 10k 12 5k and 15k SOLAR INVERTERS Safety and Conformity Safety and Conformity Safety All persons installing and servicing inverters must be e Trained and experienced in general safety rules for work on electrical equipment e Familiar with local requirements rules and regulations for the installation Safety Message Types AWARNING Safety information important for human safety Warnings are used for indicating potentially hazardous situations that can cause serious injury or death ACAUTION Cautions with symbol are used for indicating potentially hazardous situations that can cause minor or moderate injuries CAUTION Cautions without symbol are used for indicating situations that may result in equipment or property damage NOTE Note is used for indicating highlighted information that should be regarded with attention General Safety NOTE Before installation Check for damage to inverter and packaging If in doubt contact the supplier before installing the inverter CAUTION Installation For optimum safety follow the steps described in this manual Keep in mind that the inverter has two voltage carrying sides the PV input and the AC grid AWARNING Disconnecting the inverter Before starting work on the inverter switch off AC grid at the mains switch and PV using the PV load switch Ensure that the devi
47. S connection GSM LAN Action End user Many things can cause the GPRS connection to fail The APN username or password might be wrong Ask GSM provider for GPRS configuration Maybe GPRS is not enabled for the SIM in question Installer None Service None L00410320 07_02 109 Appendix A Event List Failed to set FTP mode The server refused to accept binary mode transfer This should not happen in production release when uploading to current Meteocontrol FTP server Event ID 36 Label GSM LAN Action Description eFTPOpen End user Failed to open FTP e Possible causes connection No internet connection Wrong FTP server address Wrong username or password e Try to connect to the FTP server from the PC Verify that the inverter has access to the internet Installer None Service None Event ID 37 Label GSM LAN Action Description eFTPTransferlype End user Call the installer Installer Change the FTP server configuration spec defining supported FTP configuration needed Call service Service Report the error Uploading the file fails when the server refuses it or when there is a problem with the internet connection Maybe the firewall blocks active mode FTP Event ID 38 Label GSM LAN Action Description eFTPChdir End user Failed to change FTP Call the installer directory only if FTP Installer directory has been Change the FTP server configuratio
48. SUM_ERROR COMM_FLASH_CHECKSUM_ERROR FSP_FLASH_CHECKSUM_ERROR Action End user Call the installer Installer Call service Service Exchange board or inverter Event ID 233 240 Description Memory check failed Display Text CTRL_RAM_CHECK ERROR COMM_RAM_CHECK_ERROR FSP_RAM_CHECK_ERROR CTRL_RAM_COMPLEMENT_ERROR COMM_RAM_COMPLEMENT_ERROR xxx_RAM_COMPLEMENT_ERROR Action End user Restart the inverter by disconnecting AC and DC using the switches If the event persists call the installer Installer Call service Service Exchange board or inverter Event ID 241 Description No contact to sensor Display Text 12C_FAULT Action End user Restart the inverter by disconnecting AC and DC using the switches If the event persists call the installer Installer Call service Service Exchange board or inverter Event ID 242 Description Communication between inverter and control board failed for more than 10 seconds Display Text SPI_FAULT Action End user Restart the inverter by disconnecting AC and DC using the switches If the event persists call the installer Installer Call service Service Exchange board or inverter Event ID 243 244 249 Description Internal communi cation error 100 Display Text FPGA_WATCHDOG TIMEOUT FSP_WATCHDOG_ TIMEOUT FSP_COMM_FAULT Action End user Restart the inverter by disconnecting AC and D
49. The default value of Duration is 1 minute The Duration function serves to avoid inappropriate activation of self consumption e Time of day Set Trigger time to the desired time of self consumption activation in the format hh mm ss Self consumption is automatically de activated when the sun sets and the inverter disconnects from the grid 7 3 2 Communication Channel Selection of a communication channel is the first step in configuration of email transmission and FTP upload Denpi To select communication channel e Use the display of the master inverter e Go to Setup gt Communication setup gt Communication channel e Select GSM to transmit FTP upload and emails via the optional GSM modem e Select Local network to transmit FTP upload and emails via Ethernet To fully activate email communication or FTP upload additional configuration is required in the menus GPRS connection setup and Data Warehouse Service Note that when the communication channel is set to Not present no FTP upload or email transmission will take place even when parameters are configured correctly in GPRS connection setup and Data Warehouse Service 7 3 3 GSM modem Refer to the GSM Manual 7 3 4 RS 485 Communication The configuration of the RS 485 network interface consists of 3 parameters in the menu Setup gt Communications setup gt RS 485 setup requires a security level 1 or higher
50. The remaining 20 modules reach a voltage value of 800 V at 10 C This string should then be connected to the last inverter input similar to PV system example 4 3 Finally a third PV system has 62 modules of the type described above With two strings of 25 modules 12 modules remain for the last inverter input 12 modules only produce 480 V open Dafoe circuit voltage at 10 C The voltage at the last inverter input is consequently too low A correct solution is to connect 22 modules to the first inverter input and two times 20 modules to the remaining two inputs This corresponds to 880 V and 800 V at 10 C and 1000 W m2 similar to PV system example 4 Optimising PV Power The ratio between installed PV power at STC Pstc and nominal inverter power Pnom the so called PV to grid ratio Kpv ac is used to evaluate the sizing of the inverter To reach a maximum Performance Ratio with a cost efficient solution the following upper limits should not be exceeded The values in Table 4 17 are for guidance only Corresponding power for inverter type TIX Series System type Tracker systems Fixed systems with optimal conditions Close to ideal orientation between SW and SE and inclination more than 10 Fixed systems with semi optima conditions Orientation or inclination is outside the above mentioned limits Fixed systems with sub optimal conditions Orientation and inclination is outside th
51. To change the SO calibration parameter first enter the new setting then restart the inverter to activate the change For layout of the SO terminal block see Illustration 6 2 For detailed specifications reference is made to 11 7 Auxiliary Interface Specifications For setup support pulses per kWh and more see 6 Connection of Peripheral Units for instructions 6 4 Relay Output The relay output can be used for either of the following purposes e _as trigger for an alarm or e as trigger for self consumption The relay is potential free Type NO Normally Open For setup activation and deactivation refer to 6 Connection of Peripheral Units 6 4 1 Alarm The relay can trigger a visual alarm and or an audible alarm device to indicate events of various inverters to see which ones refer to 10 1 Troubleshooting 6 4 2 Self consumption Based on a configurable amount of inverter output power or time of day the relay can be set to trigger a consumption load eg washing machine heater etc Once triggered the relay remains closed until the inverter disconnects from grid eg at the end of the day To avoid overloading the internal relay it must be ensured that the external load does not exceed the capability of the internal relay refer to 11 7 Auxiliary Interface Specifi cations For loads exceeding the internal relay capability an auxiliary contactor must be used L00410320 07_02 51 Connection of Peripher
52. age in the intermediate circuit 2 4 Autotest Procedure An automatic test of the inverter can be initialised by activating the inverter autotest procedure e Via the display go to Setup gt Autotest and press OK e Via the web interface go to Inverter level Setup gt Setup details gt Autotest and click on Start gt Test The inverter autotest manual can be downloaded from www danfoss com solar L00410320 07_02 21 Change of Functional Safety 3 Change of Functional Safety and Grid Code Settings 3 Complete and sign the form Change of Functional Safety Parameters 3 1 Functional Safety Settings For access via web server The inverter is designed for international use and it can i f Generate a settings report handle a wide range of requirements related to functional safety and grid behaviour Parameters for functional safety Fill out the form generated by and some grid code parameters are predefined and do not the web interface on the PC require any alteration during installation However some 4 Send the following to the DNO grid code parameters will require alterations during instal lation to allow optimisation of the local grid i Toe torm cnange or FUNGHANaN Safety Parameters completed and signed To meet these different requirements the inverter is E Letter requesting copy of authorisation equipped with preset grid codes to accommodate to be sent to the PV plant owner
53. al Un 6 5 GSM Modem For wireless communication a GSM modem is available Sow bf y Illustration 6 9 Placement of GSM Modem and GSM Antenna 1 Communication board External mounting position for GSM antenna a GSM antenna internal mounting Table 6 4 Legend to Illustration 6 9 For more details refer to the GSM Manual 6 6 Ethernet Communication The Ethernet communication is used when applying the master inverter functionality via the web interface of the TLX Pro and TLX Pro variants For layout of the Ethernet Interface see 11 7 Auxiliary Interface Specifications and 11 7 1 Network Topology TLX and TLX For service purposes Ethernet communication can be used to access the service web interface 6 7 RS 485 Communication RS 485 communication is used for communication with accessories and for service purposes 52 L00410320 07_02 150AA010 10 User Interface 7 User Interface 7 1 Integrated Display Unit NOTE The display activates up to 10 seconds after power up The integrated display on the inverter front gives the user access to information about the PV system and the inverter The display has two modes 1 Normal The display is in use 2 Power saving After 10 min of no display activity the back light of the display turns off to save power Re activate the display by pressing any key ooo A KL Illustration 7 1 Overview of Display
54. alities that may harm the power supply L00410320 07_02 37 Installation and Start up 5 Installation and Start up 5 1 Installation Dimensions and Patterns N d KI Illustration 5 5 Mount on non flammable surface Illustration 5 1 Avoid constant stream of water Ei ied Illustration 5 6 Mount upright on vertical surface Illustration 5 2 Avoid direct sunlight ag IX Illustration 5 7 Prevent dust and ammonia gases Illustration 5 3 Ensure adequate air flow Illustration 5 4 Ensure adequate air flow 38 L00410320 07_02 Installation and Start up Illustration 5 8 Safe Distances Observe these distances when installing one or more inverters One row mounting is recommended Contact the supplier for information on mounting in more rows L00410320 07_02 39 Installation and Start up oe 414mm a 300mm e 57mm 420m 50mm gt Illustration 5 9 Wall Plate NOTE Use of the wall plate delivered with the inverter is mandatory Use screws that can safely carry the weight of the inverter The inverter must be aligned and it is important that the inverter is accessible at the front to allow room for servicing 40 L00410320 07_02 580mm Denpi Installation and Start up 5 2 Mounting the Inverter Lift the inverter upwards 2 over the top of the mounting plate until the inverter tilts towards the wall 3 ACAUTION For safe handling of th
55. at security level 1 e via the display at Setup gt Setup details gt PV configuration e via the web interface at Inverter gt Setup gt Setup details gt PV configuration The autodetection is subsequently overridden To set the configuration via the display manually 1 Turn on AC to start the inverter 2 Enter installer password supplied by distributor in the display setup menu Go to Setup gt Security gt Password 3 Press Back and use the arrows to find the PV configuration menu under the menu setup details go to Setup gt Setup details gt PV config uration 4 Select PV configuration mode Make sure that the configuration that corresponds to the wiring is selected go to Setup gt Setup details gt PV configuration gt Mode Parallel L00410320 07_02 47 Connection of Peripheral Un 6 Connection of Peripheral Units 6 1 Overview CAUTION Auxiliary interfaces are provided via PELV circuits and are safe to touch during normal operation AC and PV must however be turned off before installation of peripheral units NOTE For wiring details refer to 11 7 Auxiliary Interface Specifi cations The inverter has the following auxiliary input output Communication interfaces GSM modem RS 485 communication 1 Ethernet communication 2 all TLX variants service web interface TLX Pro and TLX Pro variants only web interface functionality Sensor inputs 3 e PT100
56. ate and fix the failure before continuing 3 Repeat this procedure for all arrays It is allowed to distribute the input power on the inputs unevenly presuming that e The nom PV power of the inverter is not exceeded 6 2 8 2 10 3 12 9 15 5 kW The maximum short circuit current of the PV modules must not exceed 12 A per input 4 On the inverter turn the PV load switch into off position Connect the PV cables by means of MC4 connectors Ensure correct polarity The PV load switch can now be switched on when required 150AA003 10 Illustration 5 22 DC Connection Area Darfi ACAUTION When unmated the MC4 connectors are not IP54 Intrusion of moisture may occur In situations where the PV connectors are not fitted a seal cap must be mounted included in the scope of the delivery All inverters with MC4 connections are delivered with seal caps on inputs 2 and 3 During installation the seal caps of those inputs that are to be used are discarded NOTE The inverter is protected against reversed polarity but it will not generate power until the polarity is corrected To achieve optimum production the open circuit voltage STC of the PV modules must be lower than the max input voltage of the inverter see 11 1 General Data multiplied with a factor of 1 13 Uoc STC x 1 13 lt Umax inv 5 7 1 Manual PV Configuration Set up the inverter for manual PV configuration
57. ation needed Modem did not connect to any GSM network Either GSM coverage is missing or SIM card is not activated The upload file was Service corrupted during None upload Event ID 18 Label GSM LAN Action Description eModemNoNetwork End user e Check GSM signal strength If not OK try a different provider e Check if the SIM cards work in a mobile phone Installer Install router with built in GSM modem and replace for better reception Service None Event ID 19 Description SIM card did not respond to PIN query SIM card is missing or has failed Label GSM LAN eModemSIMResponse Action End user Check if the SIM card works in a mobile phone Installer Replace modem Service None Event ID 20 Description Upload file exists on server with exactly the same serial and time stamp in name DWH refuses to overwrite existing log files on server Label GSM LAN eUploadFileExists Action End user Avoid uploading to the same FTP server from different sites Installer Change FTP server configuration spec defining supported FTP configuration needed If the problem persists call service Service Report the error Failed to parse modem model Event ID 21 Label GSM LAN Action Description eModemParseMfgr End user Failed to parse modem Call the installer manufacturer Installer Replace modem Service None Event ID 22 Label GSM LAN Ac
58. atus gt Inverter gt General To change the grid code e for security level 2 obtain a 24 hour username and password from Service e log on using the username and password provided security level 2 e select grid code L00410320 07_02 13 Description of the Inverter e via the display at Setup gt Setup details via the web interface at Inverter level Setup gt Setup details For further information see 3 2 Change Procedure For details of individual grid codes contact Danfoss Selection of a grid code activates a series of settings as follows Grid power quality enhancement settings For further information see 9 Ancillary Services Functional safety settings e The cycle RMS values of the grid voltages are compared with two lower and two upper trip settings e g overvoltage stage 1 If the RMS values violates the trip settings for more than the duration of clearance time the inverter ceases to energise the grid e Loss of Mains LoM is detected by two different algorithms 1 Three phase voltage surveillance the inverter has individual control of the three phase currents The cycle RMS values of the phase phase grid voltages are compared with a lower trip setting If the RMS values violate the trip settings for more than the duration of clearance time the inverters cease to energise the grid 2 Rate of change of frequency ROCOF The ROCOF values positive or negative are
59. ay 77 kWh m 0 Past 4 weeks 0 This week 250 kWh m 0 Last week 320 kWh m 0 2 weeks ago 450 kWh m 0 3 weeks ago 421 kWh m 0 4 weeks ago 483 kWh m 0 This year 0 January 1000 kWh m 0 February 1000 kWh m 0 March 1000 kWh m 0 April 1000 kWh m 0 May 1000 kWh m 0 June 1000 kWh m 0 July 1000 kWh m2 0 August 1000 kWh m 0 September 1000 kWh m 0 October 1000 kWh m 0 November 1000 kWh m 0 December 1000 kWh m 0 Past years 0 This year 10000 kWh m Irradiation from this week shown in kWh m2 Irradiation from one month shown in kWh m Yearly irradiation up to 20 years back are shown 0 Last year 10000 kWh m2 0 2 years ago 10000 kWh m 0 3 years ago 10000 kWh m 0 20 years ago 10000 kWh m 0 Time stamps 0 Installed 30 12 99 0 Power down 21 00 00 Date of first grid connection When the inverter last changed to operation mode off grid 0 Prod initiated 06 00 00 0 De rating 0 Total de rate 0 h 1 Grid voltage 0 h 1 Grid current 0 h 1 Grid power 0 h 1 PV current 0 h 1 Temperature 0 h 0 Freq stabiliza 0 h When the inverter last changed to operation mode on grid eriod of time the inverter has limited power production in total eriod of time the inverter has limited power production due to grid voltage eriod of time the inverter has limited power production due to grid current Period of time the inve
60. cable ensure identical earthing potential of all inverters 4 2 1 Mains Circuit Breaker Cable Fuse and Load Switch No consumer load should be applied between the mains circuit breaker and the inverter An overload of the cable may not be recognised by the cable fuse see 2 3 1 Functional Overview Always use separate fuses for consumer loads Use dedicated circuit breakers with load switch functionality for load switching Threaded fuse elements like Diazed and Neozed are not considered adequate as a load switch Fuse holder may be damaged if dismounted under load Use the PV load switch to turn off the inverter before removing replacing the fuse elements The selection of the mains circuit breaker rating depends on the wiring design wire cross sectional area cable type wiring method ambient temperature inverter current rating etc Derating of the circuit breaker rating may be necessary due to self heating or if exposed to heat The maximum output current per phase can be found Table 4 2 TLX Series Maximum inverter 90A 119A 149A 187A 224A current lacmax Recommended blow fuse type gL 13 A 16 A 20 A 25 A gG Recommended automatic fuse type B Table 4 2 Mains Circuit Specifications L00410320 07_02 23 Requirements for Connection Darfi Outer diameter Cable Condition Specification AC Max recommended cable length TLX Series 6k 8k and 10k Max recommended cable leng
61. ce cannot be unintentionally reconnected Use a voltage tester to ensure that the unit is disconnected and voltage free The inverter can still be charged with very high voltage at hazardous levels even when it is disconnected from grid mains and solar modules Wait at least 30 min following disconnection from grid and PV panels before proceeding ACAUTION Maintenance and modification Only authorised personnel are allowed to repair or modify the inverter To ensure personal safety only original spare parts available from the supplier should be used If non original spare parts are used the compliance with CE guidelines in respect of electrical safety EMC and machine safety is not guaranteed The temperature of the cooling racks and components inside the inverter may exceed 70 C Observe the danger of burn injury ACAUTION Functional safety parameters Never change the parameters of the inverter without authorisation from the local energy supply company and instructions from Danfoss Unauthorised changes of functional safety parameters may cause injury or accidents to people or inverter Additionally it will lead to the cancellation of all inverter operating approval certificates and Danfoss warranties Danfoss cannot be held responsible for such injuries or accidents L00410320 07_02 Safety and Conformity Hazards of PV Systems DC voltages up to 1000 V are present in a PV system even when the AC grid is disconnected
62. ciency 84 L00410320 07_02 Technical Data Nomenclat Parameter TLX Series TLX Series TLX Series TLX Series TLX Series ure 6k 8k 10k 12 5k 15k Dimensions HW en i Acoustic noise level MPP trackers 3 Operation t t peration temperature 25 60 C Table 11 1 General Specifications 1 According to FprEN 50524 where relevant 2 At identical input voltages At unequal input voltages Vmppmin can be as low as 250 V depending on total input power 3 Remotely controlled via CLX monitoring and grid management product or third party device At rated grid voltage Vac Cos phi 1 At rated grid voltage Vac Parameter TLX Series Functional Safety Passive Active AC discon nection PELV on the communi Class II Islanding detection loss Three phase of mains monitoring ROCOF Voltage magnitude Included Frequency rs n Insulation resistance Included RCMU Type B es n Indirect contact Yes class I protection grounded Table 11 2 Functional Safety Specifications L00410320 07_02 85 Technical Data 11 2 Norms and Standards Normative References Directive LVD Directive EMC Safety Integrated PV load switch EMC immunity EMC emission Utility interference CE Utility characteristics S0 Energy Meter Functional Safety Germany Greece Italy Spain Portugal UK Ancillary Services Austria Belgium Czech Republic TLX Series 2006 95 EC 2
63. compared to the trip settings and the inverter ceases to energise the grid when the limits are violated e Residual current is monitored The inverter ceases to energise the grid when the cycle RMS value of the residual current violates the trip settings for more than the duration of clearance time a sudden jump in the DC value of the residual current is detected e _Earth to PV isolation resistance is monitored during start up of the inverter If the value is too low the inverter will wait 10 minutes and then make a new attempt to energise the grid Note The value is offset by 200 kQ in order to allow for measuring inaccuracy e If the inverter ceases to energise the grid due to grid frequency or grid voltage not three phase LoM and if the frequency or voltage is restored Denpi within a short time short interruption time the inverter can reconnect when the grid parameters have been within their limits for the specified time reconnect time Otherwise the inverter returns to the normal connection sequence See 9 Ancillary Services for additional non safety function alities which are grid code specific 2 3 4 Derating Derating the output power is a means of protecting the inverter against overload and potential failure Furthermore derating can also be activated to support the grid by reducing or limiting the output power of the inverter Derating is activated by 1 PV over current 2 Internal ove
64. derated for an AC grid where the voltage is below this limit Lower grid voltage may occur if the inverter is installed in a network placed at a distance from the transformer and or with high local loads for example in an industrial area To ensure adequate AC grid voltage measure the grid voltage at 10 00 am 12 00 am and 2 pm when the load and irradiance are high There are two alternatives 1 Downsize the PV plant to e Pstc Pnom Kpv ac measured grid voltage 230 where Pstc is the installed PV power at STC Pnom is the nominal inverter power Krv ac is the so called PV to grid ratio 2 Contact the local DNO to increase the limit on the transformer Denpi 4 3 2 Thin Film The use of TLX Series inverters with thin film modules has been approved by some manufacturers Declarations and approvals can be found at www danfoss com solar If no declaration is available for the preferred module it is important to obtain approval from the module manufacturer before installing thin film modules with the inverters The power circuit of the inverters is based on an inverted asymmetrical boost converter and bipolar DC link The negative potential between the PV arrays and earth is therefore considerably lower compared to other transfor merless inverters CAUTION Module voltage during initial degradation may be higher than the rated voltage in the data sheet This must be taken into consideration when designing t
65. dinitState End user Internal fault Installer unexpected MCH Service initialisation state Report the error 108 L00410320 07_02 Appendix A Event List Event ID 30 Label Description eModemSetPIN Failed to set PIN code The PIN code is wrong Be careful if the inverter is reset it will set the same PIN code again After two resets the SIM will block because it received 3 attempts to set wrong PIN GSM LAN Action End user See description If the card is blocked put it in a mobile phone and use the PUK code to unlock Installer None Service provider None Failed to set GPRS username User name is invalid Avoid white space Event ID 31 Label GSM LAN Action Description eGPRSParams End user Failed to set GPRS APN is invalid Use only alpha numeric a z A Z 0 9 and dot access point name characters APN Installer APN is invalid Use only None alpha numeric a z A Z Service 0 9 and dot None characters Event ID 33 Label GSM LAN Action Description eGPRSAuthPasswd End user User name is invalid Avoid white space Installer None Service None Event ID 34 Label Failed to set GPRS password Password is invalid Avoid white space Description eGPRSAuthPasswd GSM LAN Action End user User name is invalid Avoid white space Installer None Service None Event ID 35 Label Description eGPRSOpe Failed to open GPR
66. e above mentioned limits Table 4 17 Optimisation of PV Configuration According to Dr B Burger Auslegung und Dimensionierung von Wechselrichtern f r netzgekoppelte PV Anlagen Fraunhofer Institut f r Solare Energiesysteme ISE 2005 L00410320 07_02 35 Requirements for Connection NOTE The data is only valid for northern European conditions gt 48 North The PV to grid ratio is provided specifically for PV systems that are optimised with respect to inclination and orientation Design for Reactive Power The nominal active power P and the maximum apparent power S of the inverter are equal Thus there is no overhead for producing reactive Q power at full active power When the inverters are installed in a PV power plant which has to generate a certain amount of reactive power the amount of installed PV capacity per inverter must therefore be reduced Two cases must be expected 1 A certain power factor PF is required e g PF 0 95 thus the PV to grid ratio Kpv ac should be multiplied with 0 95 The corrected ratio is then used for dimensioning the plant 2 The DNO specifies a required amount of reactive power Q the nominal power P of the plant is known The PF can then be calculated as PF SQRT P2 P 2 Q2 The PF is then applied as above Design for Low AC Grid Voltage The nominal output power of the inverter is specified at a grid voltage of 230 V The input power should be
67. e inverter two people must carry the unit or a suitable transport trolley must be used Safety boots must be worn Illustration 5 12 Place Inverter in Mounting Bracket Place the lower part of the inverter against the mounting Illustration 5 10 Position the Inverter bracket Pa 3 Tilt the inverter as shown in the illustration and place the i top of the inverter against the mounting bracket Use the two guides 1 at the top plate to control the inverter SS horizontally 4 a N N a Illustration 5 13 Fasten screws Illustration 5 11 Secure the inverter Lower 4 the inverter and make sure that the hook of the inverter base plate is placed in the lower part of the L00410320 07_02 41 Installation and Start up mounting bracket 5 Check that it is not possible to lift the bottom of the inverter away from the mounting bracket 6 Fasten the screws on either side of the wall plate to secure the inverter 5 3 Removing the Inverter Loosen the locking screws on either side of the inverter Removal is performed in the reverse order of mounting With a firm grip at the lower end of the inverter lift the inverter approximately 20 mm vertically Pull the inverter slightly away from the wall Push upwards at an angle until the wall plate releases the inverter Lift the inverter away from the wall plate 5 4 Ope
68. ed Pair STP Cat 5e ooo a oo Cable jacket diameter a E L00410320 07_02 89 Technical Data Parameter Parameter Details Specification Cable specification Cable jacket diameter Cable type Shielded Single Pair Number of wires depend on the sensor type used Via EMC cable clamp br 3 3 Cable shield termination Maximum wire gauge 2 5 mm Maximum resistance per wire Via EMC cable clamp i 25m ooo Maximum cable length Sensor Specification Sensor type Output voltage of sensor Max output impedance sensor Input impedance electronics Direct contact protection Double Reinforced insulation Yes Short circuit protection Yes Energy meter input SO input Cable specification Cable jacket diameter Cable type Shielded Single Pair 2 wire Via EMC cable clamp x m 4 8 mm Cable shield termination 2 5 mm 3 Class A 12 mA for an 800 Q load 24 5 mA 12 VDC 16 7 Hz es Maximum wire gauge Maximum cable length Sensor Input Specification Sensor input class Nominal output current Maximum short circuit output current Open circuit output voltage Maximum pulse frequency lt oO Direct contact protection Double Reinforced insulation Short circuit protection Yes Table 11 8 Auxiliary Interface Specifications 1 A maximum of 100 inverters can be connected in 1 network If Parameter Condition Specification GSM modem is used for portal upload the number of invert
69. edance as function of no load voltage for the TLX ni type inside wall under ground free air Series inverters is shown in the following graph etc Ambient temperature UV resistance 4 2 2 Grid Impedance The grid impedance must correspond to the specifications to avoid unintended disconnection from the grid or derating of the output power It is similarly important that 26 L00410320 07_02 Requirements for Connection 150AA049 11 0 Da 230 235 240 245 250 255 Uscl V Illustration 4 6 Grid impedance Maximum permissible grid impedance Q versus No load grid voltage V For guidance and recommendations on dimensioning the PV generator module array to align with the following inverter capability refer to 4 3 1 Recommendations and Goals when Dimensioning 4 3 Requirements for PV Connection The nominal maximum input specification per PV input and total is shown in Table 4 4 To avoid damaging the inverter the limits in the table must be observed when dimensioning the PV generator for the inverter Parameter TLX Series O a p e f a f o Number of PV inputs JEE E Maximum input voltage open circuit Vacmax Maximum PV input power per MPPT Pmpptmax 8000 W Max nom converted PV input power total 2Pmpptmax 10300 W 12900 W 15500 W Table 4 4 PV Operating Conditions L00410320 07_02 27 Requirements for Connection 1A Isc 12 250 I dc max
70. ents for Connection the limits the inverter reduces input power to keep the temperature at a safe level The thermal management concept of the inverter is based on forced cooling by means of speed controlled fans The fans are electronically controlled and are only active when needed The back side of the inverter is designed as a heatsink that removes the heat generated by the power semiconductors in the integrated power modules Additionally the magnetic parts are ventilated by force At high altitudes the cooling capacity of the air is reduced The fan control will attempt to compensate for the reduced cooling At altitudes higher than 1000 m derating of the inverter power at system layout should be considered to avoid loss of energy Altitude 2000m 3000m Max load of inverter Table 4 19 Compensation for Altitude NOTE PELV protection is effective up to 2000 m above sea level only Other factors like higher irradiation should also be taken into account The heatsink should be cleaned regularly and checked for dust and blocking elements once a year Optimise reliability and lifetime by mounting the inverter in a location with low ambient temperature NOTE For calculation of ventilation use maximum heat dissipation of 600 W per inverter 4 3 5 Simulation of PV Contact the supplier before connecting the inverter to a power supply for testing purposes e g simulation of PV The inverter has built in function
71. er and inform about the grid phase voltage e Voltage on phase 1 is OK Wait 10 minutes on phase L1 L2 and or L3 to see if the inverter reconnects to the grid If the event reappears on site service is needed Installer Measure the grid voltage e OK call service e Not OK call the DNO for a resolution Service Exchange the inverter Event ID 16 18 Description The inverter has detected a voltage peak on the grid Display Text UGRID_INSTANTANIOUS_HIGH_L1 UGRID_INSTANTANIOUS HIGH_L2 UGRID_INSTANTANIOUS HIGH_L3 Action End user Call the installer and inform about the grid phase voltage e Voltage on phase 1 is OK Wait 10 minutes on phase L1 L2 and or L3 to see if the inverter reconnects to the grid If the event reappears on site service is needed Installer Check the AC installation all fuses and the RCD e OK call service Service Exchange the inverter Event ID 19 24 48 53 Description Grid frequency too low or too high Display Text FGRID_LOW_S1_L1 FGRID_LOW_S1_L2 FGRID_LOW_S1_L3 FGRID_HIGH_S1_L1 FGRID_HIGH_S1_L2 FGRID_HIGH_S1_L3 Action End user Call the installer and inform about the grid frequency e Frequency is OK Wait 10 minutes to see if the inverter reconnects to the grid If the event reappears on site service is needed Installer Check the AC installation all fuses and the RCD e OK call service Service Exchange the inve
72. erature 3 Grid Overvoltage When the grid voltage exceeds a DNO defined limit U1 the inverter derates the output power If the grid voltage increases and exceeds the defined limit 10 min mean U2 the inverter ceases to energise the grid in order to maintain power quality and protect other equipment connected to the grid PIW 150AA033 11 S U U1 U2 M Illustration 2 5 Grid Voltage above Limit Set by DNO U1 Fixed Table 2 8 Legend to Illustration 2 5 At grid voltages lower than the nominal voltage 230 V the inverter will derate to avoid exceeding the current limit L00410320 07_02 15 Description of the Inverter 2 3 5 MPPT ni 100 0 I E 300 1000 W m 100 500 W m OBE REER V A RT A iia 150AA036 11 98 4 4 0 5 10 15 20 25 30 35 40 17 W m s Illustration 2 7 Measured MPPT Efficiency for Two Different Ramp Profiles A Maximum Power Point Tracker MPPT is an algorithm which is constantly trying to maximise the output from the PV array The MPPT algorithm is based on the Incremental Conductance algorithm The algorithm updates the PV voltage fast enough to follow rapid changes in solar irradiance 30 W m s 2 3 6 PV Sweep The characteristic power curve of a PV string is non linear and in situations where PV panels are partly shadowed for example by a tree or a chimney the curve can have more than one local maximum power poin
73. ers in a Potential free Relay output x1 network is limited to 50 contact 2 For underground use outdoor burial type cable is recommended Rating AC 250 V AC 6 4 A 1600 W for both Ethernet and RS 485 Rating DC 24 V DC 6 4 A 153 W 3 Third input is used for compensation of the irradiation sensor Maximum wire 2 5 mm 4 The number of inverters to be connected in the RS 485 network gauge i cae depends on which peripheral device is connected Overvoltage Class III ACAUTIO N Modem GSM To ensure fulfilment of IP enclosure rating correctly mounted cable glands are essential for all peripheral cables ACAUTION To ensure EMC compliance shielded cables must be applied for sensor inputs and RS 485 communication Unshielded cables may be applied for alarm outputs Other auxiliary cables must pass through the designated EMC cable clamps to establish mechanical fixing and in case of shielded cable termination to the shielding device Table 11 9 Auxiliary Input Specifications 90 L00410320 07_02 Technical Data 1 RS485 z 2 x RJ 45 lt eee ee ee Ethernet 2 x RJ45 QU000000 DONO 2 3 4 5 6 0000000 0000000 7 P ale eooooooooeo P es
74. es The interval between each logging 0 Web Server 0 Reset password 1 Service 1 Store settings 1 Restore settings 1 Replicate settings 1 Restart comm board 1 Restart control board 1 Grid management 62 Resets the password of the Web Server to its default value Store inverter settings and data in the display of the inverter Restore all inverter settings and data stored in the display of the inverter Replicate all inverter settings to all other known inverters in the network Only visible if master mode is enabled L00410320 07_02 User Interface Display Functions 1 Apparent power S 1 Max power S 15000 VA 1 Active power P 1 Lim type Off 1 Max power 15000 W 1 Percentage 100 0 1 Reactive power Q 1 Setpoint type Off 1 Off 1 Value 1 00 1 State Overexcited 1 Output power limit 1 Lim type 1 Max power 0 Security 0 Password 0000 0 Security level 0 0 Log out Description When using remotely controlled PLA set this selection to Off Only shown when Limit type is Absolute limit Only shown when Limit type is of AC power or of inst PV Configure PF P and Q U using the web interface No setpoint Only shown if Set point type is set to Const PF or Const Q Absolute limit Pct based on PV installed PV Pct based on ACP AC power rating PLA Password Current security level Log out t
75. escribes the final step of configuring the sensor inputs using the display or the web interface Go to the Calibration menu under Setup Setup gt Calibration and choose the sensor to be configured Temperature Sensor The temperature sensor inputs for the PV module temperature and the ambient temperature may be calibrated using an offset ranging from 5 0 to 5 0 C Enter the correct values for the sensors under the Temp sensor offset menu Setup gt Calibration gt Temp sensor offset Irradiation Sensor Pyranometer In order to use an irradiation sensor the scale and temperature coefficient of the sensor must be entered Enter the correct values for the sensor at Setup gt Calibration gt Irradiation sensor Energy Meter SO sensor In order to use an energy meter SO sensor the scale of the energy meter must be entered in pulses kWh This is done under the SO sensor input menu Setup Calibration SO sensor input The relay provides multiple functions Set the relay to the function required Alarm By default the alarm functionality is disabled To activate the alarm go to Setup Relay Function and select Alarm then go to Setup Relay Alarm state and select Enabled The alarm functionality including the relay can also be tested from this menu If the alarm is triggered it will remain active for the period of time defined under Alarm time out the value 0 disables the time out functionalit
76. ete log off at at security level 0 Subsequent user accounts created Setup Security provide access to a predefined subset of menus according to user profile Define user profile at Plant gt Setup Web Server Profiles e The web interface automatically logs off the user after 10 minutes of inactivity Security levels are similar in the inverter display and the web interface A security level grants access to all menu items at the same level and to all menu items of a lower security level Throughout the manual a 0 1 or 2 inserted after the menu item indicates the minimum security level required for access Access to levels 1 and 2 requires a service logon comprising a user ID and a password e The service logon provides direct access to a specific security level for the duration of the current day e Obtain the service logon from Danfoss e Enter the logon via the web interface logon dialog 7 1 1 View Parameter Description 0 Mode On grid Displays present inverter mode See 2 3 3 Definition of Operation Modes 0 Prod today 12345 kWh Energy production today in kWh Value from inverter or SO energy meter 0 Power output 12345 W Current output power in Watt 0 utilization bar Shows level of inverter utilization as of max utilization Table 7 2 Menu Structure View 7 1 2 View 2 Pressing F1 once more will result in the following screen being shown Parameter Descript
77. f different PV connections systems are illustrated with the explanatory overview in Table 4 7 L00410320 07_02 29 Requirements for Connection Example String capacity A Inverter ientati Generator and connectio inclinati C Connection point B External Inverter inputs External parallel Internal splitter connection parallel connection in inverter 1 differ 2 identi 4 identi 6 ident 31 3 different 3 in parallel Required Splitter output optional Optional 1 string eena a Not permitted 1 string 1 string 1 string for string 1 Optional for strings 2 and 3 x Yes 4 in parallel Required Splitter i i output optional ca 3 in parallel Optional Splitter Splitter F in series output Required 2 via 1 string 1 string Y connector Table 4 7 Overview of PV System Examples When total input current exceeds 12 A external splitter is required 30 L00410320 07_02 Requirements for Connection 4 x 4 mm 6 x 4 mm Illustration 4 9 PV System Example 2 Illustration 4 9 PV System Example 1 Table 4 8 PV System Examples 1 2 External C capacity External parallel Internal orientation Generator splitter connection parallel and connectio connection inclination in inverter 3 identical x Yes 3 in parallel Required Splitter
78. gh voltage transmission lines In such cases the cases the DNO permits a short duration discon inverter can continue to supply power to the grid using nection in which case the inverter must be back fault ride through FRT functionality on grid within 2 seconds Continuous power supply to the grid is essential AaB to help prevent a complete voltage black out and stabilise the voltage in the grid to increase the energy delivered to the AC grid uo L00410320 07_02 7 Darfi Ancillary Services To the right of line 2 a short duration discon nection from grid is always permitted The When a short duration disconnection from grid occurs reconnect time and power gradient can be negotiated with the DNO the inverter must be back on grid after 2 seconds Below line 3 Below line 3 there is no requirement to remain connected to grid the active power must be ramped back at a minimum rate of 10 of nominal power per second Ucrio z l 3 z 100 a 90 70 4 30 0 150 700 1500 Time ms Illustration 9 2 German Example N OTE Parameter Description To enable reactive current during FRT select a medium FRT upper Upper grid voltage magnitude for voltage grid code threshold level engaging a high voltage FRT FRT lower threshold Lower grid voltage magnitude for engaging Parameters related to FRT level a low voltage FRT These parameters are set automatically upon selecting the Sta
79. he PV system since excessive DC voltage can damage the inverter Module current may also lie above the inverter current limit during the initial degradation In this case the inverter decreases the output power accordingly resulting in lower yield Therefore when designing take inverter and module specifications both before and after initial degradation into consideration 4 3 3 Overvoltage Protection The inverter is manufactured with internal overvoltage protection on the AC and PV side If the PV system is installed on a building with an existing lightning protection system the PV system must also be properly included in the lightning protection system The inverters are classified as having Type III class D protection limited protection Varistors in the inverter are connected between phase and neutral cables and between PV plus and minus terminals One varistor is positioned between the neutral and PE cables Connection point Overvoltage category according to EN50178 mcs Category PVside category Table 4 18 Overvoltage Category 43 4 Thermal Management All power electronics equipment generates waste heat which must be controlled and removed to avoid damage and to achieve high reliability and long life The temperature around critical components like the integrated power modules is continuously measured to protect the electronics against overheating If the temperature exceeds 36 L00410320 07_02 Requirem
80. iciency for each inverter rating are depicted below n 100 150AA038 11 o8 gt an 96 5 94 92 Use V 420V 700V 800V 90 T T 0 2000 4000 6000 PIW Illustration 2 9 Efficiency TLX Series 6k Efficiency versus AC Power kW n 100 150AA040 11 98 5 96 5 94 4 925 90 5 T T 0 2000 4000 6000 PIW Illustration 2 10 Efficiency TLX Series 8k Efficiency versus AC Power kW 18 L00410320 07_02 Description of the Inverter n 100 150AA041 11 98 5 96 5 94 4 92 90 T T 0 2000 4000 6000 PIW Illustration 2 11 Efficiency TLX Series 10k Efficiency versus AC Power kW n 100 150AA042 11 98 965 94 925 T 0 2000 4000 6000 PIW Illustration 2 12 Efficiency TLX Series 12 5k Efficiency versus AC Power kW L00410320 07_02 19 Description of the Inverter n 100 150AA043 11 98 96 94 924 90 5 T T 0 2000 4000 6000 Illustration 2 13 Efficiency TLX Series 15k Efficiency versus AC Power kW TLX Series ik 91 8 92 8 91 4 92 4 92 8 osn oe or oan 28v Table 2 10 Efficiencies TLX Series 6k and TLX Series 8k TLX Series PuowlP 700V 5 10 20 25 30 50 75 100 EU 95 7 97 0 96 7 96 1 97 3 97 3 9
81. ied to the terminal block must use M16 cable glands and EMC cable clamps L00410320 07_02 49 Connection of Peripheral Un Cable gland 1 Place the M16 cable gland in the cabinet add the nut and fasten the cable gland Unscrew the cap of the cable gland and slide it over the cable Insert the cable through the cable gland hole EMC cable clamps 1 6 Loosen the screw in the EMC cable clamp Strip the cable jacket off in a length equal to the distance from the EMC cable clamp to the terminal block in question see Illustration 6 2 If shielded cable is used strip the cable shield approx 10 mm and fix the cable in the cable clamp as shown in the following illustrations e Thin shielded cable cable shield is folded back over the jacket e Thick shielded cable gt approx 7 mm e Unshielded cable alarm output Fasten the cable clamp screw to secure it and check that the cable shield is mechanically fixed Fasten the cable gland cap Terminal block 1 50 Strip off insulation from the wires approx 6 7 mm Insert the wires in the terminal block and fasten the screws to secure them properly i 160AA014 10 Illustration 6 6 Thin Shielded Cable cable shield is folded back over the jacket 160AA015 10 Illustration 6 8 Unshielded Cable Alarm Output L00410320 07_02 160AA016 10 Connection of Peripheral U
82. ion Indicates whether or not any grid management measures are in effect 0 Grid mgmt eee Only visible if enabled by the current grid code 0 Performance ratio 87 Performance ratio is shown if irradiation sensor is available local or master 0 Total CO2 saved 123 T j j 0 Total revenue 234 5 Euro Lifetime CO2 emission saved calculated using configured value Lifetime revenue calculated using configured value Table 7 3 Menu Structure View 2 For TLX Pro only 7 1 3 Status Display Functions 0 Ambient Conditions 0 Irradiance 1400 W m Description Only applicable if sensors are connected Irradiance as detected by sensor NC if not connected 0 PV module temp 100 C 0 Ambient temp 20 C 0 Irr sensor temp 32 C 0 Photovoltaic 0 Present values 0 PV input 1 0 Voltage 1000 V 0 Current 15 0 A 54 PV module temperature as detected by sensor NC if not connected Ambient temperature as detected by sensor NC if not connected Irradiation sensor temperature as detected by sensor NC if not connected Voltage detected at PV input 1 Current detected at PV input 1 L00410320 07_02 User Interface Display Functions 0 Power 10000 W 0 PV input 2 0 Voltage 1000 V 0 Current 15 0 A 0 Power 10000 W 0 PV input 3 0 Voltage 1000 V 0 Current 15 0 A 0 Power 10000 W 1 Maximum values 1 PV input 1 1 Voltage 1000 V 1 Current 1
83. ivity if no DHCP is present Open the internet browser and ensure pop ups are enabled 5 Type http invertername in the address field e Find the serial number on the product label located on the side of the housing Invertername is the final 10 digits of the serial number 1 Only works for Windows 95 and XP For MAC and Windows 7 and newer the setup wizard in the display must be used for initial start up of the inverter Type TLX Pro 6k PV input 1000 VDC max 2 x 12 A 250 800 VDC MPP Output 3 x 400 VAC N PE 50 Hz Class I S nom 6 KVA 3 x 9 A max P nom cos Phi i 6 0 KW P nom cos Phi 0 95 5 7 KW P nom cos Phi 0 90 5 4 kW Chassis IP54 Temp 25 C to 60 C HON TNE 39F0151000000G000 Functional Safety VDE 0126 1 1 A1 VDE AR N 4105 Made in Denmark Danfoss Solar Inverters A S CE Illustration 8 1 Product Label 6 At initial start up the inverter runs a setup wizard L00410320 07_02 69 Web Server Quick Guide 8 4 Operation 8 4 1 Web Interface Structure The web interface overview is structured as follows Dashes my Plant Xx D inverter Group View Status Log Setup x4 MEETA XxX 5 Inverter_1 Production graphs off aay 100 0 Monthly Yearly Performance graphs Monthly Yearly Language Contact Logout Security level 0 Danfoss Solar Inverters x 7 Illustration 8 2 Overview 70 L00410320 07_02 Denpi
84. kW power plant with a 10 PV module efficiency the total area of the modules yields 150 m which again yields a minimum resistance of 40 MO m2 150 m 267 kQ The required limit of 1 MQ has for that reason been lowered to 200 kQ 200 kQ to allow for for measuring inaccuracy with the approval of the German authorities Deutsche Gesetzliche Unfallsversicherung Fachhausschuss Elektrotechnik During installation the resistance must be verified before connecting the PV modules to the inverter The procedure for verifying the resistance is found in the section on PV Connection Earthing It is not possible to earth any of the terminals of the PV arrays However it is compulsory to earth all conductive materials e g the mounting system to comply with the general codes for electrical installations Parallel Connection of PV Arrays The PV inputs of the inverter can be internally or externally connected in parallel See Table 4 7 The advantages and disadvantages of parallel connection are e Advantages Layout flexibility Parallel connection makes it possible to apply a single two wire cable from the PV array to the inverter reduces the installation cost e Disadvantages Monitoring of each individual string is not possible String fuses string diodes may be necessary After making the physical connection the inverter carries out an autotest of the configuration and configures itself accordingly Examples o
85. lel then fix it by connecting the inverter inputs in parallel to distribute the current into the inverter installing a second inverter Service None Event ID 115 Display Text Action Description PV_ISO_TOO_LOW End user The resistance Call the installer and inform about isolation resistance between the PV Display Status gt Photovoltaic gt Isolation resistance strings and ground is Installer too low for the Check minimum recorded isolation resistance Status gt Photovoltaic gt inverter to start up Isolation resistance security level 1 needed e Go through the PV installation and check connectors cables and modules for insulation failure e If the failure is present while on site disconnect PV input 1 and restart the inverter to locate the affected PV string Continue with strings 2 and 3 Make a visual inspection of all PV cables and modules Check that the installation is correct according to the installation manual as this event could indicate that the PE connection is missing Service None Event ID 116 Display Text Action Description SELF_TEST 4 6 WRONG_POLARITY End user Wrong PV polarity Call the installer Installer Check whether or not the inverter starts when connecting each PV input separately Be aware of parallel connections Service None 12 1 4 Internal Events Event ID 201 208 Display Text Action Description TPOWER_HIGH_L1 End user Internal temperature is TPOWER_HIGH_L2
86. ler GSM is not connected End user Open the cover and check if the modem is installed Verify that the SIM card is installed and working This is done by moving the SIM card to a phone If problem persists call service Service Exchange the GSM module Event ID 7 Label GSM LAN Description eModemilnitFail Modem s low level initialisation failed The GSM module has a serious problem Action End user Call the installer Installer End user Open the cover and check if the modem is installed Verify that the SIM card is installed and working This is done by moving the SIM card to a phone If problem persists call service Service Exchange the GSM module L00410320 07_02 105 Appendix A Event List Event ID 9 Label GSM LAN Description Internal fault unexpected state eUnexpectedState Action End user Reset the inverter by disconnection If the event persists call the installer Installer Call service Service Report the error Upload failed not vailable logged into home nor roaming if allowed GSM network GM logs on and off GSM network Indicates poor signal reception Event ID 10 Label GSM LAN Action Description eModemReplyParse End user Modem response not Failed Reset the inverter by disconnection If the event persists call the recognised installer Installer Call service Service Report the error Event ID 11 Label GSM LAN Actio
87. lter components in Off grid mode from EMC filter components Main contributor for exchange of reactive power is the LCL filter 9 5 1 Constant Value The inverter can be set to provide a fixed reactive power value in one of the following ways e Off e Constant reactive power Q e Constant power factor PF Off The inverter will not use any internal setpoint for reactive power but an external setpoint source can be used TLX inverters support a number of third party grid management units for managing reactive power Set the setpoint type to Off This will enable the inverter to accept a setpoint for PF and Q transmitted via RS 485 from the external source Constant Reactive Power Q The inverter will generate a fixed level of reactive power specified as a percentage of the inverter s nominal Dafoe apparent power S The value of constant reactive power Q can be set in the range from 60 under excited to 60 over excited The value can be maintained from 3 of nominal power Constant Power Factor PF Constant power factor specifies a fixed relation between active and apparent power P S i e a fixed Cos 9 The power factor PF can be set in the range from 0 8 under excited to 0 8 over excited The reactive power generated by the inverter is thus dependent on the active power generated Example PF 0 9 Generated active power P 10 0 kW Apparent power S 10 0 0 9 11 1 kVA Reactive po
88. mum PV input power per MPPT Pmpptmax1 Pmpptmax2 Pmpptmax3 Max Nom Converted PV Input Power Total The 2 and or 3 MPP trackers can handle more power in total than the inverter can convert The inverter will limit the power intake by shifting the MPP when surplus PV power is available 28 L00410320 07_02 Requirements for Connection 150AA080 10 2 O N S iz 2 Illustration 4 8 Max Nom Converted PV Input Power Total 1 Operating range for each individual MPP tracker 2 Zmpptmax Converted Table 4 6 Legend to Illustration 4 8 Reversed Polarity The inverter is protected against reversed polarity and will not generate power until the polarity is correct Reversed polarity damages neither the inverter nor the connectors CAUTION Remember to disconnect the PV load switch before correcting polarity PV to Earth Resistance Monitoring of the PV to earth resistance is implemented for all grid codes as supplying energy to the grid with too low a resistance could be harmful to the inverter and or the PV modules According to the German VDE0126 1 1 standard the minimum resistance between the terminals of the PV arrays and earth must be 1 k Q Voc thus for a 1000 V system this corresponds to a minimum resistance of 1 MQ However PV modules designed according to the Darfi IEC61215 standard are only tested to a specific resistance of minimum 40 MQ m2 Therefore for a 15
89. n 6 3 Sensor Inputs 6 3 1 Temperature Sensor Three temperature inputs are provided Temperature Sensor Function Input Ambient temperature Readout via display or web interface and or communication logging PV module temperature Readout via display or web interface Irradiation sensor Internal use for temperature correction temperature Table 6 3 Temperature Sensor Inputs The supported temperature sensor type is PT1000 For layout of the temperature sensor terminal block see Illustration 6 1 For detailed specifications refer to 11 7 Auxiliary Interface Specifications For setup support offset adjustment and more see6 Connection of Peripheral Units for instructions 6 3 2 Irradiation Sensor The irradiation measurement is read out via the display or web interface and or communication logging The supported irradiation sensor type is passive with a max output voltage of 150 mV For layout of the irradiation sensor terminal block reference is made to the overview of Peripheral Units For detailed specifications reference is made to 11 6 Mains Circuit Specifications For setup support sensitivity adjustment and more see 6 Connection of Peripheral Units for instructions 6 3 3 Energy Meter Sensor S0 The energy meter input is read out via the display or web interface and communication logging The supported energy meter is supported according to EN62053 31 Annex D SO is a logical count input
90. n Description eConnectionUna End user Only take action if the event reoccurs e Check GSM signal strength If not OK try a different provider e Check if the SIM cards work in a mobile phone Call the installer Installer Install router with built in GSM modem and place it for better reception Service None Event ID 12 Label GSM LAN Description eModemLinkOpenFail Failed to open upload connection generic Something other than GPRS or FTP failed Action End user Only take action if the event reoccurs e Check GSM signal strength If not OK try a different provider e Check if the SIM cards work in a mobile phone e Other FTP server Try to configure another different FTP server If event persists call the installer Installer Call service Service Report the error Event ID 13 Label GSM LAN Description eModemLinkCloseFail Failed to close connection FTP or GPRS after upload Not critical data was sent OK Action End user Not a serious event If the event reoccurs inform the installer Installer Call service Service provider Report the error 106 L00410320 07_02 Appendix A Event List Event ID 17 Description Uploaded file size check did not match Part of the file was probably lost Label GSM LAN eUploadFileSize Action End user Call the installer Installer Change FTP server configuration spec defining supported FTP configur
91. n spec defining supported FTP specified configuration needed Call service Service Report the error Event ID 39 Label GSM LAN Action Description eFTPPut End user Failed to start file Uploading the file fails when the server refuses it or when there is a upload problem with the internet connection Maybe the firewall blocks active mode FTP Installer None Service None 110 L00410320 07_02 Appendix A Event List Event ID 40 Label Description Failed to read uploaded file back to verify Getting the file listing from FTP server failed This indicates that there is a problem with the server or internet eUploadFileRead Action End user Call the installer Installer Change the FTP server configuration spec defining supported FTP configuration needed Service Report the error There is no data log to upload All unsent log has been sent and inverter has not yet generated any new log This is not an error It just indicates that all logged data that need uploading have already been uploaded connection Event ID 41 Label GSM LAN Action Description eNoData End user Installer Service The master inverter s serial number is invalid Event ID 42 Label GSM LAN Action Description eTimeNotSet End user The master inverter s Call the installer RTC is not set Inverter Installer time and date must be Set time and date set for uploads to Service
92. n On grid mode Red Inverter PR lt 50 or inverter has an error Yellow Inverter PR between 51 and 70 or inverter in Connecting mode Green No errors and inverter PR 270 and inverter in On grid mode Overall plant status Current production kW x Real time energy production level Yield today kWh x Cumulative yield for the day Performance ratio x Real time performance ratio Total yield kWh x Cumulative yield since initial startup Power limit adjustment x Power limit as of nominal inverter AC output rating Table 8 2 Plant Overview NOTE To calculate performance ratio PR an irradiation sensor is required go to Setup gt Calibration 8 5 Additional Information Refer to the TLX Series Web Server User Manual to learn more about e inverter start up and check of settings e Messaging e Graphs e Remote access e Web portal upload e Logging capacity and changing the logging interval e Settings backup and restore Ww L00410320 07_02 7 Ancillary Services 9 Ancillary Services 9 1 Introduction Ancillary services comprise inverter functionalities which aid transport of power on grids and contribute to grid stability The ancillary services required for a particular PV system are determined by the point of common coupling PCC and the grid type to which the system is connected The PCC is the point where the PV system is connected to the public electricity grid
93. n connections can be used NOTE Ring topology is not allowed 92 L00410320 07_02 Technical Data Illustration 11 8 Network Topology Linear Daisy Chain 1 Star Topology Ring Topology not allowed Ethernet Switch Table 11 13 Legend to Illustration 11 8 NOTE The two network types cannot be mixed The inverters can only be connected in networks which are either solely RS 485 or solely Ethernet NOTE Ethernet connection is recommended for faster communi cation RS 485 connection is required when a web logger or data logger is connected to the inverter or via CLX monitoring and grid management product or third party device L00410320 07_02 93 Appendix A Event List 12 Appendix A Event List 12 1 1 How to Read the Event List The Event List holds an action field for each event or the categorised group of events The Action field should be understood as progressive steps and recommendations as follows e Step 1 End User e Step 2 Installer e Step 3 Service 12 1 2 Grid Events Event ID 1 6 Display Text Action Description UgridRmsLowS2L1 End user Grid voltage too low UgridRmsLowS2L2 Call the installer and inform about the grid phase voltage UgridRmsLowS2L3 e Voltage on corresponding phase is OK UgridRmsLowS1L1 UgridRmsLowS1L2 UgridRmsLowS1L3 If the event reappears on site ser
94. nd monitoring via Ethernet Table 2 3 Monitoring Local 8 L00410320 07_02 Description of the Inverter TLX TLX TLX Pro TLX Pro Danfoss Grid management Remotely controlled active CLX Home GM2 CLX GM4 power PLA CLX Standard GM CLX Home GM CLX Standard GM Remotely controlled reactive CLX Home GM CLX GM4 power CLX Standard GM3 CLX Home GM CLX Standard GM3 Dynamic reactive power Jv daa Constant reactive power PF CLX Home GM2 v and Q CLX Standard GM3 Fixed active power P limit s Fixed apparent power S s limit Closed loop reactive power control Open loop reactive power CLX Home v4 control CLX Standard GM3 Table 2 4 Grid Management 1 Max 50 inverters per network 2 Max 3 inverters per network 3 Max 20 inverters per network 4 Ethernet max 100 inverters per network 5 Or by other third party products via RS 485 6 By third party product TLX TLX TLX Pro TLX Pro Commissioning Replication of settings neS Table 2 5 Commissioning 4 Ethernet max 100 inverters L00410320 07_02 9 Darfi Description of the Inverter Product Label Type TLX Pro 6k PV input 1000 VDC max 2 x 12 A 2 250 800 VDC MPP Output 3 x 400 VAC N PE 50 Hz Class I S nom 6 kVA 3 x 9 A max P nom cos Phi 1 6 0 kW P nom coa Phi 0 95 5 7 KW P nom cos Phi 0 90 5 4 kW Chassis 1IP54 Temp 25 C to 60 C HOMO TE mu 1 39F0151000000G000
95. ning and Closing the Inverter AWARNING Remember to observe all ESD safety regulations Any electrostatic charge must be discharged by touching the earthed housing before handling any electronic component Illustration 5 14 Loosen Front Screws Darfi Use a TX 30 screwdriver to loosen the two front screws Turn the screwdriver until the screws pop up Screws are secured with a spring and cannot fall out Illustration 5 15 Open the Inverter Push the front cover upwards When a slight resistance is felt give the front cover a tap on the bottom to snap it into holding position It is recommended to use the holding position instead of dismounting the front cover completely 42 L00410320 07_02 Installation and Start up Illustration 5 16 Close the Inverter To close the inverter hold on to the lower end of the front Illustration 5 17 Fasten Front Screws cover with one hand and give it a tap on the top until it falls into place Guide the front cover into place and fasten the two front screws ACAUTION The two front screws are the PE connection to the front cover Make sure that both screws are mounted and fastened with the specified torque L00410320 07_02
96. nternal error Voltage measured before and after the relay differs by more than 20 V Display Text UGRID_UINV_DIFF_HIGH_L1 UGRID_UINV_DIFF_HIGH_L2 UGRID_UINV_DIFF_HIGH_L3 End user Call the installer Installer Call service Service Exchange the inverter Event ID 216 218 Description Current measured on AC side is too high Display Text IGRID_HW_TRIP_L1 IGRID_HW_TRIP_L2 IGRID_HW_TRIP_L3 Action End user Call the installer Installer If software version is 1 09 or older update to latest software version If this does not help call service Display Status gt Inverter gt Serial no and SW version Service Exchange the inverter Event ID 223 Description Replaced by events 255 257 Display Text IGRID_SUM_HIGH Action End user Call the installer Installer Update software to latest version Service None L00410320 07_02 99 Appendix A Event List Event ID 224 Description Defective RCMU circuit should also include events 350 352 from self test fail safe Display Text RCMU_OVERRANGE End user Call the installer Installer If self test does not complete successfully call service partner Service Exchange the inverter Event ID 225 231 Description Failure in Memory Eeprom Display Text CTRL_EEPROM_CHECKSUM_ERROR COMM_EEPROM_CHECKSUM_ERROR AUX_EEPROM_CHECKSUM_ERROR POWER_EEPROM_CHECKSUM_ERROR CTRL_FLASH_CHECK
97. o security level 0 0 Service logon 0 User name 0 user name 0 Password 0 password Table 7 6 Menu Structure Setup For TLX Pro only Only to be used by authorised service personnel Ww L00410320 07_02 6 User Interface 7 2 Overview of Event Log The event log menu found under Log displays the last event which has occurred Latest event Example The latest event is of type Grid and the specific event ID is 29 This can be used to diagnose the problem See 12 Appendix A Event List for more information on specific events When an event is cleared Latest event is set to 0 Illustration 7 2 Latest Event Last 20 events The event log menu contains the submenu Last 20 events which is a log of the last 20 events In addition to the information provided by latest event this log also provides the time and date of the event as well as the status On Off of the event Illustration 7 3 Past 20 Events The latest event is shown at the top of the screen The event was registered at 14 33 28 on January 29th 2009 The event is grid related the specific ID is 29 and the Darfi event is no longer active Note that several entries registered at the same time may be present This however does not mean that the inverter experienced all registered events Some of the events may be a result of the original event 7 3 Peripheral Units Setup 7 3 1 Sensor Setup This section d
98. o the download area at www danfoss com solar or contact the supplier of the solar inverter L00410320 07_02 Description of the Inverter 2 Description of the Inverter 2 1 Variants The TLX Series inverter range comprises the variants TLX TLX TLX Pro TLX Pro TLX TLX TLX Pro TLX Pro Common features User interface Display Service web interface Web interface Languages Table 2 1 Common Features L00410320 07_02 7 Description of the Inverter TLX TLX TLX Pro TLX Pro Monitoring Internet FTP portal Optional retrofit Optional retrofit GSM module GSM module user defined incl CLX portal Js Via accessories only CLX portal CLX Home CLX Home GM CLX StandardGM Weblogger CLX Standard Email Weblogger Optional retrofit CLX portal GSM module only with a box or GSM module v4 SMS Optional retrofit GSM module Relay alarm or self v4 SolarApp v4 Via accessories Via accessories CLX Home CLX Home CLX Standard3 CLX Standard CLX Home GM CLX Standard GM Table 2 2 Monitoring Internet 1 1 GSM module per inverter 2 RS 485 max 3 inverters per network 3 RS 485 max 20 inverters per network 4 Ethernet max 100 inverters per network 5 Max 50 inverters per network TLX TLX TLX Pro TLX Pro Monitoring local User Interface Display for simple configuration and monitoring Built in web interface for advanced configuration a
99. ooter Options on the footer bar Language Opens a pop up window Click on the country flag to change the language of the web interface to the desired language for the active session e Contact Opens a pop up window which displays Danfoss contact information e Logout Opens the log in log out dialog box e Security level Displays the current security level as explained in 7 1 1 Security Levels L00410320 07_02 71 Web Server Quick Guide 8 4 2 Plant Group and Inverter Views The overview screens for plant view group view and inverter view display the same overall status information Denpi My Plant Inverter Group View Status Log Setup My Plant Overview e All inverters are resent 1 1 Production graphs p 1 1 Plant open loop Daily 0 00 W External 1 000 Monthly 0 00 Wh 100 0 Yearly Performance graphs Monthly Yearly Language Contact Logout Security level 0 Danfoss Solar Inverters Illustration 8 3 Plant View 72 L00410320 07_02 Web Server Quick Guide Item Unit View Description Plant and _ Inverter Group EE Red Plant PR lt 50 or Any inverter in the network in fail safe mode or missing from the scan list no contact with the master Yellow Any inverter in the network with PR lt 70 or in Connecting or Off grid mode Green Plant PR 270 and all inverters with PR 270 and all inverters i
100. otal of 10 kW PV power installed PV3 is set into individual mode and has nominal 4 kW PV power PV1 and PV2 are set into parallel PV 1 5500 W mode and have a total of 11 kW PV PV 2 5500 W power installed PV3 is set to Off PV 3 0 W and has no PV installed The master inverter can operate in a network of up to 99 follower inverters Table 7 8 Examples of Installed PV Power 7 5 Master Mode The TLX Pro and TLX Pro inverters include a Master mode feature that allows one inverter to be appointed as master inverter From the web interface of the master inverter it is possible to access any inverter in the network from one single point using a standard web browser The master inverter can act as a datalogger collecting data from all inverters in the network These data can be displayed graphically from the web interface of the master inverter or the data can also be uploaded to external webportals or exported directly to a PC The master inverter is also able to replicate settings and data to the other TLX Pro and TLX Pro inverters in the network enabling easy commis sioning and data management of larger networks Illustration 7 11 Master Mode To enable Master mode go to the Inverter details menu Setup Inverter details Master mode and set Master mode to Enabled Ensure that no other master inverters are present in the network prior to carrying out this action When Master mode is enabled it is possible
101. phase 1 Reactive power Q on phase 1 0 Phase 2 0 Voltage 250 V 1 10 min mean 248 V 1 L2 L3 433 V 0 Current 11 5 A uo L00410320 07_02 5 i User Interface Display Functions Description 1 DC cont of current 125 mA 0 Frequency 50 Hz 0 Power 4997 W 1 Apparent P S 4999 VA 1 Reactive P Q 150 VAr 0 Phase 3 0 Voltage 250 V 1 10 min mean 248 V 1 L3 L1 433 V 0 Current 11 5 A 1 DC cont of current 125 mA 0 Frequency 50 Hz 0 Power 4997 W 1 Apparent P S 4999 VA 1 Reactive P Q 150 VAr 1 Maximum values of AC Maximum values registered 1 Phase 1 1 Voltage 250 V 1 Current 11 5 A 1 Power 4997 W 1 Phase 2 1 Voltage 250 V 1 Current 11 5 A 1 Power 4997 W 1 Phase 3 1 Voltage 250 V 1 Current 11 5 A 1 Power 4997 W 0 Residual Current Monitor 0 Current 350 mA 1 Maximum value 350 mA 0 Grid management 0 Apparent power S 0 Max power S 15000 VA 0 Active power P 0 Lim type Off 0 Max power P 15000 W 0 PLA 100 Only shown if Limit type is Off 0 Reactive power Q Even though the inverter is configured to run PF P or Q U it will display Constant PF or Constant Q respectively 0 Setpoint type Off 0 Value The real time value of the setpoint for reactive power the unit depends on the selected setpoint type 0 Inverter 0 Country Germany 0 Grid Medi
102. r temperature 3 Grid overvoltage 4 Grid overfrequency 5 External command PLA feature 1 See 9 Ancillary Services Derating is accomplished by adjusting the PV voltage and subsequently operating outside the maximum power point of the PV arrays The inverter continues to reduce the power until the potential overload ceases or the PLA level is reached The total amount of time the inverter has derated can be seen in the display Log gt Derating security level 1 Derating due to PV current or grid power indicates that too much PV power has been installed whereas derating due to grid current grid voltage and grid frequency indicate issues with the grid See 9 Ancillary Services for more information During temperature derating the output power may fluctuate by up to 1 5 kW 1 PV Over current The inverter will move PV voltage until current reaches 12 A max If 12 A max is exceeded the inverter disconnects from the grid 2 Internal Over temperature Derating due to temperature is a sign of excessive ambient temperature a dirty heatsink a blocked fan or similar Refer to 10 2 Maintenance for advice 14 L00410320 07_02 i Description of the Inverter Pnom A Pnom lt L xt 1 0 S 1 0 S 0 9 0 94 0 8 0 8 0 7 0 7 0 6 0 54 Ogi 08 09 10 11 12 go 0 3 Illustration 2 6 Grid Voltage Lower than Unom 0 2 0 1 agra 15 30 45 60 t C Illustration 2 4 Derating Temp
103. rective cst MPP Maximum power point MPPT Maximum power point tracking ESD Electrostatic Discharge Introduction Abbreviation Description P P is the symbol for active power and is measured in Watts W PCB PCC Point of common coupling The point on the public electricity network to which other customers are or could be connected PE PLA Pnom POC Point of connection The point at which the PV system is connected to the public electricity grid Pstc PV RCMU Riso ROCOF RTC Q Q is the symbol for reactive power and is measured in reactive volt amperes VAr S S is the symbol for apparent power and is measured in volt amperes VA STC w THD Total Harmonic Distortion TN S Terre Neutral Separate AC Network NC TN C S Terre Neutral Combined Separate AC Network T Table 1 3 Abbreviations 1 4 Software Version Always read the newest version of this manual This manual is applicable for inverter software 2 0 and onwards To see the software version go to e via the display Status gt Inverter gt Serial no and SW ver gt Inverter via the web interface Inverter level Status gt Inverter gt Serial no and SW ver gt Inverter 1 5 Related Literature TLX Series Installation Manual e TLX Series User Manual e TLX Series Web Server User Manual e Weblogger Manual e CLX Series Quick Guides and User Manuals GSM Manual Denpi For more information go t
104. rement of the resistance between the PV arrays and earth Meanwhile it also monitors the grid parameters When the grid parameters have been within the specifications for the required amount of time depends on grid code the inverter starts to energise the grid On grid Green LED on The inverter is connected to the grid and energises the grid The inverter disconnects if It detects abnormal grid conditions depending on grid code if an internal event occurs or if no PV power is available no power is supplied to the grid for 10 minutes It then goes into connecting mode or off grid mode Fail Safe Red LED flashing If the inverter detects an error in its circuits during the self test in connecting mode or during operation the inverter enters fail safe mode disconnecting from PV The inverter will remain in fail safe mode until PV power has been absent for a minimum of 10 minutes or the inverter has been shut down completely AC and PV Refer to 10 1 Troubleshooting for further information 2 3 3 International Inverter The inverter is equipped with a range of grid codes to meet national requirements Before connecting an inverter to the grid obtain approval from the local distribution network operator DNO For initial selection of grid code refer to 7 4 Start up and Check of Settings View the current grid code setting e via the display at Status gt Inverter via the web interface at Inverter level St
105. rter L00410320 07_02 95 Appendix A Event List Event ID 25 27 Display Text Description LOM_LINETOLINE_LOW_L1 End user Phase to phase LOM_LINETOLINE_LOW_L2 Call the installer and inform about the voltage on all three phases voltages too low LOM_LINETOLINE_LOW_L3 e Voltages are OK Wait 10 minutes to see if the inverter reconnects to the grid If the event reappears on site service is needed Installer Check the AC installation all fuses and the RCD e OK call service Service Exchange the inverter Event ID 28 30 Display Text Action Description LOM_ROCOF_HIGH_L1 End user Rate Of Change Of LOM_ROCOF_HIGH_L2 If the event reoccurs several times each day contact the DNO Frequency ROCOF LOM_ROCOF_HIGH_L3 Installer too high None Service None Event ID Display Text Action 31 33 44 46 Description IGRID_DC_CURRENT_HIGH_L1S1 End user DC grid current too IGRID_DC_CURRENT_HIGH_L2S2 Check SW version Status high IGRID_DC_CURRENT_HIGH_L3S3 e If SW version 2 15 1 12 or older a SW update is required Call the IGRID_DC_CURRENT_HIGH_STEP_L1 installer IGRID_DC_CURRENT_HIGH_STEP_L2 IGRID_DC_CURRENT_HIGH_STEP_L3 Installer Install newest SW version Service None Event ID 34 37 Display Text Action Description IRESIDUAL_HIGH End user Residual Current IRESIDUAL_STEP_S3_HIGH Turn both DC and AC off and wait until the display turns off Then turn on Monitoring Unit IRES
106. rter has limited power production due to grid power eriod of time the inverter has limited power production due to PV current eriod of time the inverter has limited power production due to excessive temper eriod of time the inverter has limited power production due to frequency support m m y visible if enabled by the current grid code L00410320 07_02 59 User Interface Display Functions 0 Pwr level adjust 0 h 0 Reactive Power 0 h 0 Reactive Power 0 Reactive Energy underexcited 1000 000 VArh 0 Reactive Energy overexcited 1000 000 VArh 0 Event log 0 Latest event 0 0 Last 20 events 0 1 29 01 2009 14 33 28 0 Grid 29 off 0 2 29 01 2009 14 33 27 0 Grid 29 on 0 20 Table 7 5 Menu Structure Production Log 7 1 5 Setup Description Period of time the inverter has limited power production due to Power level adjustment Only visible if enabled by the current grid code Due to reactive energy support Only visible if the current grid code is an MV country or custom and in TLX and TLX Pro variants Display Functions 0 Relay 0 Function Alarm 0 Stop Alarm 0 Test Alarm Description Set relay functionality to either Alarm or Self consumption Default setting of Function Stop alarm 0 Alarm state Disabled 0 Alarm time out 60 s 0 Function Self consumption 0 Power level 0 Duration 0 Trigger
107. s not covered Clean the contacts of the PV load switch once per year Perform cleaning by cycling the switch to on and off positions ten times The PV load switch is located at the base of the inverter 10 2 1 Cleaning the Cabinet Clean the inverter cabinet using pressurised air a soft cloth or a brush 10 2 2 Cleaning the Heatsink Clean the heatsink using pressurised air a soft cloth ora brush For correct operation and long service life ensure free air circulation around the heatsink at the rear of the inverter to the fan at the inverter base AWARNING Do not touch the heatsink during operation Temperature can exceed 70 C L00410320 07_02 83 i Technical Data 11 Technical Data 11 1 General Data Nomenclat Parameter TLX Series TLX Series TLX Series TLX Series TLX Series ure 6k 8k 10k 12 5k 15k AC s 10000 VA Active power at cos phi Active power at cos phi Vacs 3P N PE 230 V 400 V 20 AC current distortion THD cosphiac r Power factor at 100 load Controlled power 0 8 over excited 0 8 under excited Power loss Connecting mode a Night time power loss off a p lt 5W f 50 Hz E5 HZ per MPPT P mpptmax Max nom converted PV input power 6200 W 8250 W 10300 W 12900 W 15500 W Vmppmin MPP voltage nominal Vmppmax power 260 800 V 345 800 V 430 800 V 358 800 V 430 800 V 99 9 99 7 saa Min on grid power 20 W Effi
108. stration 9 5 TLX TLX with CLX monitoring and grid management products or third party external device Based on the input from a DNO signal interface an CLX monitoring and grid management products or third party VY 150AA079 10 ooo 0 ES a a ee ae Raas TO Illustration 9 6 Example Managing Power Using CLX Monitoring and Grid Management Products or Third party External Device 1 DNO interface radio receiver Configuration 2 CLX monitoring and grid management product or third party To configure remotely controlled output power access at device security level 1 is required Table 9 4 Legend to Illustration 9 6 78 L00410320 07_02 Ancillary Services Remotely controlled output power is configured in the CLX monitoring and grid management product or third party device See manual for CLX product or third party party device e For TLX Pro TLX Pro via the web interface navigate to Inverter level Setup gt Grid Management 9 5 Reactive Power Control The TLX and TLX Pro inverters support reactive power control which is used to control the reactive output power of the inverter The control methods of the reactive output power are described below During Stand by and Off grid the control functions for reactive power cannot be in operation which results in exchange of reactive power in Stand by mode from LCL and EMC fi
109. t local MPP Only one of the points is the true global maximum power point global MPP Using PV sweep the inverter locates the global MPP rather than just the local MPP The inverter then maintains production at the optimum point the global MPP 16 L00410320 07_02 Description of the Inverter Poc W A 150AA037 11 Illustration 2 8 Inverter Output Power W versus Voltage V 1 Fully irradiated solar panels Global MPP Partly shaded solar panels Local MPP Partly shaded solar panels Global MPP Cloudy conditions Global MPP Table 2 9 Legend to Illustration 2 8 PV sweep functionality comprises two options for scanning of the entire curve e Standard sweep regular sweep at a pre programmed interval e Forced sweep Standard sweep Use standard sweep to optimise yield when there are permanent shadows on the PV panel The characteristic will then be scanned at the defined interval to ensure production remains at the global MPP Procedure Plant level In the web interface 1 Go to Plant level Setup gt PV Sweep gt Sweep type Select Standard sweep 2 Go to Plant level Setup gt PV Sweep gt Sweep interval Enter the desired sweep interval in minutes Inverter level In the web interface Dafoe 1 Go to Inverter level Setup gt PV Sweep gt Sweep type Select Standard sweep 2 Go to Inverter level Setup PV Sweep Sweep interval Enter
110. ter Overview Chapter Content 2 9 11 Functions and specifications of the inverter 3 4 11 Pre installation and planning considerations 5 6 Installation of inverters and peripheral units 7 Local setup and monitoring of the inverter Refer to this chapter for information on obtaining access 8 9 Ancillary service features for grid support 10 Maintenance 12 Troubleshooting and events Table 1 1 Chapter Overview Functional safety and grid management parameters are password protected L00410320 07_02 1 2 List of Symbols Symbol Explanatory note Italics 1 Indicates reference to a section of the present manual 2 Italics are also used to indicate an operation mode e g operation mode Connecting 1 Encloses a path of menu navigation 2 Also used to enclose abbrevi ations such as kW Plant Menu item accessible at plant level Group Menu item accessible at group level or above Inverter Menu item accessible at inverter level or above gt Indicates a step within menu navigation 5 Note useful information I Caution important safety e information used in text E Name of plant group or inverter in sms or e mail message eg plant name Site Map Symbol b Indicates a submenu x Defines current security level where x is between 0 3 Table 1 2 Symbols 1 3 List of Abbreviations Abbreviation Description cate DHCP DNO DSL EMC Di
111. th TLX Series 12 5k Max recommended cable length TLX Series 15k DC Cable length Cable length Mating connector Table 4 3 Cable Requirements NOTE 18 25 mm 2 5 mm 21m Po Max 1000 V 12 A 4mm 48 0 km 6 mm 3 4 Q km gt 200 300 m PV ADSP4 PV ADBP4 The distance between inverter and PV array and back plus the cumulative length of PV array cabling Avoid power loss in cables greater than 1 of nominal inverter rating 2 150AA044 11 Illustration 4 1 TLX Series 6k Cable Losses versus Cable Length m 24 L00410320 07_02 Requirements for Connection 150AA045 11 m Illustration 4 2 TLX Series 8k Cable Losses versus Cable Length m 2 S lt L 80 m Illustration 4 3 TLX Series 10k Cable Losses versus Cable Length m L00410320 07_02 25 Requirements for Connection S z m Illustration 4 4 TLX Series 12 5k Cable Losses versus Cable Length m 5 2 3 1 5 4 1 a 0 5 0 m Illustration 4 5 TLX Series 15k Cable Losses versus Cable Length m Consider also the following when choosing cable type and proper cable dimensions are used to avoid losses cross sectional area Additionally the no load voltage at the connection point must be taken into account The maximum permitted grid ae i imp
112. this chapter before designing the PV system It provides information required for planning integration of TLX Series inverters into a PV system e AC grid connection requirements including choice of AC cable protection e PV system design including earthing Ambient conditions such as ventilation 4 2 Requirements for AC Connection CAUTION Always follow local rules and regulations ACAUTION Prevent the system from reconnecting secure the work area by marking closing or locking off the area Uninten tional reconnection may result in severe accidents ACAUTION Cover up all voltage carrying system components that may cause personal injury while working Make sure that danger areas are clearly marked The inverters are designed with a three phased neutral and protective earth AC grid interface for operation under the following conditions Parameter Nominal Min Max 276 V 50H 0 Grid voltage phase 230 V 184V neutral 20 Table 4 1 AC Operating Conditions When choosing grid code the parameters in the above specification will be limited to comply with the specific grid codes Earthing systems The inverters can operate on TN S TN C TN C S and TT systems NOTE Where an external RCD is required in addition to the built in RCMU a 300 mA RCD type B must be used to avoid tripping IT systems are not supported NOTE When using TN C earthing to avoid earth currents in the communication
113. tic reactive Ratio between additional reactive current grid code power k to be injected during the FRT and the depth of the sag k Alg In AU U 2 0 p u Transition time Duration of period after the sag has cleared where reactive current is still injected Table 9 2 Parameters related to FRT In addition to remaining on grid during the fault the inverter can deliver reactive current to support the grid voltage 76 L00410320 07_02 Ancillary Services 9 4 Active Power Control The inverter range supports active power control which is used to control the active output power of the inverter The control methods of the active output power are described below 9 4 1 Fixed Limit To ensure that the PV system is not producing more power than allowed the output power can be limited to a fixed upper amount set as e Absolute value W e Percentage based on total installed PV power e Percentage based on nominal AC output power Configuration To configure fixed limits security level 1 is required e For all TLX inverters via the display navigate to Setup gt Grid management gt Output power limit e For TLX Pro TLX Pro via the web interface navigate to Inverter level Setup gt Grid Management e For TLX TLX via the service interface navigate to Inverter level Setup gt Grid Management 9 4 2 Dynamic Value The output power is reduced as a variable of the grid frequency
114. time 0 Setup details 2 Country Germany 2 Grid Medium voltage 2 Safety affecting settings 2 10 min mean voltage 2 ROCOF 1 PV Configuration 1 Mode Automatic 1 PV input 1 Automatic 1 PV input 2 Automatic 1 PV input 3 Automatic 1 Force inverter power up Includes testing red LED on front Alarm time limit If 0 the alarm will be active until fixed Minimum level to activate self consumption Duration of power level to activate self consumption Hour of day to activate self consumption Settings that have influence in functional safety 2 Avg voltage limit 253 V Upper 10 min average voltage limit Maximum amount of time before the inverter must disconnect from the grid 2 Time to disconnect 200 ms due to too high avg voltage ROCOF Rate of Change of Frequency 2 Time to discon 1000 ms See 5 6 Parallel PV String Configuration May be changed to Manual if the automatic PV configuration is to be overridden Turns on grid supply to CTRL board 60 L00410320 07_02 User Interface Display Functions 0 Inverter details 0 Inverter name Danfoss 0 Group name 0 Group 1 0 Master mode 0 Master mode Enabled 0 Network 0 Initiate network scan 0 Scan progress 0 0 Inverters found 0 0 Plant name plant name 1 Reset max values Description The inverter s name Max 15 characters Max 15 characters and not only numbers The
115. tion Description eModemParseM odel End user Call the installer Installer Replace modem Service None L00410320 07_02 107 Appendix A Event List Event ID 23 Label GSM LAN Action Description eModemParseRvsn End user Failed to parse modem Call the installer revision Installer Replace modem Service None Event ID 24 Label GSM LAN Action Description eModemParseRSSI End user Failed to parse modem Call the installer RSSI Installer Replace modem Service None Event ID 26 Label GSM LAN Action Description eModemSecurityNotPIN End user SIM card requests a This SIM card is blocked Find the PUK code insert the SIM into a code but it is not PIN mobile phone and unblock it Try a different provider commonly PUK Installer because SIM is locked None Service None Event ID 27 Label GSM LAN Action Description eModemParsePINStatus End user Failed to parse Reset the inverter by disconnection If the event persists call the response to pin status installer query Installer Call service Service Report the error Event ID 28 Label GSM LAN Action Description eModemParseNe End user Failed to parse tRegStat Power cycle the inverter response to network Installer registration status Replace modem If that does not help call service query Service provider Report the error Event ID 29 Label GSM LAN Action Description eUnexpecte
116. transistor or wrong PV polarity Display Text SELF_TEST 4 6 SHORT CIRCUIT Action End user Call the installer Installer Call service Service Exchange the inverter Event ID 262 Description Short circuited booster transistor or wrong PV polarity Display Text SELF_TEST 4 6 SHORT_CIRCUIT_WRO NG_POLARITY Action End user Call the installer Installer Check the PV installation for polarity errors If OK exchange the inverter Call service Service Exchange the inverter Event ID 263 Description Internal software error Display Text INTERNAL_ERROR Action End user Check event log to see if this is logged more than once per day e If no no action required e If yes call the installer Installer Update software to latest version Service Exchange the inverter Event ID 350 Description DC bias in RCMU is too high during self test Display Text SELF _TEST 4 5 DC BIAS FAILED 102 Action End user Call the installer Installer Call service Service Exchange the inverter L00410320 07_02 Appendix A Event List Event ID 351 Description DC bias in RCMU is too high during self test Display Text SELF _TEST 4 5 RMS BIAS FAILED End user Call the installer Installer Call service Service Exchange the inverter Event ID 352 Description RCMU cannot detect step of 25 mA in residual current Display Text S
117. try to send email Possible cause lack of credit Try different SIM cards Installer Call service Service Report the error L00410320 07_02 Danfoss Solar Inverters A S Ulsnaes 1 DK 6300 Graasten Denmark Tel 45 7488 1300 Fax 45 7488 1301 E mail solar inverters danfoss com www danfoss com solar Danfoss can accept no responsibility for possible errors in catalogues brochures and other printed material Danfoss reserves the right to alter its products without notice This also applies to products already on order provided that such alterations can be made without subsequential changes being necessary in specifications already agreed All trademarks in this material are property of the respective companies Danfoss and the Danfoss logotype are trademarks of Danfoss A S All rights reserved Rev date 2012 11 25 Lit No L00410320 07_02
118. two independent circuits the inverter ceases to energise the grid and repeats the self test The functional safety circuits are always activated and cannot be disabled Grid Surveillance The grid is under constant surveillance when the inverter energises the grid The following parameters are monitored e Grid voltage magnitude instantaneous and 10 minute average e Grid voltage frequency e Three phase Loss of Mains LoM detection e Rate of Change of Frequency ROCOF e DC content of grid current e Residual Current Monitoring Unit RCMU The inverter ceases to energise the grid if one of the parameters violates the grid code The insulation resistance between the PV arrays and earth is also tested during the self test The inverter will not energise the grid if the resistance is too low It will then wait 10 minutes before making a new attempt to energise the grid The inverter has four operation modes For information on LEDs refer to 7 1 Integrated Display Unit Off grid LEDs off When no power has been delivered to the AC grid for more than 10 minutes the inverter disconnects from the grid and shuts down This is the normal night mode The user and communication interfaces are still powered for communication purposes Denpi Connecting Green LED flashing The inverter starts up when the PV input voltage reaches 250 V The inverter performs a series of internal self tests including PV auto detection and measu
119. um voltage 1 DC bus voltages 1 Upper 400 V 1 Max upper 500 V 1 Lower 400 V 1 Max lower 500 V 0 Internal Conditions 0 Power module 1 100 C Temperature detected at the power module 56 L00410320 07_02 User Interface Display Functions 1 Power module 2 100 C 1 Power module 3 100 C 1 Power module 4 100 C 0 PCB 1 Aux 100 C 1 PCB 2 Ctrl 100 C 1 PCB 3 Pow 100 C 0 Fan 1 6000 RPM 1 Fan 2 6000 RPM 1 Fan 3 6000 RPM 1 Fan 4 6000 RPM Description Speed of the fan 1 Max values 1 Power module 1 100 C 1 Power module 2 100 C 1 Power module 3 100 C 1 Power module 4 100 C 1 PCB 1 Aux 100 C 1 PCB 2 Ctrl 100 C 1 PCB 3 Pow 100 C 0 Serial no and SW ver 0 Inverter 0 Prod and serial number 0 123A4567 0 123456A789 0 Software version 0 MAC address 0 0 Control board 0 Part and serial number 0 123A4567 0 123456A789 0 Software version 1 Operating time 1h 0 Power board 0 Part and serial number 0 123A4567 0 123456A789 Inverter product number Inverter serial number Inverter software version Control board part number Control board serial number Control board software version Power board part number Power board serial number 1 Operating time 1h 0 AUX board 0 Part and serial number 0 123A4567 0 123456A789 1 Operating time
120. vice is needed Wait 10 minutes on phase L1 L2 and or L3 to see if the inverter reconnects to the grid S1 STAGE 1 Installer S2 STAGE 2 Check the AC installation L1 PHASE 1 e Check all fuses and the RCD RCMU L2 PHASE 2 L3 PHASE 3 All OK call service Service Exchange the inverter Event ID 7 9 Display Text Action Description UGRID_RMS_10MINAVG_HIGH_L1 End user Grid voltage average UGRID_RMS_10MINAVG_HIGH_L2 Call the installer and inform about the grid phase voltage over 10 min too high UGRID_RMS_ 1OMINAVG_HIGH_L3 e Voltage on corresponding phase is OK Wait 10 minutes on phase L1 L2 and or L3 to see if the inverter reconnects to the grid If the event reappears on site service is needed Installer Mitigation possibilities e Install cable of larger diameter to reduce the voltage drop between inverter and meter e Program PF P TLX and TLX Pro only e Call DNO to get permission to increase limit note Ugrid_RMS_ high Use installation tester to test resistance in the installation phase neutral Service None 94 L00410320 07_02 Appendix A Event List Event ID 10 15 Description Grid voltage too high Display Text UGRID_RMS HIGH S1_L1 UGRID_RMS HIGH Sl _L2 UGRID_RMS HIGH _S1_L3 UGRID_RMS HIGH_S2_L1 UGRID_RMS HIGH S2_L2 UGRID_RMS HIGH_S2_L3 S1 STAGE 1 S2 STAGE 2 L1 PHASE 1 L2 PHASE 2 L3 PHASE 3 Action End user Call the install
121. wer Q v 11 1 10 0 4 8 kVAr Configuration To configure constant reactive power access at security level 1 is required To configure the setpoint of Q or PF navigate to e Via the web interface Plant level Setup gt Grid Management e Via the service web interface Inverter level Setup gt Grid Management e Via the display Inverter level Setup gt Grid Management 9 5 2 Dynamic Value The dynamic reactive control requires either a TLX inverter with CLX monitoring and grid management product or third party device or a TLX Pro inverter Setpoint curve PF P The PF P curve is either pre configured in each inverter via the selected grid code or configured manually in the web interface The PF P control is thus operating on inverter level measuring the output power of the unit and delivering reactive power accordingly L00410320 07_02 79 Ancillary Services i 150AA076 10 CNS Illustration 9 7 Setpoint curve PF P Ethernet NS 1 Active output power measurement Table 9 5 Setpoint curve Q U The inverter controls reactive power as a function of the grid voltage U The values for the setpoint curve are Ja determined by the local utility company and must be obtained from them The Q U curve is configured on plant level The master measures grid voltage and determines and delivers reactive P Q accordingly
122. x in inverter H cid 4 identical Table 4 13 Legend to Table 4 12 When total input current exceeds 12 A external splitter is required 4 in parallel Required Splitter Splitter output output optional 3 in parallel Optional Splitter Splitter 1 in series output output L00410320 07_02 33 Requirements for Connection 12x4 mm w Ww rN a2593 aZ250 5 Illustration 4 9 PV System Example 7 Illustration 4 9 PV System Example 8 Table 4 14 PV System Examples 7 8 Example C Internal parallel connection in inverter Required 2 strings via 1 string 1 string Y connector External parallel connection String Connection point B capacity A Inverter External orientation Generator splitter Pk 4 identical and connectio Pot Table 4 15 Legend to Table 4 14 inclination n box When total input current exceeds 12A external splitter is required Inverter inputs 6 identical 34 L00410320 07_02 Requirements for Connection PV Cable Dimensions and Layout The power loss in the PV cables should not exceed 1 of nominal value in order to avoid losses For an array of 5000 W at 700 V this corresponds to a maximum resistance of 0 98 Q Assuming aluminium cable is used 4 mm gt 4 8 Q km 6 mm gt 3 4 Q km the maximum length for a 4 mm cable is approximately 200 m and for a 6 mm cable approximately 300 m
123. xample in e Compensation for inductive loading by injection of capacitive reactive power e Voltage control To compensate for this a generator exchanging reactive power operates either at a lagging power factor also known as over excited or at a leading power factor also known as under excited The technical definition of reactive power Active power P measured in Watts W Reactive power Q measured in volt ampere reactive VAr Apparent power S is the vector sum of P and Q and is measured in volt ampere VA is the angle between current and voltage and thus between P and S NA 150AA054 11 Q VAr p P W Illustration 9 1 Reactive Power In the inverter the reactive power is defined either as Q The amount of reactive power as a percentage of the nominal apparent power of the inverter PF Power Factor The ratio between P and S P S also referred to as Cos Displacement Power Factor at fundamental frequency 74 L00410320 07_02 Ancillary Services 9 2 Ancillary Services Overview The following table outlines the individual ancillary services TLX TLX TLX Pro TLX Pro Danfoss Grid management Remotely controlled active CLX Home GM2 CLX GM4 power PLA CLX Standard GM CLX Home GM CLX Standard GM3 Remotely controlled reactive CLX Home GM CLX GM4 power CLX Standard GM3 CLX Home GM CLX Standard GM3 Dynamic reactive power v Dynamic reactive power Q
124. y and the alarm will sound continuously While the alarm is active it may be stopped at any time To stop the alarm go to Setup Relay and select Stop alarm 64 L00410320 07_02 User Interface e Stop alarm e Test alarm e Alarm state e Alarm time out The alarm is activated by any of the following events Event ID Description 40 The AC grid has been out of range for more than 10 minutes 115 The insulation resistance between ground and PV is too low This will force the inverter to make a new measurement after 10 minutes 233 240 Internal memory error 241 242 Internal communication error 243 244 251 The functional safety processor has reported Fail safe 350 364 An internal error has set the inverter in Fail safe Table 7 7 Activation of Alarm Self consumption By default the self consumption functionality is disabled To enable self consumption go to Setup Relay Function and select Self consumption Once enabled the self consumption functionality is activated by output power level or a time of day Set up the conditions for activation as follows e Output power level Set Power level to the desired minimum output power level for activation of self consumption The default value of Power level is 3000 W Set the Duration period Self consumption will activate when output exceeds the minimum power level for the period defined in Duration

Download Pdf Manuals

image

Related Search

Related Contents

E 103 User Manual PDF    Samsung CTR164NC01 Korisničko uputstvo  Untitled - Epralima    formacion  Focal S 700  

Copyright © All rights reserved.
Failed to retrieve file