Home
        FORMAT FOR SENDING COMMENTS Document No.: Doc WRD 16
         Contents
1.    5 7 3 Vertical routing of cable    In some embankment dams vertical routing of signal cables from sensors should be avoided as far  as possible  However  in some cases  vertical routing of cable is convenient or unavoidable  In  such cases the cables should be routed vertically only through the filter  Figure 7 schematically  shows preferred method for vertical routing of instrumentation cables through the filter     5 8 Cable Care    Cable problems are a common cause of bad data in geotechnical measurement programs   Following precautions should be taken to reduce the chances of cable damage in the project     1  Cable should be protected from sharp objects  which can cut through the jacket and into the  conductors  If the cable has to be buried  fine sand or clay should be used as the burial  material  not rocks or sharp stones  If this is not possible  the cable should be protected by  enclosing it in conduit     2  To prevent tension of buried cable resulting from ground settlement  the cable should be  routed with a zig zag pattern  A horizontal zig zag of 0 5m in every 15m may be provided     3  If multiple cables are routed in the same trench  they should be separated by 25mm or more   Crossing of cables should be avoided     4  Cables should be tagged at regular intervals to make for easv identification in the field     5  Cables should be kept awav from chemical solvents  as certain solvents can attack the plastic  jacket and insulation     R ock fill    Graded ma
2.    e                          4 100 min  drill hole    All dimensions in millimetres     Fig  4 Typical installation of piezometer in foundation of dam  5 4 Grouted Borehole Installation  Certain situations may require the boreholes to be grouted after the installation of the piezometers   A grouted borehole installation requires that the total depth of the hole be drilled to one meter past  the planned piezometer installation depth  The following installtion procedure should be followed   1  Flush the borehole with water or biodegradable drilling mud   2  Tie piezometer to signal cable in the filter end up orientation   3  Lower piezometer into borehole  Add additional weight  sand bag  if necessary   4  Completely fill remaining borehole with bentonite cement grout mixture  The requirement of the    grout mix is that it should have the same stiffness as the surrounding ground  For guidance  typical mixes for hard and medium soils and soft soils are given in Table 1     5  Mark piezometer cable at surface with stake or flag  Terminate wires and connect to Vibrating   Wire Readout  The weatherproof Vibrating Wire Readout mav not need anv further protection  from the elements     6  Begin to collect periodic readings  Initial pressure readings will be high  Continue to evaluate  readings as installation stabilizes  Installation stabilization is contingent on local conditions   including soil permeability  Complete datum readings after installation stabilizes  this period  can 
3.   its air goes out and it gets saturated with water  Allow the water to cool down to the room  temperature     5                    ue    UONJEJUSWNIJJSUI JO                       y z 614    00 08 JOVNIVHO NO 901        LY WOOH 10H1NOO NI  SVQ    14           TIM 3782 3409 3409      V XOU HOLIMS HOW               NOLLVLS NOILVAH3S8O AHVHOGW3L NI 031  007        HOLIMS  O1 Q3103NNOO             1          1      HOYI WOH4 318V9 3802        S3LON                                        SVQ    gS                    6109 04    88 0105U8S        BJQEJ 8409 b ATA  007211 1v  15  NOLLVAS 5    00 SLL 13 LY NVId            235                                                  WNO               uonisod o1                        AHVHOGWAL ext              318VO       edy 005  jejeuiozeid                 4                                          Bd 00     7ejeujozeid                           i 4           00                                                  f LUE     TAT 2169 4          26           L             einsseid jos          LI                 Ea  NOILdIHOS3Q          gt                               jo    210  a JN3IWMNVSW3  sixy WYG  NOILOAS 55040 WVA GHLNAWNALSNI  IVOIdAL  00 06  21644         S318VO JHO9 9               Ql  a9 to         EM  ANIAN       6    00 021   151  NOLLVLS NOLLVAH3S8O AHVHOdW3L   251          15 NOILVAH3S80 AHVHOdW3L ji  a B 00 0EL           TOHINO9 01 251 9 ISLWOH4     dvii dIH MOT38    1  318  0 3H09 0  33HHL  REL                        IA        ea
4.  a bentonite seal over the installation to isolate the piezometer  Continue to build the  embankment over the piezometer     Continue to protect the cable from sharp bends along its path  Avoid crossing cables  If  necessary to cross cable paths  isolate cables with fill material between them     Bury cable using fine embankment materials  compacting lightly  Continue process creating  layers over the cable until it is covered with at least 0 5 meters of material  Use only light  tamping equipment     Build water stops as specified     Mark piezometer cable at surface with stake or flag  Terminate wires and connect to Vibrating   Wire Readout     Start to collect periodic readings  Initial pressure readings typically will be high  Continue to  evaluate readings as installation stabilizes  Installation stabilization is contingent on local  conditions  including soil permeability  Complete datum readings after installation stabilizes   this period can be hours or days depending on local conditions     5 7 Laying of cables    5 7 1 General precautions    Careful and skilled cabling is required in installation of piezometer as sensor cable joint and a  large part of cable is permanently embedded and no future access is available for any  maintenance and corrective action     The procedure for laying cable differs with individual installations  In general  however  all  installations have the following common requirement     a     b     c     d     e     Cable should be protected 
5.  compacted earth i  fill in main trench 450  i     o  LO     Embankment soil         2  Selected fine material M MEAN Y  Cables    0    el ki    ol       EN D  C C All dimensions in millimetres      Cross sections A A  B B  C C     Fig  5 Typical installation of piezometer in embankment of dam    b  Material around sensor should be placed bv hand shovel and compacted with a light dutv  pneumatic or petrol backfill tamper  First laver of material over sensor should be around 250  mm high and compacted                 Similar lavers of material should be put over this and  compacted properly until at least 500 mm of material has been placed  Rubber tyre  equipment can cross the location  but no vibratory rollers should be permitted over the sensor  until a compacted thickness of at least 1 m is laid            cable trench around 400   800 mm wide and upto 500 mm deep is dug along the offset  trenches  as shown in figure 4 and figure 5  Depth and width depends upon number of cables  trench has to carry  Based upon cable layout design  the trench runs into abutment and then  along abutment to downstream side or directly to downstream side towards observation  room  These cable trenches carry the individual cables from piezometers to observation  room     d  Before laying cables  trench should be properly cleaned and leveled with 30 mm of fine sand  at bottom of trench along the path  Any sharp rocks should be removed to prevent cable from  accidentally getting damaged  Centre di
6.  of  significant places retained in the rounded off value should be the same as that of the specified  value in this standard     TABLE OF CONTENTS  0  FOREWORD  1  SCOPE    2  VIBRATING WIRE PIEZOMETERS  2 1 OPERATING PRINCIPLES    2 2 ACCESSORIES  2 2 1 HOUSING  2 2 2 THERMISTOR    2 3 CABLE   2 4 CABLE IDENTIFICATION TAGS  2 5 JUNCTION CUM SWITCH BOX  2 6 CABLE SPLICING KIT   2 7 READ OUT INDICATOR    3  TVPICAL INSTRUMENTATION SCHEME    4  VERIFICATION AND CALIBRATION  4 1 BOIL THE FILTER  4 2 REASSEMBLE THE PIEZOMETER  4 3 QUICK ZERO CHECK  4 4 DOWNHOLE PRESSURE CHECK    5  INSTALLATION  5 1 SATURATING FILTER  5 2 INSTALLING PIEZOMETERS USING SAND  5 3 INSTALLING PIEZOMETERS IN FOUNDATIONS USING SAND  5 4 GROUTED BOREHOLE INSTALLATION  5 5 IN SITU OR PUSH IN INSTALLATION  5 6 EMBANKMENT INSTALLATION    5 7 LAVING OF CABLES  5 7 1 GENERAL PRECAUTIONS  5 7 2 CABLE TRENCHES  5 7 3 VERTICAL ROUTING    5 8 CABLE CARE    6  TAKING READINGS  6 1 INITIAL READINGS  6 2 TAKING OF READINGS    7  CONVERTING FREQUENCY INTO PRESSURE  7 1 TRANSDUCER CONSTANT  7 2 PRESENTATION OF DATA    8  TEMPERATURE CORRECTION    1  SCOPE    This standard covers details of installation  maintenance and observation of Vibrating Wire type  pore water pressure cells for earth and rock fill dams     2  VIBRATING WIRE PIEZOMETERS   2 1 Operating Principle   The vibrating wire piezometer contains a magnetic  high tensile strength stretched wire  one end  of which is anchored and the other end fixed to a di
7.  taking readings as piezometer is  pushed into the borehole bottom  Ensure that pressures do not exceed the maximum range   capacity  of the piezometer shown on the calibration certificate  If pressure exceeds this  maximum  slow or halt the piezometer push in until the excess pressure dissipates     4  Detach drill rod   5  Completely fill remaining borehole with bentonite cement grout mixture     6  Wait for pressure readings to stabilize  Excessive porewater pressure caused by the push in is  typical immediately after installation  Installation of a bentonite cap may cause a reverse  pressure effect as the bentonite draws water away from the piezometer     7  Mark piezometer cable at surface with stake or flag  Terminate wires and connect to Vibrating   Wire Readout     8  Start to collect periodic readings  Initial pressure readings typically will be high  Continue to  evaluate readings as installation stabilizes  Installation stabilization is contingent on local  conditions  including soil permeability  Complete datum readings after installation stabilizes   this period can be hours or days depending on local conditions     11    56 Embankment Installation    The following installation procedure should be followed for the piezometers that will be installed in  an embankment as it is being constructed     1     Form a shallow horizontal trench or slot for the piezometer  Carefully place the piezometer into  the trench  Avoid kinking the cable during installation     Place
8. FORMAT FOR SENDING COMMENTS  Last Date for Comment is 31 December 2009    E Mail ID for sending comments  rrdash bis org in       Document No   Doc WRD 16  504 C       Title  CODE OF PRACTICE FOR INSTALLATION  MAINTENANCE AND OBSERVATION OF  INSTRUMENTS FOR PORE PRESSURE MEASUREMENT IN EARTH AND ROCKFILL DAM      VIBRATING WIRE TYPE ELECTRICAL PORE PRESSURE CELL  First Revision of IS 12949        Organization  Individual           Clause  Retin  SI   Sub clause Comments  N        General  PR Proposed Change  o     UESTRE   Technical     Justification For Change   igure Table   Editorial                                      FOR COMMENTS ONLV DOC  WRD 16  504  C  OCTOBER 2008    BUREAU OF INDIAN STANDARDS    Draft  Indian Standard    CODE OF PRACTICE FOR INSTALLATION  MAINTENANCE AND OBSERVATION OF  INSTRUMENTS FOR PORE PRESSURE MEASUREMENT IN EARTH AND ROCKFILL DAM      VIBRATING WIRE TVPE ELECTRICAL PORE PRESSURE CELL  First Revision of IS 12949     ICS No  93 160     Not to be reproduced without the permission of BIS or used as standard     FOREWORD   Formal clauses of the foreword will be added later     The soil mass is composed of solid soil particles and voids filled with water and air  The  constructed embankment will alwavs contain a certain volume of air and water within the voids   The air is compressible while water is highly incompressible  Hence when embankment settles  due to compaction by rolling  or due to self weight  the void space contract  This causes press
9. INSTRUMENTATION SCHEME    A typical instrumentation scheme of an earth dam is shown in Figure 2  The cables have been  routed to the downstream side in temporary observation rooms and will be connected later on to a  central data acquisition system on the top of the dam     Note1  The arrangement shown for cable routing in figure 2 is typical for an earth fill dam and is not to be  universally used  Various methods of cable routing are used depending upon the location  size and the  design of the dam  The designers and the consultants are the best people to determine the layout for cable  routing from the sensors to the observation room     4  VERIFICATION AND CALIBRATION    The main purpose of a verification test is to provide reasonable assurance that a sensor is  functioning properly  Unless there is access to sophisticated test facilities and calibration  equipment  acceptance tests may not be expected to achieve the accuracy and precision of the  calibration data provided on the sensor calibration record  Thus during evaluation of the results of  an acceptance test  look for obvious non conformance rather than an exact match between the  data and the data on the calibration record     Each piezometer should be verified and calibrated before it is installed in the dam or its  foundations  The following procedure should be followed for this purpose     41 Boil The Filter    Remove the filter from the piezometer and boil it in a large vessel for at least 15 minutes  so that
10. also gives the  coefficients  which is required to convert field readings into units of pressure using the linear or the  polynomial conversion method     7 1 Transducer constants  The value of calibration factor K  constant C and A  are provided by the instrument manufacturer  by calibrating the instruments in the factory  The pore pressure P at any time can then be    determined as follows     P K  f  f  C t t   As  A  in kPa    Where      calibration factor  kPa Hz    fo   zero frequency  Hz   at to  C  f   frequency  Hz  at            coefficient of temperature Hz   C       Atmospheric pressure at the time of calibration  kPa   A   Atmospheric pressure at the time of installation  kPa        temperature of instrument at the time of calibration in   C  and  t   temperature of instrument at the time of observation in   C     The value of    and    are fed into the read out unit or data acquisition system which then give the  pore pressure reading directly in engineering units     7 2 Presentation of data  Data from piezometers should be duly processed and presented in the following graphical formats     a  Construction stage   Plot to be drawn for pore pressure and embankment height versus time  b  Operation Stage   Pore potential  reservoir level versus time  8  TEMPERATURE CORRECTION  Thermistor for temperature measurement should be integrated with all vibrating wire piezometers   The thermistor gives a varying resistance output related to the temperature and can be calcu
11. aphragm  The diaphragm deflects in response    to applied pore water pressure  changing the tension in the wire and its resonant frequency     Calibration of the piezometer establishes the relationship between pore water pressure and  resonance frequency     To operate the piezometer  the wire is plucked by sending a broadband signal down the  piezometer cable to a coil magnet assembly beside the wire  When the plucking signal is turned  off  the wire continues to vibrate at its resonance frequency  which induces an alternating current  in the coil magnet  This signal can be read at the other end of the cable and then converted to  units of pressure     The relationship between wire tension and resonant frequency is given by the following equation     f   og   p  7  2L Hz    where f   resonant frequency of wire in Hertz       tension of wire in kg cm   g   980 cm sec   p   density of wire in kg cm   L   length of wire in cm    The resonant frequency is directly proportional to the square root of wire tension and inversely  proportional to the length of the wire     2 2 Accessories  2 2 1 Housing    For application in dams  the above mechanism is sealed in heavy duty stainless steel housing   preferably with vacuum or inert gas inside it to prevent the corrosion of wire     2 2 2 Thermistor    A thermistor should be incorporated in the sensor for temperature sensing and if necessary  to  make the temperature correction in the zero reading     2 3 Cable    Cable used should be 
12. be hours or days depending on local conditions        Table 1  Grout Mixes    Grout Mix for Hard and Medium Soils Grout Mix for Soft Soils  Materials Weight Ratio by Weight Weight Ratio by Weight  Portland Cement 43 kg 1 43 kg 1  Bentonite 11 kg  as required  0 3 18 kg  as required  0 4  Water 114 liters 2 5 283 liters 6 6       5 5 In Situ or Push in Installation    Sometimes it may be desirable to push the piezometers in rather than drill and install them  This  installation method requires a cone head piezometer  It provides the advantage of readings from  an instrument placed directly into the native formation  However  it also requires extra precaution  to prevent twisting of the signal cable or damaging the piezometer by exerting too much force  while driving it into position     The piezometer has a right hand thread  A disposable adapter is needed to thread onto to the  piezometer to make the drill rod connection  The following installation procedure should be  followed     1  Assemble the adapter to the piezometer     2  Attach a coupling pin to the bottom of the drill rod and feed signal cable through the drill rod   Continue assembling the drill rod string while threading the cable  Cable length should be  adequate for total installation depth plus surface distance requirements  If borehole depth  requires drill rod be added as piezometer is lowered  it should be ensured that no twisting of  cable occurs     3  Connect the Vibrating Wire Readout to the cable  Begin
13. e 00 9ET T MN   251  NOILYLS NOIL VAH3S80 AHVHOdW3L                  TOHINO9 O1 251 WOH4  TAVH dIH M0738    1  318v2 3802 0   INO  00  05 HO      dol WVG NO WOOH 1081102     00 051        rs eu                      4 2 Re assemble the Piezometer    Dip piezometer inside the boiled water and reassemble filter  Ensure water enclosed between  diaphragm and filter does not leak out of sensor when it is tilted or turned around     4 3  Quick Zero Check    Ideallv  this test should be conducted in a draft free room where the piezometer can be kept ata  constant temperature  At minimum  the piezometer should be placed in a location that is out of  direct sunlight and allowed to reach thermal equilibrium with the surface it is resting on and the  surrounding air  This may take an hour  The piezometer should not be handled during this time or  during the test     Connect the signal cable to readout and obtain a frequencv reading  Readings should be checked  and ensured for their repeatabilitv  Applv calibration factors to convert the frequencv to a pressure  reading in Pa     If the local elevation is above sea level  the pressure reading that obtained will most likely be  negative because the sensor calibration is referenced to one standard atmosphere  sea level   To  calculate an approximate correction for elevation  allow 0 1 kPa for every 10 meter of elevation  above sea level  Add the correction to the reading     Note  For example  if the elevation is 1 000 meters  add a correct
14. e signal cable is lined up with the same reference  used for the shallow position  Allow the piezometer to adjust to temperature at that depth   Readings should be checked and ensured for their repeatability  Then record the frequency  reading  and the temperature reading  Convert both readings to units of pressure by applying  calibration factors  Subtract the shallow pressure from the deep pressure     Note     It is done to avoid having to correcting for altitude     Convert both pressure values to feet or meters of liquid head and compare to the distance  between the two marks made on the signal cable  There are many variables that can degrade the    accuracv of this test  including positioning errors  the specific gravitv of water at each depth  the  temperature of the piezometer at each depth  etc  Correction should be made for these     Note   The real purpose of the test is to verify that the piezometer gives roughly the reading that was  expected     5  INSTALLATION  5 1 Saturating Filters    The filter from piezometer should be removed and soaked or boiled in water for about 15 minutes  or until the filter is saturated with water  The filter can be removed bv opening the locking nut with  a spanner wrench  In some models the filter is removed      pulling out the filter holder  In some  other models the filter can be removed bv unscrewing the conical tip     Before replacing the filter  the end of the piezometer should be filled with water  With the filter end  of t
15. er into the borehole when the desired sand level is achieved     5  After piezometer is lowered to the desired depth  add sand with a tremie and continue pulling  the casing until it is above piezometer  Continue filling with sand until at least six inches  150  mm  of sand has been layered above the piezometer     Note     There is an alternative method to the steps described in steps 4 and 5 and i e called bag  installation  It is done by placing a piezometer into a canvas bag filled with sand and lowering the bag  into the borehole is also an acceptable piezometer placement technique  similar to the technique shown  in figure 3      6  Isolate the piezometer by creating a bentonite clay seal above the piezometer sand zone  created in step 5  Installation specifications should be referred for thickness of seal  Typical  seal thickness is a minimum of one foot  Bentonite chips should be used and the seal should    8    10     be created slowlv to ensure that no disturbance takes place in the piezometer placement   Continue to pull casing up to complete this step     Bentonite Setup Time  Maintain a water filled borehole while the bentonite sets up  Tvpical  time for the bentonite chips to set up and form a seal is two to three hours  Bentonite suppliers  directions should be consulted for recommended time intervals    Completelv fill remaining borehole with bentonite cement grout mixture    Mark piezometer cable at surface with stake or flag  Terminate wires and connect to V
16. from damage bv angular and sharp particles of material in which it  is embedded     Cables mav be spliced without affecting sensor reading  nevertheless splicing should be  avoided wherever possible  If necessarv  use special cable jointing kits available from factorv     In earth rock embankments and backfill  cable shall be protected from stretching due to  differential compaction of embankment  Cable shall also be protected from damage bv  compaction equipment     The cables should be protected against prolonged exposure to sun and mechanical damage   It is  therefore  necessary that the cable is properly covered at all times     Cable should be earthed at suitable locations     5 7 2 Cable trenches    a     At any cross section  filling of dam is allowed to continue to an elevation of around 0 5 to 1 m  higher than where piezometers are to be mounted  Positions where piezometers  whether  foundation or embankment  are to be mounted should be carefully marked  Offset trenches  as per figures 4  amp  5 to reach correct required elevation are dug at these positions     Manually compacted back fill Embankrentieyei  Selected fine material                 o    X o    N    Y FK      8     1T        e               A i i      X      8 9  N    IPE    100 _     600 al 450 M N Cables  A A  300 450 300  N      Main trench                     Embankment soil                  j RQ  Selected fine material M D as    Cables 8mooooooo       1  LO            Bentonite plug ta      B B  Hand
17. he piezometer facing up  the filter should be replaced  A small amount of water may squeeze  through the filter stone as this is done     Assembled piezometer should quickly be inserted into a bottle or bucket off water  keeping it  submerged while it is transported to the field  Water enclosed between diaphragm and filter should  not leak out before installation of the piezometer  A saturated filter with no air gap should be  ensured for accurate readings     5 2 Installing Piezometers in Open Standpipes    This procedure may be used for the installation of piezometers  which are in the vicinity of the  dam site but are located outside the foundation area  For monitoring water level in an open  standpipe  sufficient time should be allowed for level to stabilize after lowering piezometer  assembly into the borehole     5 3 Installing Piezometers in Foundations Using Sand    The procedure described herein can be used for installing piezometers in the foundation of the  earth and rock fill dam  A traditional borehole installation requires that the total depth of the hole  be drilled to one meter past the planned piezometer installation depth  Installation procedure  should be as follows     1  Flush the borehole with water or biodegradable drilling mud     2  Create a sand zone using a tremie to drop wet sand to the borehole bottom  Elevate casing to  maintain casing above the sand level     3  Tie piezometer to signal cable in the filter end up position   4  Lower the piezomet
18. ibrating   Wire Readout  If the Vibrating Wire Readout is weatherproof it may not need any further  protection from the elements    Begin to collect periodic readings  Initial pressure readings typically will be high    Continue to evaluate readings as installation stabilizes  Installation stabilization is contingent    on local conditions  including soil permeability  Complete datum readings after installation  stabilizes  this period can be hours or days depending on local conditions     Sensor cable                         Tie string     _ Open top      xm   Tie wire  e A     Bronze metal screen    Water saturated     IE clean sand  2 4 mm   G Ex    Eo  c                       4   a j A    SISSE               Vibrating wire  Aot m Pore pressure cell  4       EL Tie wire        70                All dimensions in millimetres     Fig  3 Piezometer cable assembly before installation    Piezometer cables 12 mm apart    Trench     Hole for NIT  Foundation tvpe tip  lt    4     XE EN    T               2    Offset trench    12 min  L     600 900 450 900   Main trench       Offset trench Compacted      earth fill El us  2 E  Place embankment TY o  tips in offset trench   1 S           d     Grout    _    n           cement   sand   1 3         A cl e c  X E E E  EIE           Clean saturated sand    o d ER   o Name       15    Bentonite plug Sellected fine material     Cables             a   i E            G    gt        o A              Pore pressure cell assembly   9 N   o     
19. ion of 10 kPa to the pressure reading     The working of piezometer may be considered satisfactorily if the difference between the corrected  pressure and zero is within 2 percent of the full scale of the piezometer  2 MPa for a 100 MPa  piezometer   To make a more precise check  corrections should be done for the true altitude  the  barometric pressure  and the temperature     4 4 Down Hole Pressure Check    This test is conducted in a water filled borehole or standpipe piezometer  Sensor calibration record  is required for this test     Mark signal cable at two depths  one at a shallow depth and the other as deep as possible  within  the range of the piezometer   Measure from the location of the diaphragm  23 mm  0 9 inch  from  the tip of the borehole piezometer  112 mm  4 4 inches  from the tip of the push in piezometer  and  51 mm  2 inches  from the tip of the embankment piezometer  Pull the filter off the piezometer  fill  it with clean water  and replace the filter  Hold the filter end up until the piezometer is placed in the  water     Lower the piezometer to the shallowest mark on the signal cable  Clamp the cable in position and  wait at least 30 minutes for the piezometer to adjust to the temperature of the water  Connect the  piezometer signal cable to the readout device  Readings should be checked and ensured for their  repeatability  Record the frequency reading and the temperature reading at the shallow depth     Lower the piezometer until the other mark on th
20. lated    by using the following equation     T          B LnR    C LnR      273 2   C    Where T   temperature in   C  LnR  Natural log of thermistor resistance  A   Constant  B   Constant  C   Constant    The resistance is measured with an Ohmmeter  The cable resistance is subtracted from the  Ohmmeter reading to get the correct thermistor resistance  The value for the constants is generally  given by the manufacturer     
21. perature to stabilize  Take particular care  that sunlight does not fall on any surface of piezometer     b  Make sure that filter is fully saturated with water  Reading will be seriously affected due to  surface tension effects in pores of filter in case filter is not fully saturated  At low pressures  below 50 kPa  the problem is more acute     c  Make sure that temperature and barometric pressure are recorded at the time of taking zero  reading     6 2 Taking of readings    The observations of the pore pressure cells should begin as soon as the instruments are covered  and may continue at gradually increased time intervals as recommended by the designer  s    During construction stages  the readings with time and date are stored in the read out and should  be transferred to the computer at regular intervals  After construction is over  it is advisable to  store and process the readings directly in a data acquisition system     7  CONVERTING FREQUENCY READINGS TO PRESSURE    Many of these functions can be performed automatically by the devices described above  After  installation of the piezometer in the field  it should be allowed to reach thermal equilibrium   typically 20 25 minutes  before taking the first reading  Temperature gradients through the body of  a piezometer can cause reading errors     Calibration values are given in the Calibration Certificate provided with each piezometer  The  calibration units  digits  are frequency2 x 10 3  The Calibration Certificate 
22. stance between successive cables should be kept at  around 25 mm  A distance of 100 mm must be left free from sides of trench  To take care of  any increase in length due to settlements  cable should be zig zagged by providing a  uniformly distributed slack of around 0 5 m in a 15 m length of each cable     e  In instances in which more than one layer of cables are placed in a given array  the cables  should be separated from each other by a vertical interval of not less than 100 mm of hand  compacted sand or selected fine embankment material     f  Bentonite plug  A mixture of 5   bentonite  by volume  and 95   embankment material  should be placed at  15  meter intervals  or midway between the piezometer tips whenever  distance is smaller     g  In rockfill dams with earth fill cores  it is convenient to install sensors and cables in trenches  in core and fine filter zones and in ramps in coarse filter and compacted rock fill shell zones   A typical installation of cable in the rockfill region is illustrated in figure 6  Carefully graded  rockfill should be used around the cable trench  While routing of cables through rockfill  the  main trenches carrying cables should be filled with coarse sand completely passing 5 mm  sieve  The relative spacing between individual layers of cables as shown in figure 6 may be  maintained  The graded material surrounding the main trench should be provided with  properly graded layers to prevent migration of sand filling in the main trench  
23. suitably protected to prevent water seepage through it  Cables may be  terminated in an intermediate junction cum switch box or directly routed to the observation room     A typical vibrating wire piezometer is shown in figure 1   2 4 Cable Identification Tags    After connecting cable to pore pressure cell the free end of cable should be marked or identified  with a permanent tag  A minimum of 3 tags should be used in the cable which should be placed at    4    a maximum spacing of 10 m over the entire exposed length of cable with non corrosive material or  plastic tags engraved or embossed with appropriate transducer numbers  Permanent identification  should be used to prevent errors in identifving pore water pressure cells and their connecting    cables   4 Core cable       Piezometer Cable housing Cable gland    Fig  1 Tvpical vibrating wire piezometer  2 5 Junction Cum Switch Box    Multi position junction cum switch box suitable for connecting and switching inputs from group of  sensors to the readout unit should be provided  It should be water proof and made of non   magnetic material     2 6 Cable Splicing Kit    Cable jointing should be avoided to the extent possible  In case  it becomes necessarv cable  slicing kit should be used to make a water resistant sealed joint between two cable ends                 gripping the armouring     2 7 Read out Indicator  The read out unit should be portable and suitable for reading all types of vibrating wire sensors   3  TYPICAL 
24. terial    Sand finer than   mm        Fig  6 Cable routing in rockfill region    Sensors  Core              Fig  7 Vertical routing of cable through filter  6  TAKING READINGS    The easiest way to take readings from the vibrating wire piezometer is by using the portable  readout unit  The portable readout reads the piezometer  displays the reading  and stores for  subsequent downloading to the computer  Reference should be made to the user   s manual given  by the manufacturer for complete details     For situations where continuous logging of piezometer output is required  a single channel logger   or a multi channel datalogger may be used  Reference should be made to the user   s manuals of  these products given by the manufacturer for operational details     15    6 1 Initial reading    In any vibrating wire piezometer  when wire is plucked  it has an initial frequency reading when no  pressure is exerted on its diaphragm  It is therefore necessary that an initial zero reading be  accurately determined for each piezometer  as this reading will be used for subsequent data  reduction  The reading prior to installation  when no pressure has been applied  should be taken  as initial reading     Special consideration should be given to the following     a  Make sure that piezometer temperature reaches thermal equilibrium  Temperature variation  across body of piezometer results in temperature transients and consequently error in  reading  Allow 20 25 minutes for piezometer tem
25. ure  in the pore fluid comprising air and water  Thus  the intergranular pressure is reduced due to  opposing pore pressure and therefore the shear strength depends upon intergranular pressure     Pore pressure is also caused due to the seepage of water through an embankment  The initial  energy head of percolating water at entrance into the dam is greater than the energy heat at any  point in the interior  The difference represents the loss of energy due to friction forces of  percolation  The potential of the water decreases as it seeps through the dam  Pore pressure due  to percolation is determined by subtracting the corresponding elevation from the flow potential at  that point being considered  Thus pressure at any point in a dam at any time is the function of  compaction  consolidation and seepage  Procedures for testing the pore pressure cells both in the  laboratory and in the field before installation are under formulation     This standard was first published in 1990  however  the Committee responsible for the formulation  of this standard decided to revise it based on the experience gained during the last decade as well  as technological development in the field     For the purpose of deciding whether a particular requirement of this standard is complied with the  final value  observed or calculated  expressing the result of a test or analysis  shall be rounded off  in accordance with IS 2   1960    Rules for rounding off numerical values   revised      The number
    
Download Pdf Manuals
 
 
    
Related Search
    
Related Contents
コロル ネコトイレ F60フード付  Manual do Utilizador do PS-9000 Português    p60-p78 - TOJIKI TONYA  Lincoln 1998 Continental Automobile User Manual  ATN PS-7 operator`s manual  QS10.121  SCA031U サイドカメラ接続アダプター  Voir les caractéristiques complètes  Panasonic TH-103VX200U Specification Sheet    Copyright © All rights reserved. 
   Failed to retrieve file