Home

Case Study--Field Implementation of Automated Torque-and

image

Contents

1. Pulling Out Of Hole while drilling drilling distance between hole and bit depth lass than 35 m e POOH Rotate Pulling Out Of Hole with rotation while drilling e RH Running In Hole while drilling e RIH Rotate Running In Hole with rotation while drilling e POOH Trip Pulling Out Of Hole while tripping tripping distance between hole and bit depth larger than 35 m e POOH Trip Rotate Pulling Out Of Hole with rotation while tripping e RIH Trip Running In Hole while tripping e RIHTrip Rotate Running In Hole with rotation while tripping e ROB Rotating Off Bottom while drilling e ROB Trip Rotating Off Bottom while tripping Model Calibration and Tuning Off bottom rotating values during back reaming and drilling were used to qualify correct model setup with static input data i e borehole geometry and trajectory information During the first part of casing or screen runs the drag model was checked and calibrated There were only three steps needed to confirm that a model is sufficiently well calibrated 1 To ensure that the rig data system bit or shoe tracking depth parameter was set in accordance with the drill pipe casing or tubing tally 2 To check that the running weight trend follows in parallel with a modeled friction factor curve If the real time values follow a different slope a unit system mismatch or faulty string weight configuration is most likely to be t
2. for this 9 5 8 casing run 12 IADC SPE 128243 Hookload t 40 80 120 160 200 240 s RIH Trip N RIH Trip Min 1000 2000 30004 E pa E a p Q D Q 40004 5000 4 6000 12 cH03 cH cHa1 on03 OH0 1 OH0 1 7000 Fig 9 Actual values for RIH Trip and RIH Trip Min over simulated curves for Manaia ERD 9 5 8 casing run 2 By creating reliable torque and drag reference charts for the field supervisors they were able to streamline operations and give clear hole conditioning guidelines to the driller e Definition of hook load limits while tripping Once a drag trend was established for a trip a hook load margin of 30 klbs was added to this friction factor trend line Then the drill pipe tally was updated with do not exceed hook load values per stand connection and passed on to the driller e Optimization of running string configurations For all screens to be lowered into the hole hook load simulation models were prepared by the engineers Then the limit friction factor trend curve causing the drill pipe to buckle helically anywhere along the running string profile was defined Further a stiffened running string including heavy weight pipe and drill collars was remodeled If the helical buckling limit friction factor was identified the field supervisors were informed with a basic hook load drag chart to identify as early as possible if and when to pick up additional heavy weight pipe and collars In cases
3. process By actively using the tool the expectation was to benefit from several advantages e Monitor wellbore condition and hole friction Time apply and monitor effect of hole cleaning measures Prevent lost time by avoiding pack off and stuck pipe situations Adjust running string configuration to overcome drag and avoid helical buckling as needed Plan trajectories to optimize reach of completion runs Pick the most economic and environmentally acceptable mud system for each hole section Minimize hidden lost time as much as possible Well Design Consistent capturing of quality pick up and slack off weights allowed the Maari well planners to calibrate the modeled hook load and drag charts in the best possible way This benefited the Maari field development as follows e Original plans considered the use of oil based mud systems in 16 hole sections Through engineered understanding of drag and a drilling sequence which allowed the most challenging sections to be drilled latest in the project this was ultimately reduced to only 5 reservoir sections Sections which were changed from SBM to WBM included 9 5 8 casing runs up to 3 000 m at max 75deg inclination On Maari synthetic based cuttings were loaded in skips and shipped ashore for disposal in a land farm Being able to revert back to water based mud systems on large 14 1 2 hole sections has greatly improved cuttings disposal cost and offshore logistics as well as reduced the risk of wait on
4. sign of hole degradation indicated by black line in left plot but not deemed critical by the operations team which decided to proceed operations 12 14 hole was drilled without troubles to section TD IADC SPE 128243 5 Torque kNm 5 10 15 20 25 30 35 40 45 50 L 1 L 1 li 1 1 1 rt J Depth m 2200 Fig 4 Torque plot for a 14 2 drilling run on MR3P8 T amp D Monitoring Workflow The workflow for the T amp D monitoring approach was clearly defined in the planning phase of the Maari field development Model Generation and Import The first step in the process is to model a set of simulated friction factor curves for the BHA that is going to be lowered into the hole For this purpose a T amp D simulation software is required which calculates the planned hook load and torque for the operations RIH POOH and ROB The following information is required as a minimum input e String configuration weight per foot OD length of all components Source BHA reports e Wellbore geometry cased and open hole diameters measured depths Source well reports and summary sheets e Planned trajectory and or actual surveys inclination azimuth MD Source survey and updated trajectory files from directional drilling company Mud weight Source daily mud reports Block weight Source real time sensor data stream Generation of hook load reference charts simulated curves To generate modeled hook load reference cu
5. swivel packing 10 IADC SPE 128243 Source Data Update Frequency One key requirement for the ADPM system is a sampling rate which is higher than one data point per ten seconds Nevertheless the T amp D relevant operations require a higher sampling rate for which a frequency of 1Hz is preferred As some operations can last for only 15 to 20 seconds a more representative amount of data is required for the median calculation of the stand per stand values Generally it is challenging to receive such a high sampling rate from the data providers at the rig site As the rig sensor system on the Maari offshore rig was capable of streaming 1 Hz data it allowed the T amp D tool to have a high amount of values available for the calculations which highly improved the quality and authenticity of the values presented to the users Depth Tracking One challenging issue encountered was related to the quality of the sensor signals for the channels hole and bit depth Bit tracking on standard rig data systems is a derived value from block position The system uses a hook load trigger to determine if the block travels empty or if it has the actual string attached If hook load exceeds the trigger limit bit position is changed as per the measured block position change As soon as hook load drops below that value bit tracking ignores any changes in block position The torque and drag system is affected adversely in three situations a While pulling out of hole th
6. weather down time e Good knowledge of actual hole friction factors allowed refocus of risk management efforts away from what the team has labeled excessive drag events Unable to run intermediate casing to TD Unable to run screens to TD and set ESP in planned tangent sections String pack off and stuck pipe events associated with poor hole cleaning e While drilling the first reservoir section the reservoir hole exited the producing formation and a low side sidetrack was required Pick up and slack off values gathered from the T amp D tool gave a good indication of current friction values and allowed making real time planning decisions on where to position the side track 8 IADC SPE 128243 what is the maximum acceptable dog leg to still be able to run the screened liner completion to TD e Similarly later reservoir sections were extended by up to 800m and screen runs and running string configurations were modeled to ensure successful landing of liner hangers Although possible as a contingency none of the wire wrapped screen strings needed to be rotated to get to TD e Well documented drag information from Maari enabled planning and approval of the Manaia ERD appraisal well MNIP4 which at approx 8km and MD TVD ratio of 4 was a step change over the most ambitious Maari wells of 4 8km and MD TVD ratio of 3 7 Maari friction factor results were used as planning basis for MN1P4 trajectory in particular its tangent section inc
7. SPE International IADC SPE 128243 PP Case Study Field Implementation of Automated Torque and Drag Monitoring for Maari Field Development M Niedermayr J Pearse and M Banks OMV New Zealand Limited G Thonhauser and P Zoellner TDE Thonhauser Data Engineering GmbH Copyright 2010 IADC SPE Drilling Conference and Exhibition This paper was prepared for presentation at the 2010 IADC SPE Drilling Conference and Exhibition held in New Orleans Louisiana USA 2 4 February 2010 This paper was selected for presentation by an IADC SPE program committee following review of information contained in an abstract submitted by the author s Contents of the paper have not been reviewed by the International Association of Drilling Contractors or the Society of Petroleum Engineers and are subject to correction by the author s The material does not necessarily reflect any position of the International Association of Drilling Contractors or the Society of Petroleum Engineers its officers or members Electronic reproduction distribution or storage of any part of this paper without the written consent of the International Association of Drilling Contractors or the Society of Petroleum Engineers is prohibited Permission to reproduce in print is restricted to an abstract of not more than 300 words illustrations may not be copied The abstract must contain conspicuous acknowledgment of IADC SPE copyright Abstract This case study presents a novel app
8. Time Rig Sensor Data to Improve Daily Drilling Reporting Benchmarking and Planning A Case Study Paper SPE 99880 presented at the SPE Intelligent Energy Conference Amsterdam The Netherlands April 4 Z llner P 2009 Automated Monitoring of Torque and Drag in Real time MS thesis Mining University Leoben Leoben Austria
9. al time torque analysis 6 IADC SPE 128243 When generating running weight charts for casing strings no centralization was considered in the models The casing strings used on Maari were mostly rigid type There was no additional drag per centralizer to be added to produce a good match between model and field data Even for casing strings equipped with spring type centralizers the actual recorded data did not show significant deviations from the modeled trend lines The output of the T amp D simulator needs to include a table listing the measured depth hook load and torque for several different friction factors Once these values are available they need to be pasted into a predefined template which can then be imported into the T amp D monitoring tool All these steps need to be done manually by the engineer in charge or the 24 7 support team tracking the ongoing operations The graphical output of the exported data can be seen in Figs 3 and 4 e RIH blue solid lighter with increasing FF e POOH red solid lighter with increasing FF e ROB green solid torque trending lighter with increasing FF drag bold line to indicate centre zero friction factor Once the models are imported and loaded on one of the screens for an imminent BHA run there is no further user interaction required as the actual values appear as the operations are conducted The list below shows the different operations that can be tracked with the T amp D tool e POOH
10. are recorded for every single stand while the rig crew is performing RIH POOH or ROB Out of the available data points the system filters and eliminates outliers and calculates the median value for each stand of pipe which is then visualized in real time on the value over depth plot This approach of limiting the data was implemented to prevent getting a confusing plot showing too many values overlaying each other and making trend analysis nearly impossible In addition start and end of BHA or casing runs had to be detected to allow further filtering of recorded data and trend comparison with a certain set of friction factor curves simulated for the detailed string components lowered into the hole In summary the following states and operations had to be detected by the ADPM system e RIH POOH and ROB T amp D operations on a stand per stand basis considering the difference between drilling tripping and running casing screens tubing e Hook load and torque during T amp D operations e Stands or joints of string moving up or down in the hole IADC SPE 128243 One filtered value of torque and hook load representing a T amp D operation for each stand or joint of pipe including the corresponding stand depth and reasonable trimming values to exclude acceleration forces caused by static friction e effects e Runs of tubu
11. both operational optimization such as avoidance of train wrecks minimization of hole conditioning avoiding picking up extra heavy weights or drill collars from the pipe deck and feasibility optimization of well design concepts such as rig selection whether casings need friction reducing technologies if casing floatation is needed which trajectories can be achieved if SBM or WBM is required Reliable friction factor analysis combined with drag trending is particularly critical for inclined and extended reach wells where operating parameters are often pushed to the limits of equipment material and string buckling As a consequence detailed monitoring of torque and drag is a key element in the successful construction of planned wells as well as in modifying plans for future wells Drag monitoring is already done in many locations and in a variety of ways Most of the methods applied rely on personal observation and interpretation and are therefore prone to inconsistency However these parameters are so important that a consistent and engineered approach is preferred to remove individual interpretation and associated inconsistencies The Maari field development in New Zealand is a development where torque and more importantly drag data would be critical to success in achieving planned objectives optimizing performance and adding significant value by making feasible development of some of the upside of the field IADC SPE 128243 3 The
12. d in the ADPM algorithm for the T amp D related operations This allows compensating such a phenomenon by simply adding or subtracting a predefined value from the calculated one On Maari this approach worked very well as the effect was not detrimental in the shallow near vertical sections In deeper more critical sections it also did not adversely affect the interpretation of results with regards to analysis of hole condition or matching of friction factor models In near vertical boreholes with little drag contribution to the overall hook load this may become a bigger issue The main purpose of the tool namely to track changes in ongoing trends will not be affected However direct comparison of friction factors from various wells rigs will become more unreliable Hook Load Calibration Issue Another calibration issue which became clearly visible with the drag plot is shown in Fig 7 below Whenever a trip was interrupted to slip and cut the drilling line the actual hook load values were shifted from the 0 3 to the 0 2 simulated friction factor trend curves once tripping proceeded This phenomenon confirmed the approach of monitoring trends with deviations thereof instead of relying on single absolute values Hookload t 100 120 140 1 8 Hook load shift after slip amp cut mo drill line 1800 5 Depth m 2000 2100 2200 2300 Fig 7 Hook load shift after slip and cut drilling line and change
13. e string weight drops below the hook load trigger whereupon bit tracking stops This is not critical as it occurs usually around 100 to 300m MD with BHA in safe hole and no adverse affects on the T amp D tool b After running casing the last tracked bit position is at or very close to the current well TD As the next rig operation is a trip in hole the bit position needs to be reset to surface If this is not done correctly the ADPM system assumes a bit on bottom condition and logs the BHA trip in hole as slide drilling As torque and drag values are only calculated while being off bottom tripping reaming during a drilling connection etc and not while making hole the T amp D model is rendered useless in such cases c A similar situation occurs after a roundtrip when the bit tracking stops at a bit position somewhere between 100 and 300m of hole depth When running a new assembly bit tracking will start at a different depth and results in a mismatch of actual and modeled hook load values Case a is not critical and does not need to be addressed further To avoid the adverse affects of cases b and c the driller needs to reset the bit depth to zero after a casing has been landed and set bit position to match pipe tally as soon as bit tracking starts to operate on trip in hole If this is not done or set to a wrong value the calculated torque and drag values are automatically linked to a wrong depth On Maari this happened quite frequently in th
14. e very beginning which did not allow comparing the actual values with the simulated ones due to a shift in depth In addition the hole depth was set back to the same depth as the bit while tripping into the hole Fig 8 This caused the system to wrongly detect drilling operations as the hole depth was increasing together with the bit These problems were solved by talking to the drillers and explaining them the impact if they do not set their bit depth correctly In addition manual corrections and recalculations have been made which allowed the engineers to perform their analysis once the trip in was finished Hookload t Time 2 0 G G 10 H RIH Trip MD Bit Depth Interrupted RIH curve due to 2000 4 incorrect depth tracking 2000 oN E 40004 4000 a Q a 6000 4 6000 x g 8 Interrupted RIH curve for a 5 1 2 screen run due to incorrect depth tracking 8000 4 Fi IADC SPE 128243 11 Automatic Detection of Casing Runs The problem with the incorrect depth tracking also influenced the automatic detection of tubular assembly runs Especially for casing runs where the bit depth channel was not reset prior to the subsequent trip in the ADPM rule was not always able to detect the correct start and end of the run In such cases it was necessary for the users to manually create a run or adjust the boundaries in the Runs Management Vi
15. ew Fig 2 Improvements for the automated detection of tubular assembly runs need to be implemented in order to make the system more robust against errors in sensor data channels Lessons Learned and Results The benefit gained from automated real time capturing of actual values and comparison with modeled hook load and torque can be grouped in two areas The Maari drilling campaign has benefited from both the future planning aspects as well as being able to make more immediate operations decisions 1 The quality of drag trending curves and good match with drag models showed lower friction values than anticipated The T amp D system also documented effective drag reduction by simple measures such as short intervals of circulating while running casing This allowed the drilling team to take a more aggressive approach to well operations and design e As a consequence it was possible to switch over from synthetic based to water based mud systems allowing a drastic reduction in skip and ship effort and cost e Manaia 1 was originally planned as a vertical well situated approximately 7km south west of the Maari wellhead platform location The vertical appraisal well was cancelled due to the excessive risk of waiting on weather downtime which might be encountered while moving the rig to the new location The low friction factors encountered while developing the Maari field allowed the drilling team to submit a plan to appraise the Manaia structure with an e
16. factors that made Maari such an ideal candidate for a new approach in T amp D monitoring were e Long and shallow wells e Strict environmental constraints reduction in use of SBM was a significant goal e All wells required screened completions to TD barefoot completions were not feasible due to the risk of loose sands being produced e Upside potential existed both in extending the planned base case wells as well as in drilling into additional structures further from the platform To benefit from operational optimization it was necessary to provide field and office people with an automated way of tracking torque and drag in real time To benefit from the feasibility and optimization of well design concepts it was necessary to provide just the engineers in the office with an automated way of tracking and recording torque and drag data In order to improve the monitoring process it was essential to make use of the rig sensor data combined with an automated algorithm recognizing the ongoing rig operations This improved approach of tracking T amp D in real time was presented by Kucs et al 2008 after its applicability was successfully proven during an OMV field test on two 12 000 ft near vertical wells in the Vienna basin The main principle behind the technique is a hook load and torque comparison of actual versus simulated values These actual values are captured in real time for different operations such as drilling tripping or running casing
17. he reason A faulty configuration can also occur if couplings ESP cable and clamps or other added weight is not included in the effective weight per foot of individual string components 3 To adjust the block weight input value for the model run to match actual and modeled values in the shallow section of a BHA or casing run This variation was never observed to be more than 5 klbs from actual block weight In many cases this happened due to additional weight from extra running gear i e casing fill up tool and casing elevators Often a shift in hook load values occurred after slipping and cutting the drill line see Fig 7 Field Implementation Setup This chapter gives an overview on all the required equipment needed on the offshore rig itself as well as in the onshore offices in order to run the T amp D monitoring tool Further the workflow between the engineers as well as the training procedures of the personnel is addressed Rig site Setup The rig site setup for the T amp D monitoring approach consists of three data acquisition boxes which are connected to the on site data provider units rig sensor system mud logger and directional driller The sensor data acquired for the system had to be exactly the same as that seen by the driller at his console It was very important that only one consistent set of numbers was used by everyone involved in the project Data acquired also had to be free from personal interpretation so that although s
18. hifts crews and project personnel changed consistent engineered data continued to be collected For this purpose the data set selected for the T amp D monitoring was the one of the rig sensor system as this is the one that is also available for the driller at his console Nevertheless the data from all three sources is collected as IADC SPE 128243 7 the T amp D tool can be run in combination with a real time data plotting software allowing analysis of additional data sources if a diverging trend is detected In addition two database and application servers are located at the rig collecting the sensor readings from the data boxes storing and replicating it to the onshore servers for the engineers and giving the personnel at the rig access to the results via the T amp D screens Hook load trends overlaying predictions at various friction factors were shown real time on a dedicated screen to the drilling supervisor at the rig site but the project team decided not to install such a screen for the driller Instead do not exceed hook load values were issued as a print out table on the string tally sheet Onshore Setup The onshore setup is very simple as it only requires one server where the replicated data from the rig site server is stored In order to access the results every engineer is provided with a T amp D installation together with real time data plotting software If installed on a laptop the operations can be tracked in real time f
19. lar assemblies start and stop times e Hook load for a certain amount of time after the string is released out of the slips to track differential pipe sticking Based of the automated detection and calculations of the ADMP system the following three plots can be presented to the user e Runs Management View Fig 2 e Surface Hook Load over Depth Fig 3 e Surface Torque over Depth Fig 4 k BJA Glia X Alke pr Time MD Bit Depth a 2009 09 12 00 00 2009 09 14 00 00 2009 09 16 00 00 SEE 00 2009 09 20 00 00 2009 09 22 00 00 2009 09 24 00 00 2009 09 26 00 00 500 1000 a E 1500 a a iit LI 2500 3000 Drilling Run 1 16 Casing Run Drilling Run 2 10 3 4 Casing Run Drilling Run 3 Liner Run Fig 2 Runs Management View allows tracking of TxD in real time as well as to manually adjust and create tubular assembly runs Hookload t Hookload t m 100 xa ri on am 40 r 40 art iii 160 am te l RIH RIH Trip x RIH Rotate POOH Trip h POOH 5004 OOS 1000 M 7 POOH Rotate POOH Trip RIH Trip 1000 4 20004 T i e ji AH i 5 150044 30004 a E IESi A g S 3 3 Ci ego i g 4 Q 2004 J ry 3000 5000 4 p i i 3500 HAL i 6000 4 ste 7 t k Fi 40004 X Adverse but not critical drag trend 4500 70004 Continued operations Fig 3 Drag plots for left two 12 drilling runs on Manaia ERD right MR1P7 lower completion run 5 1 2 x 6 5 8 NOTE Clear
20. lination The planning team was in a better position to evaluate drilling risks and associated operational downtime caused by hole drag or stuck pipe situations Because of the short planning to execution interval some technologies usually applied on ERD wells were not available For example the long lead time for casing floatation equipment prohibited the use of floatation technique to run the long 9 5 8 production casing The drilling team decided to move ahead with operations instead of waiting on the equipment This decision was only possible with a very good understanding of the friction factors to be expected and an accordingly designed well path Being able to assess expected downtime risks based on well documented data greatly benefited the AFE approval process Technical Difficulties Encountered Several problems were encountered during the first tests on the real time sensor data The most important ones to note are addressed below Pick Up and Slack Off Weight Cross over For several wells on which the T amp D tool was tested the following behavior of the POOH and RIH curves was observed while drilling and tripping at depths below 1 500 m Hookload t 25 50 ia bi is m L 1 e RIH Trip b nr cd Sog alg POOH Trip a v 500 kN y te CS i fe Oio S aa w ka E wA A A e rat See oy 3 a 1500 d e s t ee a perea Intersection of POOH and RIH Taso ane
21. n Manaia ERD was set at approximately 6 340 m with an inclination of 88deg at the shoe The tangent section of the well was drilled at 77deg inclination Based on friction factors seen for the Maari wells this angle would just allow casing running Any higher inclination than this would have resulted in gradual loss in running weight If drag increased the drilling crew was supposed to circulate through the fill up and circulation tool FAC tool which had been shown to drastically drop the drag values in Maari wells The lower part of the well trajectory had increased hole angles of 85deg in the geological landing tangent and built to horizontal in the reservoir Overall the casing run was executed as per plan with increased drag only observed in the lower build and hold section which required setting almost all casing weight down The string was tensioned with 100 klbs overpull followed by bumping the string down which established movement black circle in Fig 9 If the inclination in the tangent section had been larger all the running weight would have been lost prior to reaching TD whereas a smaller angle would have resulted in excessive drag in the lower section The T amp D tool captured this significant difference between start up friction versus recorded slack off friction Fig 9 below shows the actual values for RIH Trip average hook load value for each joint and RIH Trip Min minimum value recorded over a joint compared to the simulated curves
22. n from the data acquisition process In order to achieve these requirements several iterations were necessary to find out which method and plot to use Although there were a lot of possibilities discussed such as friction factor FF over depth delta hook load plots or tension and torque profiles field feedback clearly indicated a need to stick with traditional hook load and torque values versus depth plots While new visualization methods may enable further interpretation options display in a familiar format proved to be the most appropriate presentation technique Nevertheless a simple tool showing only the continuously measured values for hook load and torque plotted over depth was not an option It was required to clearly differentiate between the T amp D relevant operations RIH POOH and ROB rotating off bottom with a further distinction between drilling tripping and wellbore conditioning for different types of tubular assembly runs In order to achieve this goal the Automated Drilling Performance Measurement ADPM system introduced by Thonhauser 2004 and Thonhauser et al 2006 was used to detect these types of operations in real time As described by Z llner 2009 the first step in the development cycle was to design new operations recognition rules which are able to automatically detect and differentiate between the T amp D relevant operations by making use of the rig sensor readings In addition the hook load and torque readings
23. nfident decisions to swap from synthetic to water based mud in hole sections that industry experts have previously classified as border line casing floatation area e elimination of synthetic based mud in intermediate sections the overall environmental impact of the drilling campaign has been drastically reduced e planning a new extended reach well based on monitoring results has allowed appraising and future production for a satellite field otherwise likely stranded e the field application has also proven 24 7 support and maintenance of equipment far off service provider home base The case study also outlines technical difficulties encountered and how these were addressed during product testing and its first commercial field application Introduction Maari Field The Maari oil field was discovered in 1983 PMP 38160 is operated by OMV New Zealand Limited 69 on behalf of its joint venture partners Todd Maari Limited 16 Horizon Oil International Limited 10 and Cue Taranaki Pty Ltd 5 The permit contains the Maari discovery and is located close to another oil discovery the Manaia field in block PEP 38413 The initial development drilling campaign called for five production and three injector wells Sixteen of the sections were initially planned to be drilled with synthetic based mud partly due to the drag concerns in the highly deviated wells In 2 IADC SPE 128243 addition provision was made for the construction of further 4
24. on a stand per stand basis and automatically plotted against the measured depth of the bottom of the assembly The resulting trend quickly shows if the values are diverging from acceptable boundaries which could cause issues at a later stage in the trip This early and clear identification of potential future issues allows action to be taken before problems actually happen Wellbore conditioning operations can be optimized in advance based on the quality of the wellbore which is evaluated automatically without interfering with ongoing rig operations i e no dedicated rig time to take pick up and slack off values Purpose and Concept of Real time T amp D Monitoring The torque and drag monitoring system developed for the Maari drilling project had to be kept as simple and usable as possible The most important goals were to acquire and present data to prevent lost and reduce hidden lost time as well as to track wellbore condition in real time Presentation of the data had to be simple and intuitive to prevent incorrect assumptions and misinterpretations due to new visualization techniques In the beginning of the software development phase several different types of plots were assessed for their applicability at the rig site Another clear goal was to totally automate most of the tool s functions in a way that only a minimum of engineering intervention and assistance was required during the well construction process as well as to remove all interpretatio
25. r their valuable input and support for this work particularly in the development and testing phase of the system e ENSCO 107 management and crew for their support during rig up and system configuration as well as implementation e MD Totco technical support in enabling a 1Hz data update link from the rig data system e BHI and Halliburton Sperry for providing an uplink of critical down hole data e OMV offshore supervisors for providing useful feedback and their open minded acceptance of some trial and error experiments in optimizing the system in the best possible way 14 Nomenclature HWDP Heavy weight drill pipe DC Drill collar WHP Wellhead platform T amp D Torque and drag SBM _ Synthetic based mud WBM Water based mud TD Total depth FF Friction factor RIH Running in hole POOH Pulling out of hole ROB Rotating off bottom BHA Bottom hole assembly OD Outer diameter MD Measured depth TVD True vertical depth ERD Extended reach drilling References IADC SPE 128243 1 Kucs R Sporker H F Thonhauser G and Zoellner P 2008 Automated Real Time Hookload and Torque Monitoring Paper SPE 112565 prepared for presentation at the IADC SPE Drilling Conference Orlando Florida USA 4 6 March 2 Thonhauser G 2004 Using Real time Data for Automated Drilling Performance Analysis European Oil and Gas Magazine Edition 4 170 173 3 Thonhauser G Wallnoefer G Mathis W 2006 Use of Real
26. roach to capturing torque and drag trends real time while drilling complex and extended reach wells Data processing algorithms automatically process rig sensor data They recognize current rig operations and log drill string torque and drag parameters Data is automatically collected presented and shared without any exposure to human error or interpretation in data recording allowing engineered real time and longer term decisions to be made with accurate and consistent data The tool relies on updated torque and drag models but otherwise works without further input or drilling process interruptions and it does not require extra personnel on or off site The main purpose of the new system is to confirm hole condition The system acquires and displays well documented field and operation specific drag values On Maari this information has been used to make strategic decisions on mud systems critical casing runs running strings trajectories accessible targets and contingency planning The paper outlines the monitoring process and system support It will present actual results and detail how its use has aided planning drilling and logistics Field data will be presented in support of the examples listed below e minimized back reaming during drilling connections and overall reduced hole cleaning efforts e real time decisions on location need and quantity of HWDPs or DCs in the screen running strings avoiding rig time to pick up tubulars from deck e co
27. rom all over the world via a secured internet connection In addition to all these individual installations one multi screen environment is setup in the remote operating center which continuously shows the drag and torque trend curves allowing monitoring of the rigs operations Training and People Issues Prior to being used operationally on the first well only the office personnel was trained to varying levels as required One engineer was selected as the focal point who received full and detailed training over a period of one week Other engineers were given an introductory run through rather than full training In hindsight more training of the other engineers would have been beneficial Once all the office personnel were familiar with the system each of the offshore supervisors was trained at the rig site to the extent necessary to benefit from the real time data plots Another key training point was to eliminate the use of interpretive terms such as overpull which are prevalent and can be misleading Instead of traditional instructions such as do not pull more than 30k overpull instructions were issued phrased as follows hook load should not exceed 30 klbs above the predicted value on the 0 2 friction factor line at that depth Expectations and Results from Real time T amp D Monitoring Optimized Operations On Maari there was a large potential for the T amp D approach to assist in all phases of the well construction
28. rves a commercial drilling software package was used to produce multipoint tripping hook load analysis reports These reports were then exported into Excel format The modeling software requires the user to enter friction factor assumptions and operation modes At Maari a set of 5 friction factor combinations was generated for each operating mode per default The friction factor modeling was kept very simple as only one single friction factor was used for both open and cased hole sections In addition all friction was assumed to be translated from drag into torque when rotating the string The concept of using real time data to get feedback for the friction factor model relies on the understanding that well friction factors should not be misunderstood as pure material friction but also include feedback from hole geometry and hole condition Both needed to be considered when making operational decisions with tortuosity data available from survey information Special model refinement features i e for well tortuosity or for sections of a string having friction reducing devices attached were neither used for long term feasibility planning nor for real time data correlation Three operations were modeled for each set of 5 friction factors e Sliding in hole to reference slack off hook load values RIH e Sliding out of hole to reference pick up hook load values POOH e Rotating off bottom to reference rotating weight values ROB as well as reference for re
29. s curves while tripping A 4 t z e 4 B o 7 e a 250 oF Fig 5 Hook load intersection of POOH and RIH curves As Fig 5 indicates the curves for POOH and RIH while tripping intersect at a certain depth below which the hook load while pulling out is lower compared to the one while running in hole As this is in contrast to the physical laws and also because this phenomenon did not occur on every trip tracked further investigation was necessary The plot of sensor data shown in Fig 6 verified that this problem was not caused by the drag monitoring filters its hook load calculations or operations detection but that there must be a problem with the hook load sensor or measurement process itself It further shows that the hook load was constantly lower for the two times where the string was pulled out of hole red section compared to where it was run in hole blue section IADC SPE 128243 9 jo Je Je ao jo j2 j2 wo o jo jo ao j jo jo a jo x gt 9 j 2 E I e d 0 Bl EDIESIE a 3 2 2 E Se Ze x r RETE arat gegee 2222 g Siiaa d d o o o o losses jo o jo e22 wo N NEFFE jo vw W LI a d o o o o 3 3 E it ive So st o ite e F w Fig 6 Higher hook load while RIH compared to POOH In order to address this data phenomenon and make trend comparisons possible an additional parameter was include
30. t of hole were drilled without stuck pipe or pack offs although a total of 11 hole sections where switched from a SBM to a WBM system e Based on the concept discussed in this paper significant drilling efficiency improvements were achieved which could be quantified e It was possible to develop a software tool to support the drilling crew with automated torque and drag monitoring information in real time A key element for the success was the early inclusion of feedback from rig personnel in the development and the extensive field testing of the system prior to its use for this project e New workflows for the rig crew as well as the supporting engineers had to be developed to utilize the new tool to its maximum potential The traditional way of using hook load overpull as alarm value was replaced by a concept using overpull not exceeding 30 klbs above predicted value on the 0 2 friction factor line Training played a key role in changing and adopting the workflows of the team e Based on the experience gained a number of future improvements will further enhance the tools and workflows developed such as user interface improvements and optimization of system setup e Future enhancements are also expected from an improved way of displaying relevant data Acknowledgments The authors would like to thank e OMV and TDE for the permission to publish this paper and would like to recognize Mr Hermann Sporker and Mr Richard Kucs both OMV fo
31. wells at a later stage in the project life All these wells can be drilled from or tied back to the wellhead platform WHP Tiro Tiro Moana which is equipped with 12 drilling slots The waxy nature of the crude requires heating downhole on the wellhead platform as well as the FPSO Raroa to successfully transport the crude Location and Environment The Maari field within permit PMP 38160 is located in the Taranaki Basin offshore West Coast of the North Island in the South Taranaki Bight of Tasman Sea as shown in Fig 1 Water depth is approximately 101 3 m This location is directly exposed to intense weather systems in the Tasman Sea and is subject to high winds and seas The strongest and most frequent winds and swells are generally from the west to southwest Mean wind speed is about 35 km h in winter with sustained periods during the campaign over 110 km h Waves during the development drilling campaign were recorded above 14 m Winters are cooler and weather conditions more unsettled Mean daily minimum temperature in June is 5 5 C and mean daily maximum temperature in January is 21 8 C The nearest major settlement is on the coast at New Plymouth around 120 km northeast PMP 38160 Maarte Moki 1 PEP 38413 Fig 1 Maari field location in offshore New Zealand T amp D Project Introduction Torque and drag T amp D are two key parameters in the well construction process that deserve special attention as they drive
32. were excessive drag was observed the field personnel was advised to interrupt running the screens and discuss further options with town Drag charts for the stiffened string configuration were also prepared and sent to the rig e Improvement of back reaming on drilling connections While drilling ahead hole cleaning time per stand was minimized to ream the drilled section only once In addition reaming cycles were initiated when the pick up and slack off weights diverged significantly from an established trend line Towards TD the string was also rotated into the slips if required Ultimately the hole was properly cleaned while back reaming out of hole for casing or screen runs IADC SPE 128243 13 The figure below Fig 10 shows the improvements made on drilling connections for the Maari field development It plots the average time that was spent on treating the borehole reaming washing circulating while making a drilling connection for the Maari well sequence Drilling Wellbore Treatment Time per Connection Avg per Well 25 N a o an Average Wellbore Treatment Time per Connection min MR3P8 MR4P9 MR5P12 MR7P5 MR8P3 MR6P2 MR1P7 MR2P1 MR9P6 Fig 10 Average wellbore treatment time reaming washing circulating while making a drilling connection for the Maari wells Conclusions The following conclusion can be summarized e Utilizing this concept a total of 43 5km 142 700 f
33. xtended reach well drilled from the WHP Queries on operational risk due to drag stuck pipe and pack off during drilling and casing runs were adequately addressed by basing designs and mitigating measures on well documented field data supplied by the T amp D system e The extended reach well design pushed the expected drilling torque above the drill string s recommended connection make up torque Good accurate knowledge of the torque friction factors allowed the well to be confidently planned with a relatively simple torque management approach rather than the un engineered drastic and costly approach of changing out the drill string for a higher torque connection The relatively simple approach taken was the use of high friction dope which allowed the drilling team to increase the recommended make up torque and therefore be able to drill to a possible maximum depth of 8 500 m This depth was nominated by the geologists as the ultimate possible well length As a mitigating measure non rotating drill pipe protectors were run to counter high torque risks e As lesson learned from Manaia the highest torque observed was while drilling out the cement in the casing Although the torque was below the rated operating torque as well as rotating speed for the top drive this operation resulted in the motor to be damaged The torque drastically dropped again once the rust was removed and synthetic based mud cuttings coated the casing wall e The 9 5 8 casing o

Download Pdf Manuals

image

Related Search

Related Contents

H57 - Citizen  Katrin 953708 waste basket  Stamina Products 15-0200 User's Manual  ZUO 50090 Installation Guide  Handler 135/175 et torche H-10      Architectural Mailboxes 5100Z Installation Guide  Adam Audio ARTist 3  Fujitsu CELSIUS W410  

Copyright © All rights reserved.
Failed to retrieve file