Home

Operating instructions HDI Two.1 Operation of the 2 option for the

image

Contents

1. to the correct input socket otherwise the HDI may mis read or give OPEN when that channel is selected as the display channel The notes below are useful for identifying the wiring of the probe should the probe test sheet not be available Selection of the channel to be displayed and hence which probe is being monitored is done internally in the HDI under control of the front panel buttons Notes on the wiring configuration of a particular probe 1 Helium probes with the 7M connector and with an active length less than 555mm will ordinarily be wired for channel A those with an active length greater than 1530400022 Aug 2002 Operating instructions HDI Two 2 555mm wired for channel B It is suggested that wire ended probes are wired to follow this convention where appropriate 2 Nitrogen probes are preferred to be in the A configuration as this also corresponds to the stand alone V configuration 3 Where there is a conflict of priorities in channel assignments for the two probes a special 2 option installed Special 2 option As well as the standard configuration of the 2 option there also exist the special 2 options which allow two probes with the same channel wiring to be connected at the same time The special 2 option is highlighted when it is incorporated in the system The special 2 option is required under a number of circumstances and a couple of examples are provided here 1 The helium probes th
2. Operating instructions HDI Two 1 Operation of the 2 option for the HDI The 2 option for the HDI allows for two probes to be connected to the HDI simul taneously It is then possible to change the probe being monitored by the HDI by the use of the front panel buttons with no need to change any physical connections It can also allow for foreground and background operation of two probes which is usually of use via the remote interface or when the control and alarm C option and or the two analogue output Z is also selected Description An HDI with the 2 option can be identified by there being two probe sockets on the back panel A second probe cable is also supplied with the unit unless either the P or P2 option is selected where one or both of the probe cables are substituted with just the mating connector for the socket This might be appropriate for installations using wire ended helium probes The two sockets are labelled A and B corresponding to the two channels of the HDI If the two sockets are each labelled with two characters then the HDI unit has a special 2 option as described below Operation As well as the hardware the unit has to be configured While this is also done at the factory before shipment it should be noted that the following configuration menu option needs to be set for correct operation 25 INP2 When connecting one or two probes to the HDI ensure that the correct probe is connected
3. at are to be used with the HDI may also be used with other HDIs or other controllers already installed To introduce a probe wired to operate on the opposite channel to that anticipated from its active length could cause confusion 2 The HDI will be used to monitor a two probes with identical active lengths for example probes installed in a number of helium storage dewars and where no distinction can be made as to which probe could be connected to channel A or B For example two probes both wired for channel A could be connected to the two sockets of the HDI when it has a special 2 option This may also apply where probes have different active lengths but still remain with the same channel wiring Care should be taken in the this case as to which probe is connected to which socket Identification of the special 2 option There are three types of the 2 option one standard and two special Although the socket labelled B always goes to channel B it may be wired so as to connect a probe wired for channel A in other words be a conversion socket This is one of the two special 2 options the other variant being for the similar changeover being applied to the channel A socket The three 2 options are designated as follows Operating instructions HDI Two 3 AB The standard 2 option with the channel A socket wired for a channel A probe and channel B wired for a channel B probe AA BA The channel A socket is wired for a
4. channel A probe as is channel B which is in effect a conversion socket so that a probe wired for channel A can be monitored on channel B on the HDI AB BB The channel B socket is wired for a channel B probe as is channel A which is in effect a conversion socket so that a probe wired for channel B can be monitored on channel A on the HDI As well as identification on the back panel full details are given on the HDI system configuration and packing list supplied with each HDI unit When using the two special 2 options the user must be warned to be sure that they have connected the probes they wish to be monitored to the correct socket and not accidentally swapped them The use of these special 2 options is entirely at the users own risk Should there be a need at a later date for an HDI with a special 2 option to monitor a probe wired for the other channel for example the special 2 option AB BB needing to monitor a probe wired for channel A it is possible to get a special crossed interconnecting cable please enquire from the sales staff at Twickenham

Download Pdf Manuals

image

Related Search

Related Contents

舟亢 空 自 衛 隊 イ士 様 書 仕様書の 内容による分類 装 備 品 等 イ士  Outdoor LP Gas Barbecue Grill Model No. GBT1302W    EUROLITE Neon Tube Complete Set 12V User Manual  EN-TW-MB1010 -MANUAL-V1.0-english_2011-05-06  

Copyright © All rights reserved.
Failed to retrieve file