Home
        Septic tank installation manual - Tricel
         Contents
1.  conditions  Fill each chamber of the unit with clean water to a depth of 300mm and recheck the pipe work levels   Commence backfilling evenly around the tank ensuring that there are no voids  Continue filling the  chambers whilst backfilling  ensure that the progressive water level is no more than  300mm above the backfill level   Continue to backfill until material has reached 100mm over the tank     Complete backfilling with topsoil  Ensure lid remain above surrounding ground level     10    7 5 Deeper tank installation  amp  wet site installation     A concrete surround is required  where two or more risers are required or where the site conditions    are considered wet   A wet site is one where the water table may rise higher than the base of the Tricel unit     7 5 1Tank base plinth     Remove any soft spots or large stones and boulders    The base is constructed of a 200mm layer of concrete semi dry mix    Ensure that base is level and ensure that correct orientations are determined to accommodate the incoming  pipe work    It is important to maintain a completely dry excavation until the final pour of concrete is set  It may be  necessary to line the excavation with a continuous layer of 1200gauge polythene to maintain the integrity    of the concrete     7 5 2 Installing onto the base plinth   Lift the unit carefully into the hole and place on the prepared plinth before the concrete sets  The unit must be dead level on the plinth  The higher pipe on the tanks is to b
2. OEEEEEEE TEL   REE ERE  ZLLLLLLLLLLLLE   PILEEELLEIL A SAOELEEEPEELEE SOCEEEEEEEEE   COAEEAEAETEETE Pane GOOEEEEEPEEEEE AOPPEEEE PELE   POCEPEPEPEEEES UOdTETT ETE  VIILITTTITITTE IISI             ZLLLLLLLLLLLLE p     LEEEETEET EEA  7 ZILLLLLLLLLELE     o LULLLLEELLA   VOOLEEELEEELEE G oncrete  S emi d ry mix PPEOLEEPLE EL    ry  ZLLLLLLLLLLELE zi AOCEPEEPEEE COOETTEETTE ET EE C onc rete Se mi d J MX ee  PPPPLPEPPEL L  COOLOEEEEEEEES AOCEEL EE EET LE      ACPEEEEEE TT As  dtttttttttt        COOEFOEEEEEE ETE  beeeeeerereres S6bCee tet tts VOOOEEEEEEEEEE  eeeeeereeeeees                200 200          7 4 Dry site installation     7 4 1 Tank base plinth   L  Remove any soft spots or large stones and boulders  O The base is constructed of a 200mm layer of concrete semi dry mix   O Ensure that base is level and ensure that correct orientations are determined to accommodate    the incoming pipe work    7 4 2 Installing onto the base plinth    L  Lift the unit carefully into the hole and place on the prepared plinth   O The unit must sit dead level on the plinth   O The higher pipe on the tanks is to be connected to your upstream  inlet  pipe work and the  lower pipe on the tank is to be connected to you downstream  outlet  pipe work  Connect and  seal the pipe work to the tank  checking alignment to ensure there is an adequate fall for each  pipe    O Mount manhole risers  if used     7 4 3 Backfilling dry site     Concrete       Refer to backfill specification appropriate for site
3. TRICEL       TRICEL    Table of contents     1  Health  amp  safety precaution So  sciccicsiecsccssencssssestssscicssessastagcacs sede sbetanecstesses anatszinds cbsctnsenendsosacucecuceeanesceaesnaeit 2  2  Transportation  offloading and Storage  oo    eesssceceeseeeeeeeteteteseeeeeseseeceeesenseacaratarararsnesaceeeeeeeeneees 2  3  The wastewater purification process       csssseceseseseseseseeeeeeeececacarscaeseseseececaearseseeeeeeeeeeeseneeatararaneeess 3  As    TarbeGimensS ions siciiccessicssedessceseesselencitueteseceseasaestanssdbientaretshsostea teeta cdivepanueudecalooabapedecyepistusseasededs cpotacasecdcaes 4  5  Tank Grawin giiiecccicnsiaedaniien nitude deans iiataelaibiauiin bhadlaieeieatuldea usta n intakes 4  6  Manhole risers      deep inverts              ccccecccecssesecsesesesesesececscsesesesscecscsesesssacecacaesesaeaeaearsesnssesesaesesneeseeetans 5  Tae MIASCALLBCIO AE E A E dint ssaiaearhanes delete dubai EEEE  5  7 1  Pre    installation INSPECHOM Ss     dcccscasciseccasccsoconsacecdncdesousacastcutspecon  eatacatocsbcusnaccassssshasiacechedhoeemnucatuedss 5  7 2 Quick installation QUIGCLINGS  oe eee eeeecs eee eeeeeseseeeeeeacecsaesesesenaeseseeeeaeseseeeeasaeseeeeataeeeesaeseeatseseeetataesees 6  7 3 Detailed installation information    0 0    eseseseeeeeeeeseceeeseseseseseeeeeeeesasacaraeaeaeseseacacacaeseseseseeeeeeeseeatatarararees 7  7 4 Dry site installation  sessisccetcestsrsssccectcsesinsccncvecatevesctavasicivescoetececeutorecsdedacstieavs
4. ay  De sludge period  minimum     Nominal inlet outlet pipe diameter    Inlet invert to base    Inlet invert to ground level  tank only  Inlet invert to ground level     with 1 riser    Outlet invert to ground Level    Tank capacity  Overall length  Overall width  Overall height       5  Tank drawings     D7 RhA A d        aS ga  mm  gt  i Sal SC Ee  H N FIONN  HEW EN  I aty      i Hes    OLLA    Pn wm a a TT Hes  E2 d   ome i Oty ICa  HIM AN N Ut IL ee                                 6  Manhole risers      deep inverts      Manhole risers are available for deeper installation requirements  They are available in 180mm increments x  400mm diameter to a maximum height of 900mm  960mm from the invert level of the outlet pipe to ground level      180mm manhole risers require a standard installation for dry sites     360mm  amp  540mm manhole risers require a complete concrete backfill   See notes on deeper tank  installation and wet site installation       Never install the cover of the system under ground level     Never let groundwater enter the system   7 Only Tricel risers should be used     j     All manholes lids are lockable and should be locked for safety and to prevent unauthorised access  All       maintenance work is done through these manholes     Systems with a manhole riser of 360mm or 540mm must have a concrete surround  360mm and 540mm risers  cannot be retrofitted unless the correct base and backfill requirements are adhered to     7 Installation     7 1 Pre  ins
5. c  To prevent movement  tanks may need to be  tied down    3  Tanks are best lifted by crane or suitable lifting equipment and webbing lifting straps     do not use chains  or wire ropes in contact with the tank  Ensure tank is empty when lifting    4  Move tanks only by lifting and setting  do not drag or roll    Do not drop or roll tanks from truck trailor    3  The wastewater purification process        The septic tank is another product within the range of Tricel environmental solutions  The Tricel septic tank is an  ideal solution for wastewater treatment where sufficient land is available for an adequate drainage field    The tank is divided into two chambers  sized sufficiently to hold wastewater for an adequate amount of time for  the solids to drop to the bottom to form a sludge and the lighter material to rise to the top of the liquid to form a  scum  A certain amount of anaerobic breakdown occurs within the tank  The remaining liquid effluent is passed  through the outlet pipe into the drainage system for final treatment  The liquid is dispersed evenly within a  series of drainage pipes into the soil  The micro organisms in the soil breakdown any organic matter left in the  effluent  As most of the treatment is carried out in the percolation area  it is important that the land is adequate    for sufficient treatment of wastewater to prevent harm to the environment        4  Tank dimensions     litre  mo    110  Height above ground level    Design flow rate litres d
6. e connected to your upstream  inlet  pipe work and the lower pipe on  the tank is to be connected to you downstream  outlet  pipe work  Connect and seal the pipe work to the  tank  checking alignment to ensure there is an adequate fall for each pipe     Mount and seal manhole extensions  if used     7 5 3 Backfilling a wet site        Refer to backfill specification appropriate for site conditions  e Fill each chamber of the unit with clean water to a depth of 300mm and recheck the pipe  work levels  Commence backfilling evenly around the tank ensuring that there are no  voids  Continue filling the chambers whilst backfilling  ensure that the progressive water  level is no more than 300mm above the backfill level     e Backfill with concrete semi dry mix until it has reached 100mm over the tank   e Complete backfilling with topsoil  Ensure lid remain above surrounding ground level     11    7 6 Plinth and backfill specifications     7 6 1 Concrete backfill specification   Semi dry concrete 25n grade with a ratio of 4 5 aggregate to 1 cement   Note  Standard concrete mixes should not be used  where sulphates or similar aggressive chemicals are    present in the groundwater     Lift height  rate of rise      Determine the lift height  m   or rate of rise  m h  for the specific concrete type used  to ensure that    a design pressure  P max  of 15kN m2 on the tank is not exceeded     Vibration   The design of the tank assumes minimal compaction of the surrounding concrete  Where 
7. ed as much as possible from around the tanks using    piped drains     7 3 3 Note  water logged sites    The Tricel System is not suitable to be used in water logged sites  where the ground water may rise above  the outlet level  Please contact the supplier of the system if there are difficulties on site due to  adverse water logging  Adequate drainage is important to improve wet sites  or sites with a high water  table level  It is critical that water is removed from the area surrounding the system to prevent  flotation  Excessive loading caused by site water can harm the system  please consult with the    manufacturer or a qualified engineer if in doubt     7 3 4 Excavation size    Suitably sized equipment will be required to excavate the hole and to crane the system into place   Installation depends on on site conditions  water  slopes  location etc  Excavation should be planned  with due regard to Health and Safety requirements  and should be either shored or battered back to a     safe    angle  The excavation should allow a minimum 200mm clearance between the tank and the  excavation wall or face of shoring  Unstable ground with excessive sand  peat swamps etc  may  require larger excavations  The excavation should be maintained dry by pumping or whatever suitable    means     External dimensions  Dia in meters x Length in meters  Total excavation   Width   200mm  x  Length    200mm  Excavation depth  Allow 200mm for a tank    base plinth     7 3 5 Excavation depth    T
8. er the tank for    sampling and to assist in clearing possible blockages       If sewage consists of high quantities of grease e g  from a restaurant  a grease             trap may have to be installed on a separate drain prior to the system        Note  The option of anchor straps may also be used on wet site  This should be designed by an on site    structural engineer     7 3 Detailed installation information     7 3 1 Siting     The minimum distances for installing the septic tank are outlined below                 UK   A dwelling 10 metres  Wall or boundary 5 metres  Well  borehole or spring 50 metres  Watercourse 10 metres          The soak away should be 5m from a hedge or tree    roots             Ireland        Tank and percolation area             A dwelling 7 metres  Site boundary 3 metres  Road 4 metres       Well  borehole  watercourse    10 metres  or spring    Lake 50 metres             7 3 2 Control of groundwater    Tanks must not be subjected to buoyant forces during installation  taking account of ground water  levels and surface water run off  and their accumulation in the tank pit  even if tanks are anchored    The excavation area should be adequately drained  to permanently remove ground water from the  proximity of the tank  or tanks   This is critical in order to avoid flotation of the tanks  Incorrectly  installed tanks that are subject to movement  rotation or floatation may become damaged  for which  we cannot accept liability  Water should be remov
9. he excavation depth is determined by the inlet and outlet pipe  invert levels relative to the bottom of  the tank  and allowing for the minimum base thickness shown  Dimension details of the tank are shown  on the relevant drawing  supplied with the system  Ground instability at formation level e g  running sand    may necessitate over excavation and stabilisation with hardcore or blinding concrete     NOTE  Check that the depth to the base slab is within the Service Specification requirements for the tank        Dry Site Wet Site              Ground Level    zzz PILELELLLLI Ls  VOCOEEEEEEEEET AtOEEEEEEETE   VOCOEELELEEEEE CAEAAAKALAL VOCLEEEEEEEE EE POLEELPEEL EL    PAPEETE TE Le WAtttttAA ATLL DIII  CPEEEEEE EEL COCLEEEEEEEE EE LEOEETEETEL     GOEEET EEE Le VOOCEEEEEEE EEE COEEEtEET ET    Ground Level  COECEEEEEEL LEE ke COOPPEEPPE SA   SOECPEPEEEEE EEE Pu ie COOPPEEPE EEA            COEPEEPEEE EEE T               RACE COLEES  Lda ditide VOCEEEEEEEEELE COEEEEEEEET  SENTETTT EEE E i VPECCLEEEE TA  VIPEEEEEEEEEEE cette ett t tt  COLITPTEESSETE   VLEPPLELEL TAs COOEEEEEEEE EEE VACEEEEEE EE Le    COOELEEEEETTEE   CELEEEEEEE Te COOLED EEEET EE LEOELEEEL EL     COEEETEEEEEEEE COEEEETTTE Ls COOEEEEEEET EEE CEOELLEEE EL 2  COOOLEEEEEETEE ORRERA ZILILILPLPLLLE APPELLEE EL  COOEEEEEEEEEEE WAPEEEEEEEE Lo VAAN ALE VACEEE EEE EE  COOELEEEEETTEE GEEEEEEEE Le COOEEEEEEEEEEE LOOEEEEEE EL  Sean th ak Sel s ss Sh G COOEEETEEEEETE CEEEEEEE ELS  COOOLEEELEEEEE COOTEEET EEE A   VOCEEEEEEEEEEE S
10. ied to EN 12566 1       page 5 for manhole riser details           TTM T202 RevO2 12 Mar 14       1  Health and safety precautions     As safety and security are of vital importance in septic tank installation  the following aspects are critical   e Ensure that all the information contained in this manual is adhered to at all times  e When working with machinery   electrical equipment  proximity of water shall be noted   e There is potential danger when de sludging and therefore this shall never be done alone   e Never enter a tank unless qualified to do so   e Naked flames shall not be used in the vicinity of the tank due to the danger of combustion   e The manhole cover shall never be left off an unattended tank   e Protective clothing   gloves shall be worn at all times  Always remove contaminated clothing and protective  equipment after working with septic tank   e Wash hands and face prior to eating  drinking or smoking   e A second person shall be present when carrying out maintenance   e A sampling box shall be constructed to facilitate sampling and inspection without placing personnel at risk   e Great care shall be taken when handling sludge     e Always lock the cover of the system when maintenance is completed        1  Tanks must be held down during transportation using nylon straps  do not use cables or chains to secure    tanks  Do not over tighten straps to cause deformation of the tank shell   2  Always set the tank s  on flat smooth ground free from debris et
11. les should be worn at all times  Always remove contaminated    clothing and protective equipment after completion of work  Wash hands and face prior to eating  drinking or          smoking     A certain amount of system maintenance is required  on an ongoing basis to ensure that the system is    working correctly  This is the responsibility of the homeowner     10 1 Quarterly Maintenance  3 months      The outlet distribution box should be checked monthly to ensure that the  effluent is free flowing and clear     The vent should be checked to make sure they are not blocked or covered with over grown grass   10 2 Yearly maintenance     De sludging should be also carried out yearly to prevent solids rising to the height of the outlet pipe and  being carried along with the liquid into the percolation trenches  This blocks the percolation area and  can cause flooding  Depending on usage and house population  more frequent de sludging may be  required  The de  sludging of the septic tank is the responsibility of the homeowner  De sludging is done    with a vacuum tanker  we recommend the use of a licensed company      10 2 1 De sludging  emptying the solid waste from chamber 1    primary chamber      e Remove the access cover   e Empty the Tricel septic tank using a vacuum tanker  Care must be taken not to damage the tank with the  hose of the vacuum tanker   e Replace the de sludging access cover securely   Notes   e Do not let this equipment drive over the tank  Maintain a dista
12. nce of at least 4 meters away  from the covers of the tank   e The access cover should never be left off while the unit is unattended     e De sludging should never be carried out alone     The property owner has a legal responsibility to ensure that the system does not cause pollution  a health hazard or    nuisance   16    11  Operating conditions     e The manufacturer s instructions outlined in the technical manuals must be followed at all times   e It is important that the unit is operated under the conditions for which it is designed  Any variation in    these conditions could lead to the unit not performing to its full potential        e De sludging is a critical part of the successful operation of the Tricel Septic tank  Only competent  approved personnel should carry out de sludging    e The discharge to the ground is also a critical part of the operation of the system  Correctly  constructed distribution chambers and distribution drains or polishing filters are necessary as part of the  treatment process  Incorrectly constructed drains or polishing filters could result in poor treatment of  effluent and we do not accept any responsibility in this regard    e If the system is not installed correctly  flooding  overloading  or floatation may occur  We are not responsible  for incorrectly installed systems    e Soak ways  drains and the emptying of primary tanks remain the responsibility of the client and damage to  the installation due to the influx of surface water o
13. nches  are set out in a continuous loop from the Distribution box  An access chamber should be placed before and    after the septic tank for sampling and inspection purposes and also to assist in any blockages that may occur        Distribution box  450mm high x 300mm opening Riser extension  300mm opening x 270mm high    14    8 3 Sampling chamber     A chamber must be fitted after every unit to allow easy access for sampling purposes  The inlet of    the chamber must be 150mm up from the base of the chamber to facilitate sampling cup     Ye    Inlet    Outlet          9  Finishing the garden to ground level     The finished ground level should be to the level indicated on the system     9 1 Ventilation     Ventilation is crucial to the system  Prior to installing the system  great care must be given  on how to  provide adequate ventilation  As sites differ  advice is available from BS8301  BS6297  EPA wastewater    Treatment Manuals 1999  and the manufacturer  The Tricel Septic tank is supplied with 1No 110mm socket    next to the inlet pipe for venting     15    10  Maintenance     Precaution    Any maintenance carried out inside the tank represents a confined space  Therefore the maintenance person must be  suitably trained to work in confined spaces  Sewage and sewage effluent can carry micro organisms and gases  harmful to human health  Any person carrying out maintenance on the system must be appropriately trained   Suitable protective clothing  including gloves  gogg
14. necessary  this  may be extended to include light internal vibration  Never use deep revibration which will    substantially increase the pressure on the tank  possibly causing failure     Impact of concrete on discharge     Under no circumstances should concrete be discharged directly onto the  tank     7 6 2 Gravel backfill specification     Primary backfill specification    Primary Backfill material should be free flowing granular material  Compaction should be by lightweight  rollers or vibratory plate compactor until    traffic    depth has been achieved  Compact evenly  around  the turret extensions to reduce risk of distortion  Tanks must be installed with Primary Backfill only  within the region immediately surrounding the tanks  This Primary Backfill must extend a minimum of  250mm outward from the tank and directly beneath the tank     The following materials are approved as Primary Backfill    Rounded pea gravel    Minimum particle size 3mm  maximum 18 mm  compacted to a relative density of  gt 70   Gravel shall be  clean and free flowing  free from large rocks  dirt  sand  roots  organic materials or debris  Upon screening    analysis the backfill material shall have no more than 5  by weight passing 2 36 mm Sieve    Or    12    Crushed or processed stone     Minimum particle size 3 mm  maximum 12 mm  compacted to a relative density of   gt 40     Dry Gravel density must be at least 1500 kg m3  Material should be washed or screened to remove  fine particles  Upon 
15. of extra houses  bedrooms  in the houses  schools  cr  che etc  or by any other means  we are not responsible for the system in  terms of overloading or the quality of the effluent as the retention times may be compromised    e The unit is not suitable for vehicular traffic  We also recommend fencing off the area to prevent livestock    herds from accessing the unit  Where possible  unnecessary human traffic around the tank should be avoided    Terms  amp  conditions  Subject to our standard terms and conditions  which are available on request     In accordance with our normal policy of product development  this specification is subject to change  without notice     March 14    18       TRICEL    GENERATIONS OF INNOVATION    Tricel  Killarney   Ballyspillane Ind  Est   Killarney  Co  Kerry  Ireland   Tel   353  0  64 6632421   Email  sales ie tricel eu   www ie tricel eu    Tricel  Gloucester  Ltd   Fox House  Stonedale Road  Stonehouse  Gloucestershire  GL10 3SA  United Kingdom   Tel   44  0  1453 791 616   Email  sales uk tricel eu   www uk tricel eu    In accordance with Tricel normal policy of product development these specifications are subject to change without notice     
16. r anchor straps if required should be built into the foundation    A base is then formed using 200mm of concrete semi dry mix  suitable to    site conditions  and this must be flat and level        A base is constructed of a 200mm layer of concrete semi dry mix to suit    site conditions  This must be flat and level        Ensure gravel concrete are clean and contains no large materials       Lift tank into position and align as required for connecting pipe work     access shafts etc        Ensure that each tank is 100  Level  and that inlet outlets are in the    correct orientations   Secure anchor straps if required   Ballast the tank with water    Mount risers    Commence gravel backfilling in 300mm layers to 100mm over the                tank  ensuring tank and any pipe work is properly supported        Commence concrete backfilling in 300mm layers to 100mm over the    tank  ensuring tank and any pipe work is properly supported           Complete backfilling with topsoil up to ground level  Ensure that    surrounding finished ground level is never higher than the cover of the       Compaction should be by lightweight rollers or vibratory plate compactor until       traffic    depth has been achieved       Compact evenly around the riser extensions to reduce risk of distortion        Ensure that No surface loadings are transferred from the cover direct to    the tank  Cover frame construction should allow movement        An access chamber should be installed before and aft
17. r the backing up of soak ways or drains is not covered  by the manufacturer    e We shall not be liable for any damage or loss  including consequential loss  caused by the failure of  any plumbing equipment or failure caused by the inclusion of gross solids   e g    disposable diapers or  sanitary towels etc  in the septic tank    e To ensure the continuance of the systems performance  the user has to take certain precautions including  the following    e The design loading of the plant should not be exceeded    e High volume discharges such  as those from swimming pools and Jacuzzi s must never enter the system    e Surface water must not enter the system    e Do not allow large quantities of chemicals to enter the system including    o Water softener regenerate    o Disinfectants    o Strong acids and alkalis  or photographic chemicals   o Oil or grease    o Petrol or diesel    o Pesticides    o Large quantities of milk  alcohol or food    o Large quantities of bleaches or cleaners   o Baby wipes    o Sanitary towels    17    o Kitchen paper  o Nappies   e Service personnel must be accommodated with clear access to the system    e If the system has been sized by others  we will supply a system to these specification and not its  own specifications  In this case  the responsibility lies with others  in relation to the maximum flow   litres  per day  the system capacity and retention times    e If we size the system  and a greater load is placed on the system by the addition 
18. rdance with this manual should connect the plumbing from the dwelling to the septic tank  The  septic tank is plumbed for 110mm  uPVC pipe  The pipe should be vented by means of a vent pipe above the  eaves of the house  A short length of pipe with flexible joints should be used immediately before and after the    tank to allow for movement between the tank and the pipe work     Note  water logged sites             The TricelUSeptic tank is not suitable to be used in a water logged site  Please contact the supplier of the system if       there are difficulties on site due to adverse water logging  Adequate drainage is important to improve wet sites     or sites with a high water table level  It is critical that water is removed from the area    8 1 Treatment of effluent liquid     The septic tank acts as a holding chamber and treatment of effluent is carried out in the percolation  area  Effluent may be disposed into any of any of the following means for treatment    e Drainage field  UK    e Drainage mound  UK    e Percolation area  Ire   The best disposal method can depend on a variety of site factors including percolation results  soil type     water table level and topography of the site  Please refer to the onsite engineer for further details   8 2 Distribution box     A distribution box and inspection chamber should be fitted between the tank and the percolation area  A  Distribution Box should be used to correctly construct the percolation trenches  The percolation tre
19. screening analysis the backfill material shall have no more than 5  by weight  passing 2 36 mm Sieve    Use of other than specified backfill and bedding materials will void the tank  warranty     Backfill material shall not be frozen or contain lumps of frozen material at any time during  placement           7 6 3 Top soil     Clean native top soil shall not contain rocks larger than 36mm on largest  dimension     Note  The use of geo textile barrier fabrics surrounding the primary backfill material is considered  good installation practice  The fabric must be chosen to allow the flow of water in and out of the    excavation but to prevent the movement of fine soil particles into the primary backfill material     7 6 4 Burial depth     Generally  the max depth from finished to the inlet invert level of the main shell should be no more  than 725mm  This may vary dependent upon ground water conditions     7 6 5 Loadings    If the tank is installed in an area where traffic or other superimposed loadings can be applied  consult  a structural engineer for the design of a reinforced concrete slab to prevent the load being transmitted to  the tank  or its concrete surround   If this slab is constructed immediately above the tank  it    should be separated from the concrete surrounding the tank by a compressible material     13       8  Plumbing the system     Do not  Plumb storm water  water  from roofs  drains  footpaths etc  into the Tricel septic tank  A competent  person in acco
20. seehducciesVonsnenstauearersnedaareraats 10  7 5 Deeper tank installation  amp  wet site installation  ee eseeeseeeeeeeeeseseseerseseeceserarseerreeeeteeeeeseeeeees 11  7 6 Plinth and backfill specifications    00    eee eee ee eeeeeeeeeseseaeersescecacacececaeseseseseseesenensseseseetsneentesnteateateases 12  8  Plumbing the Systeme sccsiccccc ssscscdin cies cssssaccnte che costecasaestnegs droienn srana Wepecarcnecssardutasseacslsbasastuesscacndvandsacctveadans 14  9  Finishing the garden to ground level    cence neeeeneneceeeeesenene neces eens nenecennenenenenenenneneneee 15  10  Mantena NCE isicccices cosets ccsucndeclescebinndesshensossessasabeielbbucaiiudids uuteetiasatstsioosbabbede isansa sana aasian taie iiei dessai aione 16  11  Operating CONGItIONS  20    cece esseeseeseeesescecscseseseseseseseeeessnscacacacscecesasasacacacasacasacasacasaesesseeseeteeesetees 17    It is important to read the full technical and installation guide prior to installation  This document should be  retained for the lifetime of the product and in the event of change of ownership be transferred to the new    owner        Precaution       Prior to installation  please consider finished garden level when installing the system  If you envisage that a  manhole riser extension may be required to ensure manhole lid remains above finished ground level  the system    must be installed with the appropriate excavation foundation and backfill to accommodate the riser  Please refer to    CE    Certif
21. tallation inspection     e Tanks should be subject to visual inspection prior to installation  e Check for  fractures to the shell or ribs  de laminations  scratches or abrasions deeper than 1 5mm  e Any damage should be notified to the delivery driver and or to your supplier    e Donot attempt to carry out any un authorised repairs  as this will invalidate the warranty on the tank    e Once the tank has been installed  we cannot accept any claims for damage    7 2 Quick installation guidelines     A dry site is one where the water table never rises higher than the base of the Tricel unit  A  wet Site is one where the water table may rise higher than the base of the Tricel unit  The    unit should never be installed where ground water can rise higher than the outlet pipe    All installations must be    Fit for purpose    to suit the on site conditions  which    will vary from site to site  This is the responsibility of the onsite contractor        Never roll the tanks  Tanks shall be lifted into position        The unit should be located as far away from the dwelling as is practically  possible considering topography and pipe work levels  Separation    distances must meet all National and Local regulations    Dig a hole circa 400mm larger than the system in plan        Remove any soft spots or boulders of significant size from the base or sides    of the excavation       Ground water must be pumped to give a dry excavation and excavation    lined with polythene  Provisions fo
    
Download Pdf Manuals
 
 
    
Related Search
    
Related Contents
  Zenith XBV 442 User's Manual  QHT Boiler User's Manual    MANUAL DE SERVICIO  Local  取扱説明書 - 加藤電機  Share claSS converSion and portfolio management user guide: All  TE-300 - CASIO  AquaLink® Touch™ - Pool Supply Club    Copyright © All rights reserved. 
   Failed to retrieve file