Home
        Guide to the installation of PV Systems 2nd Edition
         Contents
1.       DTI Pub URN 06 1972       Preface to 2nd edition 2006    Since the first edition  2002  the guide has been updated to reflect the significant experience gained with   in the UK PV industry under the DTI solar PV grants programmes  Other major changes covered include     1 Engineering Recommendation G83 1 2003  issued to replace ER 677 1   1 additional guidance for off grid battery systems   1 guidance for larger systems connected under ER G59 1   1 Part P Building Control notification Requirements   ETSU Report No  ETSU S P2 00355 REP 1   Authors BRE  EA Technology  Halcrow Group  SunDog Energy   2nd Edition  Sundog Energy  Halcrow Group   Energy Saving Trust    Acknowledgments Thanks to the following for commenting on the drafts  IEE  HSE  ESD  Intersolar  NAPS Systems  NHBC  Dulas   CREST  DTI Engineering Inspectorate  EST  Solarcentury   Special thanks to Martin Cotterell   First Published 2002   2nd Edition 2006    The work described in this report was carried out under contract as part of the DTI Sustainable Energy  Programmes  The views and judgements expressed in this report are those of the contractor and do not nec   essarily reflect those of the DTI  This guide was originally prepared by BRE and others on behalf of the DTI   Every effort has been made to ensure that the information given herein is accurate but no legal responsibili   ty can be accepted by the DTI  BRE and their collaborators  for any errors  omissions or misleading statements       Crown Copyr
2.     For controllers with a separate battery sense function  a fused battery  sense cable can be installed     2 5 2 Battery over current protection  A battery stores significant energy and has the capacity to deliver large fault  currents  Proper fault protection must be provided     An over current device must be installed in all active  non earthed   conductors between the battery and the charge controller     The over current device  either a fuse or circuit breaker  must    e have a trip value as specified within the charge controller manual       be rated for operation at d c   at 12596 of the nominal battery voltage   e have an interrupt rating greater than the potential battery short   circuit current     The length of cable between the over current device and battery terminal  must be as short as practicable     2 5 3 Battery disconnection    A means of manual isolation must be provided between the charge  controller and the battery  either combined with the over current device  or as a separate unit  The isolator must be double pole  d c  rated and  load break  and the length of the cable between it and the battery must  be as short as practicable     Isolation is to be installed and the system designed so that the PV array  cannot directly feed the loads when the battery has been disconnected     Combined fault protection and isolation        Acircuit breaker provided for battery fault current protection may be  used to provide isolation  if it is rated as an isolat
3.    2 3 3 Inverters       Inverters must carry a Type Test certificate to the requirements of    SA  Engineering Recommendation G83 1 or comply with all other parts of ER   G83 1 unless specifically agreed by an engineer employed by or   appointed by the DNO for this purpose  and in writing     Note  A key safety consideration is that the PV system will disconnect when the  distribution system is not energised  This is to prevent the hazardous situation  of the photovoltaic system feeding the network or local distribution system  during a planned or unscheduled loss of mains  Such an event is termed   islanding  and presents a potential danger to those working on the  network distribution system  Type Tests established through ER G83 1 ensure  that an inverter is properly prevented from such islanding operation     Other considerations addressed by ER G83 1 include the prevention  of harmonics  EMC compatibility and d c  injection     In order to simplify the earthing requirement  an inverter with an isolating  transformer is recommended  see section 2 2 1  a    This would protect against the  possibility of a c  exciting the d c  side  and remove the requirement to earth the  array frame  but does not override any need to connect the frame to earth   for lightning protection purposes        The inverter must be capable of withstanding the maximum array       voltage and current as calculated in section 2 1 2  This must include  any initial overvoltage period which is a featur
4.    amp  d c        In Equipotential Zone     Note  freestanding ground mounted  or building roof  mounted arrays  away from building metalwork  will  normally not be within the equipotential zone  However  a  solar thermal system  or other building linked metalwork   installed within reach may extend the equipotential zone   outside the normal building envelope     Install  amp  bond to earth spike Bond direct to Consumer   Note  do not take PME out of Earthing Terminal    equipotential Zone   Note  Use 10mm  braid or equiv    Note  Use 10mm  braid or equiv        b     Equipotential Zone    is defined as a zone in which exposed conductive parts  and extraneous conductive parts are maintained at substantially the same  potential by bonding  such that  under fault conditions  the differences in  potential between simultaneously accessible exposed and extraneous conductive  parts will not cause electric shock     Extraneous conductive parts    are conductive  parts liable to introduce a potential  generally earth potential  and not forming  part of the electrical installation  such as a water pipe  outside tap  a metal  downpipe     anything conductive that is connected to    Earth    but not electrically  part of the system     c  PME   Protective Multiple Earthing     an earthing arrangement whereby the  supply neutral and earth are combined into a single conductor  Where the  incoming supply is PME  the majority of domestic supply arrangements   the PME  earth cannot be take
5.   PV Array d c  Junction Box   Danger   contains live parts  during daylight     Do not disconnect d c  plugs  and sockets under load    turn off a c  supply first     PV array d c  isolator   Danger   contains live parts  during daylight     Inverter   Isolate a c   and d c  before carrying  out work     PV system   main a c   isolator        See Section    2 1 12    2 3 3    2 3 2    Do not work on this equipment  until it is isolated from both mains  and on site generation supplies    Isolate on site generator at  Isolate mains supply at             4 3       PV Installation Guide    Appendix A          4 5 Operation  amp  maintenance manual  The user manual should include as a minimum the following information   System data    e    copy of the basic system information  e A single line electrical schematic                     of the manuals and data sheets for the following system components     m PV modules  m Inverter  m Other relevant product documentation     Test results  amp  commissioning data                   of the test  amp  commissioning documentation  see Appendix A  B  amp  C    e Table of inverter protection settings  under over voltage  under over  frequency  etc      Operation  amp  maintenance data       Procedures for verifying correct system operation    A checklist of what to do in case of a system failure   Shutdown isolation and startup procedures    Maintenance  amp  cleaning recommendations  if any    Considerations for any future building works ad
6.   i e  overvoltage protection       the junction or combiner boxes   Connected to inverter  serial No                                    Array insulation Resistance   Test voltage       Ref IEC 60364 713 04 Pos     Earth _        Equipment Required   Test method  Annex 1            Earth           Insulation resistance test device  Comments    Insulation gloves    Goggles     Safety boots      short circuit box  if required                 Appendix C  cont     References       Procedure    1  The test should be repeated for each Array as minimum  It is also possible to test individual strings  if required    2  Wear the safety shoes  gloves and goggles    3  Where the test is to be undertaken between Earth and short circuited Array positive and Array  negative cables   short circuit the cables with an appropriate short circuit junction box    4  Connect one lead from the Insulation Resistance test device to the array cable s  as per the NOTE  above    5  Connect the other lead from the Insulation Resistance device to Earth as per NOTE above   6  Secure all the test leads  eg with cable ties     7  Follow Insulation Resistance Test Device instructions to ensure the test voltage is according to  table 1 and readings in M Ohms    8  Follow Insulation Resistance Test Device instructions to perform the test    9  Ensure system is de energised before removing test cables or touching any conductive parts     Table 1       Test method System Voltage Test voltage Minimum Impedance   V
7.  a  live system  See requirements of Regulation 14 of Electricity at Work  Regulations 1989         As current limiting devices  PV module string circuits cannot rely on fuse  protection for automatic disconnection of supply under fault conditions   as the short circuit current is little more than the operating current  Once  established  a fault may remain a hazard  perhaps undetected  for a  considerable time         Good wiring design and installation practice will serve to protect both the  system installers and any persons subsequently coming into contact with  the system from an electric shock hazard  operator  owner  cleaner  service  engineers  etc      e Undetected  fault currents can also develop into a fire hazard  Without fuse  protection to clear such faults  protection from this fire hazard can be  achieved only by both a good d c  system design and a careful installation         PV presents a unique combination of hazard     due to risk of shock  falling   and simultaneous manual handling difficulty  All of these hazards are  encountered as a matter of course on a building site  but rarely all at once   While roofers may be accustomed to minimising risks of falling or injury due  to manual handling problems  they may not be used to dealing with the  risk of electric shock  Similarly  electricians would be familiar with electric  shock hazards but will not be used to handling large objects at heights     Hazards associated with PV installation are outlined in th
8.  and can get an electric shock  to earth  The electric shock voltage will increase with the number of series  connected modules  The use of insulated tools and gloves  together with insulating  matting to stand or sit on  can mitigate this hazard        PV Installation Guide    Installation Sitework          An electric shock may also be experienced due to the PV array developing a ground  leakage path  Good wiring practice  double insulation and modules of Class Il  construction can significantly reduce this problem  but in any installed systems   leakage paths may still occur  Any person working on a PV system must be   aware of this and take the necessary precautions     4 0 SYSTEM INSPECTION  TESTING  amp  COMMISSIONING  REQUIREMENTS  DOCUMENTATION  amp  LABELLING  4 1 Inspection and testing       Inspection and testing of the completed system to the requirements  A 74  of BS 7671 must be carried out and documented    Provision of this documentation is a requirement of Part P of the Building  Regulations  see section 2 4 2     The inspection and testing of a c  circuits is comprehensively covered within  BS 7671 and supporting technical guides  Inspection and testing  documentation typically comprises 3 forms     an installation certificate   which includes a schedule of items inspected and a schedule of test results     The inspection and testing of d c  circuits  particularly testing PV array circuits  requires special considerations  Appendix C covers the inspection an
9.  any installation being performed by a  non PV specialist     eg a PV array being installed by a roofer  Plug and socket  Y   connectors can also be used to replace a junction box  It is good practice to keep   Y  connectors in accessible locations and where possible note their location on  layout drawings  to ease troubleshooting in future        PV Installation Guide    Design                Connectors must be d c  rated     Connectors must have the same or greater voltage and current ratings  as the string d c  main cable to which they are fitted     A sign     Do not disconnect d c  plugs and sockets under load     turn off  a c  supply first    must be fixed next to connectors  except those that are  inaccessible to anyone except trained personnel in the course of PV  maintenance or fault finding     Connectors must not be used as the means for d c  electrical switching   see 2 1 12  as d c  arcs can cause permanent damage to some connectors     Note  Plugs used in this application can be damaged by arc currents if disconnected  under load  While connectors are sometimes suggested as an alternative to  specifying a d c  rated switch  such use is not permitted     Connectors should be touch safe  ie to a standard of ingress protection  not less than IP 21   Class II and shrouded  and be of a design totally  dissimilar in appearance to any connectors used for the a c  system     2 1 8 Other inline cable junctions   In general cable junctions will be either by an approved p
10.  are current   limiting devices     even under short circuit conditions  the output current of a  module will not rise above a certain level  Isc   Operating a module in short   circuit is in general of little consequence  indeed many charge controllers in  battery charging systems routinely short circuit an array output    For small systems  the simplest approach is to ensure that the string cables  are suitably rated such that they may safely carry the maximum possible fault  current  This method relies on oversizing the string cables such that the fault  current can be safely accommodated  Such a method does not clear the fault  but simply prevents a fire risk from overloaded cables     String fuses are required for systems of four or more strings     see string fuse  section for more information  For a system with string fuses  cables may    be sized by applying the standard voltage and current multiplication tactors     2 1 6 Main d c  Cable       For a system of N parallel connected strings  with each formed of M 4 74  series connected modules  d c  main cables must be rated as a minimum at    Voltage           X M x 1 15   Current  lsc stc  X N x 1 25    2 1 7 d c  Plug and Socket Connectors   PV specific plug and socket connectors are commonly fitted to module cables by  the manufacturer  Such connectors provide a secure  durable and effective  electrical contact  They also simplify and increase the safety of installation works   They are recommended in particular for
11.  are shown below to help  when reading this Guide  They should not be used for a particular installation    without taking into account the special circumstances of each individual installation           pieoq uopnquisip         U  GOW 9104 c      peas    uoneljejsur Bugsa    yun                         ur BOW eseud    o  uonoeoid            6GO  BIA peroeuuog     Ajddns                     Ss0 0E yijds  suspenu                                             sBuuis Ad ML                                                                                                                                                                                                                                                                                                                  wood jue d        ur UOREJJEJSU  Jun Aejdsip               Addns DY  wi       T  MAPS SR SRR AR ce REG BH   w    En fn vad p  ul ajqeinoas            p   J0 EJOSI           PE Sh So a as woos jued                     4001 uo uonejjeysui      uojoajoid dE  fpi a EM  mm       e mm  E  ET zzz       _ emn  m jem 1 2     zzz    mm mmm       er  em  a  a   e m        2 m  4 _    ea  NADA em mam              UOBN      S Ad                   Domestic    a        UOREJ EJSU     o e asnoy Bunsix3                Aiddns  ONG             Aun    FS HE  UMI ELO  yun jeuinsuo                                            yun 1euinsuoo                 ui            e noejoJd                             pejoeuuo                      
12.  cover  the possible increase in voltage current     In addition  some modules have an electrical output that is considerably higher  during the first weeks of operation  This increase is on top of that produced  by temperature irradiance variation  Typically  operation during this period will  take Voc  Isc  and nominal power output  well above any value calculated  using a standard multiplication factor  To avoid oversizing for this eventuality  the array could be left disconnected for that initial period     Refer to the manufacturer for this information     2 1 3 PV Array Design   Installations within the UK  using currently available G83 1 type approved  inverters  typically operate with array voltages in the range of 120 to 500Vd c    However  it is to be noted that in some circumstances an array design can be  implemented where the array is split into sub arrays with an open circuit voltage  of less than 120 V           PV Installation Guide    Design          Note  The reason for reducing below 120 Vd c  is that d c  represents a different  hazard to a c  While an a c  shock causes muscular spasms which may allow  the person being shocked to retract or withdraw  d c  causes a continuous  muscular contraction which may force the victim into contact for a longer  period  Risk data recommends reducing the potential shock level to below  120           if practicable  Although a shock of 120        is unlikely to kill  it  could cause the victim to lose balance or concentr
13.  during and after  the installation phase     The long term safety of the system can be achieved only by ensuring that the  system and components are correctly designed and specified from the outset   followed by correct installation  operation and maintenance of the system   Consideration of operation under both normal and fault conditions is essential in  the design stage to ensure the required level of safety  This aspect is covered in  the DESIGN section of this guide        PV Installation Guide    Introduction          It is then important to ensure that the long term safety of the system is not  compromised by a poor installation or subsequent poor maintenance  Much   of this comes down to the quality of the installation and system inspection and  testing regime  This is covered in the INSTALLATION section of this guide     Similarly  much can be done during the planning and design stage to ensure that  the installation is safe for the installers  In some circumstances the application of  the CDM regulations will be required   Projects that employ fewer than five people  on site  and that last less than 30 days  or involve fewer than 500 person days of  work are exempt   All key safety issues affecting the design and installation  process are discussed in the guide  The main safety issues are    e The supply from PV modules cannot be switched off  so special precautions  should be made to ensure that live parts are either not accessible or cannot  be touched during ins
14.  of  voltage and comprising all the conductors and other electrical and associated  equipment used to conduct electricity for the purposes of conveying energy to  one or more Customers installations  street electrical fixtures  or other Networks     Islanding Any situation where a section of electricity Network  containing  generation  becomes physically disconnected from the DNOs distribution Network  or User s distribution Network  and one or more generators maintains a supply of  electrical energy to that isolated Network     ROCs Renewable Obligation Certificates equivalent to 1MWh of PV generation       PV Installation Guide    Design          2 0 DESIGN   2 1 Design Part 1   d c  System  2 1 1 PV Modules   2 1 1 1 Standard Modules    Modules must comply with the international standards  IEC 61215 in the  case of crystalline types  or IEC 61646 in the case of thin film types   Modules must also carry a CE mark     The use of Class II modules is generally recommended  and strongly  recommended for array open circuit voltages of greater than 120 V     2 1 1 2 Building integrated products modules   These products should comply with IEC module requirements as above  If no   specific    IEC Certificate    is available  eg for a one off  bespoke product  a statement   and evidence from the manufacturer is required to prove general compliance    In addition  for    integrated products    where the PV forms part of the building   envelope  eg PV roof tiles   proof of compliance 
15.  selection and sizing  The selection of a battery is generally out of the scope of this document  However   some key considerations to be flagged are     e is the battery fit for purpose  i e  appropriately rated for its duties  In  the majority of cases a true  deep cycle  battery will be required   e does it have an adequate storage capacity and cycle life      is a sealed or vented battery more appropriate for the particular  installation    e will the battery be made up of series cells or parallel banks  While  series cells will generally give better performance  practical  considerations may influence the design  In general  though  banks  with more than four parallel units are to be avoided     The sizing of a battery is generally out of the scope of this document  However   for an effective charging regime where a PV array is the only charge source  the  battery would normally be sized so that the output of the PV array falls between  the manufacturer s maximum and minimum recommended charge rates     Charge discharge rates  C  are commonly expressed as an hourly rate derived from  the formula  Rate   Capacity  Ah    Time  h   For example  a C10 charge rate for a 500Ah battery would take place at 50A     Charge rates between C5 and C20 are often used in systems with vented lead  acid batteries  for example     2 5 7 Battery installation labelling       In an enclosed location  ventilation must be provided to battery WA  installations with an air inlet at low level and 
16.  string positive and negative parts     Note  While the installer will be handling live cables during the subsequent module  installation  because the circuit is broken at the d c  switch disconnector   there is no possibility of an electric shock current flowing from the partially  completed PV string  The maximum electric shock voltage that should ever  be encountered is that of one individual PV module     Where it is not possible to pre install a d c  isolator  eg a new build project where  a PV array is installed prior to the plant room being completed   cable ends   connectors should be put temporarily into an isolation box and suitably labelled   as per d c  junction box     section 2 1 9      Cables are to be well supported  especially those cables exposed  to the wind  Cables must be routed in prescribed zones or within  mechanical protection  They must also be protected from   sharp edges     3 3 3 Live working       If it is unavoidable to work in any enclosure or situation featuring     64  simultaneously accessible live PV string positive and negative parts  this   must be performed either by utilising insulating gloves  tools  insulating   materials for shrouding purposes and appropriate personal protective   equipment  see Regulations 4 4  14 and 15 of Electricity at Work   Regulations 1989  HSE HSG 85  and BS EN 60903 and BS EN 60900  or by   covering the PV array  or by working at night  with appropriate task   lighting   When covering PV panels during instal
17.  to Note  2 in G83 1    For the connection of small embedded generators with a rating  greater than 16A per phase the DNO may choose to use this Engineering  Recommendation if it is considered to be more appropriate than G59 1  For  example the connection of a 5kVA PV array or a 10kVA Wind Turbine     This  would however need to be agreed in advance and in writing with the DNO     e Larger installations under G59 1     Written approval from DNO to be gained  prior to works  Commissioning in conjunction with DNO engineer  or as  required by DNO     1 5 Note on Layout   This guide is split into two main parts  the first detailing issues that need to be  addressed during the design phase of a project  and the second covering  installation and sitework  It is important to note  however  that many    design     issues covered in the first section may have a significant impact on the practical  installation process covered in the second     Throughout the guide the following format has been adopted to show the levels  of authority for each guideline   Bold text in blue against a shaded box with two ticks indicates  mandatory and or broadly recognised requirements   must       Text in blue with one tick indicates recommended practice     should         Text marked as notes and in italics indicates explanatory material        Introduction    PV Installation Guide       Commercial building    b     1 6 Ready Reference to the Guide    Example schematics for the two main types of system
18.  to fault currents flowing though the d c  system  Two key problems need  addressing     overloaded string cables and significant module reverse currents   both of which can present a considerable fire risk     Fault analysis shows that the maximum fault current flowing in a string cable  to be  N  1  x Isc  A system of three or fewer strings cannot generate sufficient  fault currents to present hazardous module reverse currents  Hence with three  or fewer strings  fuses can be omitted providing that string cables are suitably  rated  Such a method does not clear the fault  but simply prevents a fire risk  from overloaded cables     The installation of string fuses can provide protection against fault currents  in all other cases  While some fault combinations are less likely than others   in order to provide full protection of all cables and modules     string fuses  are required in both the positive and negative legs of the string cabling    See section 2 1 5      Note  As in section 2 1 9 it is required that some suitable means of electrical  isolation be provided  This will also enable engineers to separate out individual  strings for testing and tracing faults  A system fitted with suitable removable  string fuses provides an ideal way to accomplish this  Thus  while it may not  be necessary to fit string fuses on an array formed from two or three strings   their use may still be beneficial     2 1 11 Blocking Diodes  Blocking diodes are not commonly used in a grid conne
19.  tonii            MENINOOKL  TTENN  The SSEG installation complies with the relevant sections of Engineering Signature   Date  Name  BLOCK LETTERS      FOR CONSTRUCTION  Recommendation G83 1      being the person s  responsible tor the construction of the electrical installation  as indicated by mylour signatures below   particutars of which are de        scribed above  having exercised reasonable sk  l and care when carrying out the construction hereby CERTIFY that the construction work for which liwe have  been responsible is to the best of my our knowledge and bebet in accordance with BS 7071   amended to  dato  except for the  departure    if any  detailed as foliows        Protection settings have been set to comply with Engineering    a    The protection settings are protected from alteraton except by prior written       The extent of liability of the signatory is limited to the work described above as the subject of this Cerificate        agreement between the DNO and the Customer or his agent For CONSTRUCTION of the instafason  Signature  Safety labels have been fitted in accordance with section 6 1 of Engineering Name  BLOCK LETTERS         FOR INSPECTION  amp  TESTING  Recommendation G83 1 We beng the person s  responsible for the inspection  amp  testing of the electrical installation  as indicated by    4  sv rei ate Ta prod rasan wl and caro wen Cary eu e wget ei ay CER IFY that the work for which Uwe  have been responsible is to the best of my our knowledge and 
20.  uo UOREJ EJSU     Bi           Ad S Buis   TA               2 BUIS          Ad    wajsAs 2                                        uonej ejsul  2 e                           uonisod  Jjo ur aqeinoas   elod ejqnop   10JEJOSI uie                                i       Yo      uonelejsul                                  2048105                       oo                  pauuoosp                         PV Installation Guide    Design          1 7 List of Terms    PV cell basic PV device which can generate electricity when exposed to light such  as solar radiation    PV module smallest completely environmentally protected assembly of  interconnected PV cells    PV string circuit in which PV modules are connected in series  in order for a PV  array to generate the required output voltage    PV array mechanically and electrically integrated assembly of PV modules  and  other necessary components  to form a d c  power supply unit    PV array junction box enclosure where all PV strings of any PV array are  electrically connected and where protection devices can be located if necessary    PV generator assembly of PV arrays    PV generator junction box enclosure where all PV arrays are electrically  connected and where protection devices can be located if necessary    PV grid connected system a PV generator operating in    parallel    with the  existing electricity network    PV string cable cable connecting PV modules to form a PV string  PV string fuse a fuse for an individual PV stri
21.  where electricity supplies are  usually by long overhead lines  Surges may be induced on both the PV array  conductors or the a c  cables leading to the building     2 2 4 1 Lightning Protection Systems    Where there is a perceived increase in risk of direct strike as a consequence  of the installation of the PV system  specialists in lightning protection  should be consulted with a view to installing a separate lightning  protection system in accordance with BS 6651     Note  It is generally accepted that the installation of a typical roof mounted  PV system presents a very small increased risk of a direct lightning strike   However  this may not necessarily be the case where the PV system  is particularly large  where the PV system is installed on the top of a tall  building  where the PV system becomes the tallest structure in the vicinity   or where the PV system is installed in an open area such as a field     If the building or dwelling is fitted with a lightning protection system   LPS   a lightning protection installer should be consulted as to whether  in  this particular case  the array frame should be connected to the LPS  and  what size conductor should be used     Note  In some cases it may be possible to forgo bonding to the LPS if the array  frame is sufficiently far away from it  A system for determining whether  it is necessary can be found in BS 6651        Code of Practice for Protection of  Structures against Lightning     Alternatively  consult the inst
22. CDM Regulations    with regard to the design  installation  operation  maintenance  decommissioning and  disposal of PV installations in buildings  It also provides a commentary on the UK  legislative framework with particular reference to CDM Regulations  hazards and risks  associated with PV installations  and PV issues that must be addressed in the Health and  Safety Plan and Health and Safety File        i Draft IEC 62446 Ed 1    Grid connected PV systems   Minimum system documentation   commissioning tests and inspection requirements      Note  This standard will define the minimum information and documentation required to  be handed over to a customer following the installation of a grid connected PV system   This document also describes the minimum commissioning tests  inspection criteria and  documentation expected to verify the safe installation and correct operation of the system   This document is not written for AC module systems or systems that utilize energy  storage  e g  batteries  or hybrid systems     1 Guide CE72  Installing small wind powered electricity generating systems   Energy  Efficiency Best Practice in Housing  2004  Note  A companion Guide for small wind systems 500W to 25kW     1 Draft IEC 62257 7 2 Technical Specification     Recommendations for small renewable  energy and hybrid systems for rural electrification     Part 7 1  Generators      Photovoltaic arrays  Note  This is a draft Technical Specification not a Standard  but includes much use
23. G83 1      The scope has been extended in this 2nd edition to provide some guidance on  larger systems and off grid battery installations     Mechanical design of the PV array is not within the scope of this document  BRE  digest 489    Wind loads on roof based Photovoltaic systems     and BRE Digest 495     Mechanical Installation of roof mounted Photovoltaic systems     give guidance in  this area     1 2 Standards and Regulations   Any PV system must comply with Health and Safety Requirements  BS 7671  and  other relevant standards and Codes of Practice  Much of the content of this guide  is drawn from such requirements  While many UK standards apply in general  terms  at the time of writing there is still relatively little which specifically relates to  a PV installation  However  there are two documents which specifically relate to  the installation of these systems that are of particular relevance     e Engineering Recommendation G83 1  2003      Recommendations for the  connection of small scale embedded generators  up to 16A per phase  in  parallel with public low voltage distribution networks   e      Guidance Note 7 to BS 7671   Special Locations  Section 12 Solar  Photovoltaic  PV  Power Supply Systems  ISBN 0 85296 995 3  2003     1 3 Safety   From the outset  the designer and installer of a PV system must consider the  potential hazards carefully  and systematically devise methods to minimise the  risks  This will include both mitigating potential hazards present
24. allers of the LPS     Where an LPS is fitted  PV system components should be mounted away  from lightning rods and down leads   see BS 6651   For example  an  inverter should not be mounted on an inside wall that has a down lead  running just the other side of the brickwork on the outside of the building     2 2 4 2 Surge Protection measures    All d c  cables should be installed to provide as short runs as possible  and  positive and negative cables of the same string or main d c  supply should  be bundled together  avoiding the creation of loops in the system    This requirement for short runs and bundling includes any associated  earth bonding conductors     Long cables  eg PV main d c  cables over about 50 m  should be installed  in earthed metal conduit or trunking  or be screened cables such as mineral  insulated or armoured     Note  These measures will act to both shield the cables from inductive surges and   by increasing inductance  attenuate surge transmission  Be aware of the need  to allow any water or condensation that may accumulate in the conduit or  trunking to escape through properly designed and installed vents     Most grid connect inverters have some form of in built surge suppression   however discrete devices may also be specified     Note  To protect the a c  system  surge suppression devices may be fitted at the  main incoming point of a c  supply  at the consumer s cut out      To protect the d c  system  surge suppression devices can be fitted at th
25. an outlet at the highest  point in the room or enclosure     Sufficient ventilation is needed to remove battery gases  It is particularly important  in the case of vented lead acid units as hydrogen is given off during charging      and a concentration of more than 4  creates an explosion hazard  Ventilation  also prevents excessive heat build up     BS 6133  Safe operation of lead acid stationary batteries  gives a procedure for  calculating ventilation requirements     Battery banks must be housed in such a way that  BS 6133    e access can be restricted to authorised personnel   e adequate containment is assured   e appropriate temperature control can be maintained    Battery terminals are to be guarded so that accidental contact with persons  or objects is prevented     The ideal operating temperature for a lead acid battery is around 25  C   temperatures significantly above or below this will lead to reduced lifetime and  capacity  Indeed  at very low temperatures  discharged batteries may freeze and  burst  at high temperatures  thermal runaway can occur in sealed batteries     Items which could produce sparks  e g  manual disconnects  relays  should not be  positioned within a battery box or directly above one     Battery gases are corrosive  so cables and other items inside a battery enclosure  need to be corrosion resistant  Sensitive electronic devices should not be mounted  in  or above  a battery box     To ensure proper load charge sharing in a battery bank made 
26. artment before starting the work    The contractor registers under a Competent Person Scheme  as approved by the office   of the deputy prime minister    Note  An electronic version of the form is available at the Local Authority Building Control           website www  link2content co uk uploads buildingnotice 202005 20unprotected           1  doc  and it can be submitted using their  Submit a Plan  scheme  www  labc services co uk buildingregs default asp        e Engineering Recommendation G83 1  Sept 2003     Recommendations for the  connection of Small scale Embedded Generators  up to 16A per phase  in parallel  with Public Low Voltage Distribution Networks    Energy Networks Association  2003    www energynetworks org dg01 asp  Note  This simplified connection route applies to    type tested    inverters for systems up to  about 5kVA per phase  see sect 2 4 1   Prior notification of the Distribution Network  Operator  DNO  is not required for    single    installations  but is required for    multiple    single  phase installations  It refers to the Electricity Safety  Quality and Continuity  Regulations  ESQCR   2002  Draft prEN 50438    Requirements for the connection  of micro cogenerators in parallel with public low voltage distribution networks    is  a European version  which once issued  will also cover systems up to 16A         e Engineering Recommendation G59 1     Recommendations for the connection of  Embedded Generating Plant to the Regional Electricity Compa
27. ation  and so expose them  to another risk  e g  losing balance when working on a roof     Double insulation  insulation comprising both basic  amp  supplementary  insulation  International Electrotechnical Vocabulary IEV 195 06 08    appropriate barriers and separation of parts must be applied to all  systems with an open circuit voltage of  gt 120 Vd c      Class Il insulation on the d c  part of the PV system  even if less than  120 Vd c   is strongly recommended     Note  Double insulation of the d c  circuit  d c  wiring  connectors etc  greatly  minimises the risk of creating accidental shock current paths  eg via damaged  cable coming in contact with PV frame  and the risk of fire  Having a PV  junction box with negative and positive parts well separated and protected by  barriers  or better still by utilising separate enclosures  significantly reduces the  potential shock risk to the installer     Note  Though commonly used for the main d c  cable  e g  for long d c  cable runs  in exposed locations such as on flat roofs  or where cable is buried   sheathed  and armoured cable with two or more singly insulated cores does not  constitute double insulated cable  though in this application it is acceptable as  it affords a good degree of fault risk reduction  see 2  1 4  2C      2 1 4 d c  Cables     General  2 1 4 1 Cable sizing    Cables must be rated  as a minimum  to the voltage and current ratings  derived using the multiplication factors in 2 1 2     Standard de ra
28. be rated for operation at        x M x 1 15   e The string fuse must have a tripping current which is less than 2 x Isc   stc  and the string cable current carrying capability  whichever is the  lower value     Note  The requirement for omitting string fuses in arrays with three or fewer series  connected strings is valid for the majority of silicon crystalline  conventional   modules  However  when applying this rule  a system designer must verify  with the manufacturer that the module is capable of withstanding a reverse  current of 2 x 1 15 x Isc        w          w       PV Installation Guide    Design       For some modules  the reverse current rating provided by the manufacturer  may permit more than three parallel connected strings to be installed without  string fuses  In such cases  the number of strings that may be connected   in parallel without the use of fuses is calculated by ensuring    Ir  gt  I  ste  x  N 1  x 1 25   where Ir is the maximum permitted reverse current quoted by the module  manufacturer     The use of fuses or MCBs  miniature circuit breakers  is permissible provided  they meet the above criteria and are rated for use in an inductive circuit and  will operate for currents flowing in either direction through the device     For a system of three or fewer strings with NO string fuses  string cables  must have a minimum current rating of  Isc  stc  x  N 1  x 1 25    Note  In a PV array formed from a number of strings  fault conditions can give rise 
29. belief in accordance with  date  except for the                      if ary  detailed as follows        The SSEG installation complies with the relevant sections of BS 7671 and an     gt     Comments  continue on seperate sheet if necessary           The extent of liability of the signatory is limited to the work described above as the subject of this Cerificate   For INSPECTION AND TEST of the instalabon      Signature   Name  BLOCK LETTERS                Name Signature Date                Pagelof      note 5           Appendix B  cont      Appendix B  cont            PARTICULARS OF SIGNATORIES TO THE ELECTRICAL INSTALLATION CERTIFICATE  note                of supply  to be detaded  on attached schedules     PARTICULARS OF INSTALLATION REFERRED TO IN THE CERTIFICATE 79        ree se m wora  Means of Earthing  Distributors tacy C  Maximum demand  load     Details of installation Earth Electrode  where applicable     Instaliation Type Electrode resistance 10 earth    ne            rodis   tape etc     vee C58  To incoming water and or gas service          other elements    Main Switch or Circuit breaker  No  of poles Current rating     AURI erret qoem ementi top Fuse rating or setting      Rated residual operating current lan   MA  and operating time of ms  at lpn       ory mhara on RCD m maie are und an 4 min ras    COMMENTS ON EXISTING INSTALLATION  I  f ces c a sera o wasters sey Saanen 763           SCHEDULES  note 2    The attached Schedules are part of this document and 
30. ct system as their function  is better served by the installation of a string fuse  Historically  they were specified    to prevent any reverse current flowing through parallel connected strings  much as   a string fuse is intended to do  However    e the installation of a blocking diode results in a small voltage drop across the diode    e blocking diodes may fail as a short circuit and therefore require regular testing   Specification of string fuses can provide sufficient reverse current protection  without the problems and power losses associated with a blocking diode     If specified  a blocking diode must have as a minimum a reverse voltage  rating of 2 x Voc x number of modules in the string  stc      2 1 12 d c  Switch   The d c  switch provides a means of manually electrically isolating the entire PV  array  Such electrical isolation is required during system installation and subsequent  system maintenance or repair work  It should be located adjacent to  or integrated  into the inverter     An additional d c  switch may be specified for systems with long d c  cable runs   typically at the point of cable entry into the building      so as to provide a means  of isolating the cable for safety reasons or maintenance works     e The d c  switch must be double pole     to effectively electrically isolate  both PV array positive and PV array negative   e The d c  switch must be rated for d c  operation     Note  Switching a c  is less demanding than switching d c      wit
31. d testing of  PV array circuits and documentation to be provided     4 2 Array commissioning tests   PV array string performance tests are recommended to verify performance as  a check for faulty modules  These will entail additional tests over and above  those set out in BS 7671 and the associated guidance  This may require a  means of measuring solar radiation for larger installations if radiation levels  are changing during testing     Simultaneous monitoring of the solar radiation can present practical  difficulties unless the system has a radiation sensor installed and its   cable is accessible at the place where testing is carried out  If radiation  conditions are reasonably constant  ie no sudden obscuring of direct  sunlight by clouds   comparing one open circuit string voltage with another  will identify faulty strings     Guidance on commissioning tests can also be found in appendix C     4 3 E R  G83 1 and G59 1 commissioning   As noted in section 2 4 1 in order to satisfy the requirements of the distribution  Network Operator  various tests and documentation needs to be provided  See  section 1 4 and 2 4 1 for more details on the process to be followed depending  on the size of system     Compliance with DNO requirements will include           w       w       PV Installation Guide    Installation Sitework       e Inverters should be programmed such that the automatic protection  system operates at    m Operating voltage greater than 264 V phase to neutral  m Opera
32. ditions   Transmission of lightning induced surges   Electromagnetic interference    Two types of connection to earth need consideration   a  Earthing of exposed conductive parts  eg  the array frame   b  System earths     where an array output cable is connected to earth    The earthing arrangements recommended in this guide are based upon those  given in BS 7430  BS 6651 and BS 7671     2 2 1 Earthing of exposed conductive parts  array frame    The majority of installations will utilise class Il modules  class Il d c  cables  amp   connectors and be connected to the mains via an inverter with an isolation  transformer  This approach is recommended and permits the array frame to be  left floating     Notes to terms used in diagram    a  Isolating transformer  An isolating transformer is one in which the input  and output windings are electrically separated by double or reinforced insulation   see BS 3535     While the hazards presented by an array frame reaching the system d c  potential  may be significant  the potential fault shock current is typically much less than  that from a mains fault  Hence it is the electrical separation of the mains from the  d c  using an isolating transformer that is the key determining factor when  assessing the requirement for array frame earthing     Array Frame Earthing Decision Tree       Class 11 modules   and    Class Il Cables  connectors ions  amp  Junction Boxes  and    Isolation Transformer in Inverter    Note  to BS 3535 between a c
33. durable                                                          Circuit Description          Method of protection against indirect contact   Equipment vulnerable to testing                     Description of Work     Deviations from Wiring Regulations and special notes     See notes on schedule of test results    E                 Appendix C  cont   Appendix C  cont        Part 2  PV system   commissioning test sheets   Sheet 2  array test  Field insulation test procedure   as in draft IEC                 PV Array Test Report   d c  circuits Safety   Report reference No  Contractors name and address   Read and make sure you understand this procedure before you start any work     Insulation testing is an electric shock hazard   use caution when performing the testing   nstalllation address     NM      Do not perform the test before you have received practical training       Limit the access to the working area       Do not touch and take measures to prevent any other persons to touch any metallic surface  lest date Signature with any part of your body when performing the insulation test           Do not touch and take measures to prevent any other persons to touch the back of the  Description of work under test Test instrument s  module laminate or the module laminate terminals with any part of your body when       performing the insulation test              Whenever the Insulation test device is energised there is voltage on the testing area  The  equipment is to have to hav
34. e  inverter end of the d c  cabling and at the array     To protect specific equipment  surge suppression devices may be fitted  as close as is practical to the device           w          PV Installation Guide    Design       2 3 Design Part 3     a c  System  2 3 1 a c  Cabling    An inverter supplied from a PV array must preferably be installed in a   dedicated circuit in which        nocurrent using equipment is connected  and     no provision is made for the connection of current using equipment   and   e no socket outlets are permitted     An inverter must not be connected by means of a plug with contacts  which may be live when exposed     Where an electrical installation includes a PV power supply system  without at least simple separation between the a c  side and the d c   side  an RCD installed to provide fault protection by automatic  disconnection of supply must be type B RCD according to BS EN 60898   IEC 60755  amendment 2      a c  cables are to be specified and installed in accordance with BS 7671     The a c  cable connecting the inverter s  to the consumer unit should   be oversized to minimise voltage drop  A 196 drop or less is recommended   However in larger installations this may not be practicable or economic  due to the very large size of cable resulting  In this case the designer  should minimise voltage drop as far as possible and must remain within  voltage drop limits as prescribed by BS 7671     Note  When generating  the voltage at the inverter 
35. e DTI s free manual      Photovoltaics in Buildings     Safety and the CDM Regulations           PV Installation Guide    Installation Sitework             3 3 d c  Circuits   installation  3 3 1 Personnel    All persons working on the live d c  cabling of a Photovoltaic  PV  system  must be experienced trained in working with such systems and fully  acquainted with the voltages present on that system in particular     Plug and socket connectors simplify and increase the safety of installation works      see section 2 1 7  They are recommended in particular for any installation being  performed by    non PV specialist     eg a PV array being installed by a roofer     3 3 2 Sequence of works   All d c  wiring should if possible be completed prior to installing a PV array   This will allow effective electrical isolation of the d c  system  via the d c   switch disconnector and PV module cable connectors  while the array is  installed  and effective electrical isolation of the PV array while the inverter  is installed     Typically this would require an installation of        d c switch disconnector and d c  junction box es    e String array positive and negative cables     from the d c   disconnect junction box to either end of the PV string array    e PV array main cables from d c  switch to inverter     This should be carried out in such a way that it should never be necessary  for an installer to work in any enclosure or situation featuring  simultaneously accessible live PV
36. e automatic auto discharge capability                                                           String 1 2 3 4 n  Array Module NOTE REGARDING TEST METHOD  Quantity   Two test methods are possible   Array parameters Vocisto  a  Test between Array Negative and Earth followed by a test between Array Positive and Earth        b  Test between Earth and short circuited Array Positive  amp  Negative  Protective Device Type   Where the structure frame is bonded to earth  the earth connection may be to any suitable  Rating  A  earth connection or to the array frame  where the array frame is utilised  ensure a good  d c  Rating  V  contact and that there is continuity over the whole metallic frame    Capacity  kA     For systems where the array frame is not bonded to earth  eg where there is a class      m installation  a commissioning engineer may choose to do two tests  i  between Array cables  Wiring Type  gt  and Earth and an additional test ii  between Array cables and Frame   Phase mm  Earth ay   For Arrays that have no accessible conductive parts  eg PV roof tiles  the test should be between  Array cables and Building Earth  String test  Test method  Annex 2 Voc  V  Test Zone Preparation   Isc  A   Sun 1  Limit access to non authorized personnel   Polarity check 2  Isolate the PV array from the inverter  typically at the array switch disconnector   Earth continuity  where fitted  3  Disconnect any piece of equipment that could have impact on the insulation measurement       R   
37. e of some module types     Note  It is common practice for an inverter array power ratio to be less than unity    see section 2 6 1   but it is important to ensure that the inverter cannot be  damaged by array peak output  This is particularly the case with some thin  film PVs that have an initial overvoltage period  See also notes regarding  inverter mpp operating range in section 2 6 1        PV Installation Guide    Design             It is recommended that Inverters carry a sign    Inverter   isolate a c  and d c   before carrying out work        2 3 4 a c  Fault Current Protection    Short circuit protection for the dedicated feeder cable from the inverter s   must be provided at the consumer unit  This electrical protection is to be  specified and installed in accordance with the requirements of BS 7671     Note  Short circuit protection is not required at the inverter output   If using an RCD for a c  side earth fault protection  see section 2 3 1     2 3 5 Metering   Inverter output meter  As a minimum  metering at the inverter output  should be installed to display record energy delivered by the PV system   kWh   In addition it is highly recommended for instantaneous power  output  kW  to be displayed  This will not only add to customer  satisfaction it should lead to more effective fault detection  A kWh meter  approved by OFGEM is recommended as it may facilitate payment on ROCs  and other Electricity company scheme payments as they become available     The meter s
38. e part of a PV installation from a PV cell to the d c  terminals of the PV  inverter    a c  side part of a PV installation from the a c  terminals of the PV inverter to the  point of connection of the PV supply cable to the electrical installation    Simple separation separation provided between circuits or between a circuit and  earth by means of basic insulation    Inverter Isolating Transformer where the input  amp  output windings are  electrically separated by double or reinforced insulation    Isolation A function intended to cut off for reasons of safety the supply from all   or a discrete section  of the installation by separating the installation or section  from every source of electrical energy     Isolator  Disconnector A mechanical switching device which  in the open  position  complies with the requirements specified for isolation  An isolator is  otherwise known as a disconnector  A disconnector is otherwise known as an  isolator     Equipotential Zone where exposed conductive parts and extraneous conductive  parts are maintained at substantially the same voltage potential    PME     Protective Multiple Earthing where the supply neutral and earth are  combined into a single conductor    Distribution Network Operator  DNO  The organisation that owns or operates  a Distribution Network and is responsible for confirming requirements for the  connection of generating units to that Network     Electricity Network An electrical system supplied by one or more sources
39. e voltage and current requirements of the d c  system   the maximum values that could occur need to be assessed  The maximum  values originate from two PV module ratings     the open circuit voltage  Voc   and the short circuit current  Isc  which are obtained from the module  manufacturer  The values of Voc and Isc provided by the module manufacturer  are those at standard test conditions  stc      irradiance of 1000 W m   air mass  1 5 and cell temperature of 25  C  Operation of a module outside of standard  test conditions can considerably affect the values of Voc stc   Isc stc      In the field  irradiance and particularly temperature can vary considerably from  stc values  The above multiplication factors allow for the maximum values that  may be experienced under UK conditions     All other module types   All d c  components must be rated  as a minimum  from    a  Specific calculations of worst case Voc and Isc  calculated from  manufacturer s data for a temperature range of  15  C to 80  C and  irradiance up to 1250 W m2   b  A calculation of any increase in Voc or Isc over the initial period  of operation  This increase is to be applied in addition to that  calculated above     Note  Some types of PV modules have temperature coefficients considerably  different to those of standard mono  and multi crystalline modules  The  effects of increased irradiance may also be more pronounced  In such cases  the multiplication factors used for crystalline silicon modules may not
40. ening an  enclosure is fully aware of this     A readily accessible disconnection device shall be provided to isolate  individual strings  Isolation shall be provided in both positive and negative  string cables     Note  String isolation shall be achieved by any suitable means such as appropriately  located plug and socket connectors or removable string fuses  Any such isolation  should not be carried out with the system under load     The short circuit protection afforded by the cable installation throughout the rest  of the d c  circuit needs to be maintained in the construction and makeup of the  d c  junction box   See IEC 60536 and IEC 61140      It is recommended that short circuit protection shall be achieved by    e Fabrication of the enclosure from non conductive material   e Positive and negative busbars adequately separated and segregated  within the enclosure and or by a suitably sized insulating plate  or  separate positive and negative junction boxes    e Cable and terminal layout such that short circuits during installation  and subsequent maintenance are extremely unlikely     2 1 10 String Fuses  For a system of N parallel connected strings  with each formed of M series  connected modules     String fuses must be provided for all arrays formed of four or more strings   Fuses must be fitted in both positive and negative string cables for all strings     e The string fuse must be rated for d c  operation at the fault  energies present   e The string fuse must 
41. entification may be  omitted  Binding and sleeves for identification purposes shall comply with  BS 3858 as appropriate     2 1 5 String Cables  A string is a circuit in which PV modules are connected in series  in order for  a PV array to generate the required output voltage     String Cables String Cables    N Strings   connected  in parallel        Main d c   Cable M modules per string     connected in series        For a system of N parallel connected strings  with each formed of M series  connected modules  string cables are to be rated as follows        WV a  Array with no string fuses  of three or fewer strings only   Voltage            X M x 1 15  Current  Isc stc  X  N 1     1 25    b  Array with string fuses  Voltage  Vocst X M x 1 15  Current  lc  X 1 25    The sizing process for string cables in arrays with three or fewer series connected  strings is valid for the majority of silicon crystalline  conventional  modules   However  when applying this rule  a system designer must verify with the  manufacturer that the individual modules are capable of withstanding a reverse  current of 2 x 1 15 x Isc  See section 2 1 10 for further information     Note  PV module string circuits cannot rely on conventional fuse protection for automatic  disconnection of supply under tault conditions  This is because the short circuit  current is little more than the operating current     a fuse would simply not operate     A photovoltaic cell acts as a current source  hence PV modules
42. ful  guidance and explanation of international best practice for installation of PV systems     1 BS 6133 1995     Code of practice for Safe operation of lead acid stationary batteries     Note  This includes guidance on design  operation  amp  maintenance of battery systems     i BSI PD 6484 1979     Commentary on corrosion at bimetallic contacts and its alleviation     Note  This includes guidance on the selection of metals for mechanical design of arrays    1 BS 476    Fire tests on building materials and structures     1 BS 6399    Loading for buildings  Code of practice      1 BS 5534    Code of practice for slating and tiling  including shingles        i BS 3535    Specification for safety isolating transformers for industrial and  domestic purposes       1 BS 60947    Specification for low voltage switchgear and controlgear       1 BS3858    Specification for binding and identification sleeves for use on electric  cables and wires       i PD 6484    Commentary on corrosion at bimetallic contacts and its alleviation       Note  Information on the current Government s Grant scheme    Low Carbon Buildings  Programme    can be found on the Energy Saving Trust website www est org uk            DTI Sustainable  Energy Programmes    Do not work on this equipment  until it is isolated from both mains  and on site generation supplies    Isolate on site generator at             Isolate mains supply at    Sample Dual Supply Label G83 1    
43. h an a c  supply  the  voltage passes through O V many times a second  A switch must be rated to break  d c   an equivalent a c  rated switch is not acceptable or safe     e The d c  switch should be load break rated  the use of non load break  switches is not recommended      e The d c  switch must be rated for the system voltage and current  maxima as calculated in section 2 1 2     e The d c  switch  or switches  must be labelled as  PV array d c   isolator     with the ON and OFF positions clearly marked  Switch  enclosures must also be labelled with    Danger   contains live parts  during daylight     All labels must be clear  easily visible  constructed  and affixed to last and remain legible for as long as the enclosure     w  w  w       PV Installation Guide    Design          Note  A PV array is unusual in that it cannot be turned off     terminals will remain  live at all times during daylight hours  It is important to ensure that anyone  opening an enclosure is fully aware of this     An MCB may be used as a d c  switching device provided it meets all the above  requirements  The use of an MCB will provide protection against overcurrent  and  so the MCB  rating must be carefully chosen so as not to operate falsely for  switching surges and transients     2 2 Design Part 2   Earthing and Lightning Protection  Connection of parts of a PV system to earth affects     The electric shock risk to people in the vicinity of the installation  The risk of fire under fault con
44. hould be located where the consumer can readily observe it     Building Export meter  Although not directly part of the PV system  in order to  enable payment on exported electricity  a kWh export meter approved by OFGEM  with appropriate meter reading may be required  The appropriate Electricity  Supplier should be contacted to find out any particular requirements and to  arrange for its fitting     2 4 Design Part 4   Design Approval   2 4 1 DNO approval   A mains connected PV installation generates electricity synchronised with the  electricity supply     Installers are obliged to liase with the relevant distribution Network   Operator  DNO  in the following manner    e Single installation covered by G83 1     notification at or before day of  commissioning followed by G83 1 paperwork  G83 1 appendix 3   within 30 days    e Multiple installation covered by G83 1   application to proceed  G83 1    appendix 2   On commissioning     notification and appendix 3 as above     Note  For single installations of slightly greater than 16A attention is drawn to Note  2 in G83 1    For the connection of small embedded generators with a rating  greater than 16A per phase the DNO may choose to use this Engineering  Recommendation if it is considered to be more appropriate than G59 1  For  example the connection of a 5kVA PV array or a 10kVA Wind Turbine     This  would however need to be agreed in advance and in writing with the DNO     e Larger installations under G59 1   Written appro
45. ight 2006       Contents       1 0 INTRODUCTION  1 1 Scope  1 2 Standards and regulations  13 Safety  14 Parallel generation  15 Note on layout  1 6 Ready reference to the guide  17 List of terms    2 0 DESIGN    2 1 Design part 1     d c  system  2 1 1 PV modules  2 1 1 1 Standard modules  2 1 1 2 Building integrated products modules  2 1 2       system   minimum voltage and current ratings  2 1 3 PV array design  2 14 d c cables     general  214 1 Cable sizing  2 1 4 2 Cable type and installation method  2 1 5 String cables  2 1 6 Main d c  cable  2 1 7 d c  plug and socket connectors  2 1 8 Other inline cable junctions  2 19 d c  Junction box  2 1 10 String fuses  2 1 11 Blocking diodes  2112 d c  switch    2 2 Design part 2     earthing and lightning protection  2 21 Earthing of exposed conductive parts  array frame   2 22 System earthing  d c  conductor earthing   2 23 Inverter earthing  2 24 Lightning and surge protection  2 2 5 Lightning protection systems  2 2 6 Surge protection measures    23 Design part 3     a c  system  2 31 ac  cabling  2 3 2 a c  switch disconnector  2 3 3 Inverters  2 34       fault current protection  2 3 5 Metering         N O Ui Ui ur Ul    10    10  10  10  10  10  11   12  12  12  13  15  15  16  16  17  18  19    20  20  22  22  22  22  23  24  24  25  25  26  26       Contents    Introduction          2 4 Design part 4     design approval  2 4 1 DNO approval  2 4 2 Planning permission  2 4 3 Building Regulations   part P  electrical safe
46. ion device        A fuse assembly provided for fault current protection may be used to  provide isolation if it has readily removable fuses  eg fuse unit with  disconnect mechanism        w       w          PV Installation Guide    Design          2 5 4 Cables in battery systems   The requirements set out in the main sections of this guide apply    Note  In some circumstances  a voltage drop greater than that in section 2 1 4 1  may be justified on economic grounds    In addition     All cables must have a current rating above that of the relevant over  current device  nearest downstream fuse   circuit breaker   Cable current  ratings are to be adjusted using standard correction factors for  installation method  temperature  grouping and frequency to BS 7671     2 5 5 PV String cable and fuse ratings    String cables  upstream of the charge controller  must be rated to the  trip current of the nearest downstream device plus the rating as  calculated in section 2 1 5     A PV battery system must be designed such that the string cable  string fuse  design and specification reflects that fault currents may come either from the  array itself  from the battery or from both  Again  cable current ratings are to be  adjusted using standard correction factors for installation method  temperature   grouping and frequency to BS 7671     Note  Specification  amp  labelling for the PV cables  junction boxes  connectors  etc  should be as in the main sections of the guide     2 5 6 Battery
47. irements   Virtually all domestic PV installations will fall under the scope of Part P  Part P  requires the relevant Building Control department to be notified and approve the  work  There are two routes to comply with the requirements of Part P     e Notify the relevant Building Control department before starting the  work  Documentation will be required and a site inspection by a  Building Control officer may occur  Building Control charges may apply        w       w       PV Installation Guide    Design              Where a contractor is registered with a Competent Person Scheme  as  approved by the office of the deputy prime minister   Building Control  can be supplied with relevant documentation after the work is completed   Documentation is self certified under the Competent Person Scheme  and a site visit by Building Control is not normally required     Part P also reinforces the requirement for the provision of an Electrical Installation  Certificate  to the requirements of BS 7671      see section 4 1     Note  A copy of the Building Notice    notification form can be found on the Local  Authority Building Control website www labc services co uk     Note  At the time of writing  there are no    defined scope    competent persons  schemes to cover the installation of PV systems  Until a PV defined scope scheme is  available  full scope schemes are applicable     2 5 Battery Systems   This section of the guide covers the additional requirements where a battery forms  
48. jacent to the PV array   eg roof works  to avoid potential damage or shading of the PV array     Warranty  e Warranty Information    G83 1 INSTALLATION COMMISSIONING CONFIRMATION FORM  This form is courtesy of the Energy Networks Association  ENA  and can be  downloaded from www energynetworks org word ER  G3 1  Appendix  3 doc    Engineering recommendation G83 1 SSEG installation commissioning  confirmation   Confirmation of commissioning of a SSEG unit connected in parallel with the public  distribution network   in accordance with Engineering Recommendation G83 1   One Commissioning Pro forma per installation is to be submitted to the DNO     Site details       Property address  inc  post code        Telephone number       Customer supply number  MPAN        Distribution Network Operator  DNO        Contact details       SSEG owner       Contact person       Contact telephone number       SSEG details       Manufacturer and model type       Serial number of SSEG       Serial number version numbers of  software  where appropriate        SSEG rating  A  and power factor   under normal running conditions        Maximum peak short circuit current  A        Type of prime mover and fuel source       Location of SSEG unit within the  installation          Location of multi pole isolator                Appendix A  cont   Appendix B       Installer details ELECTRICAL INSTALLATION CERTIFICATE  Installer Note  This certificate is courtesy of the Institution of Engineering and Technol
49. lation  the covering must   be opaque  cover the whole array and be well secured     A temporary warning sign and barrier must be posted for any period  while live PV array cables or other d c  cables are being installed     Note  Covering a PV array can provide a means to prevent the need for live working   In practice  however  this is often difficult due to the practical problems of  keeping the array covered as the installation proceeds and protecting the  covering from the effects of the weather     3 3 4 Shock hazard  safe working practices   It is important to note that  despite all the above precautions  an installer  or service engineer may still encounter an electric shock hazard     Always test for the presence of voltage of parts before touching any part  of the system    Where a residual electric shock hazard is encountered  live working  practices must be adopted  see above      An electric shock may be experienced from a capacitive discharge     a charge may  build up in the PV system due to its distributed capacitance to ground  Such effects  are more prevalent in certain types of modules and systems  namely amorphous   thin film  modules with metal frames or steel backing  In such circumstances   appropriate and safe live working practices must be adopted     An example of where such hazards may be encountered is the case where an  installer is seated on earthed metal roof wiring a large PV array  In such  circumstances the installer must touch the PV cabling
50. lug and socket connector  or contained within a d c  Junction Box  see below   However in certain limited  circumstances it may be necessary for an in line cable junction to be made  eg  soldered extension to a module flying lead  although this should be avoided if at  all possible     Note  Great care needs to be applied in the design and installation of in line junctions   Where unavoidable  such junctions need to maintain the    double insulated     nature of the cables as described in section 2 1 4  eg by the use of two layers  of appropriately rated adhesive lined heat shrink sleeving   and be provided  with appropriate strain relief  Such junctions would typically be done off site   prior to works  using fittings and tools appropriate to the cable to be jointed     2 1 9 d c  Junction Box   If there is more than one string  the d c  junction box is normally the point at  which they are connected together in parallel  Junctions need to be made using  high quality connectors  typically screw terminals  The box may also contain string  fuses and test points     The d c  junction box must be labelled as    PV array d c  junction box     and  also labelled with    Danger  contains live parts during daylight     All labels  must be clear  legible  located so as to be easily visible  and durably  constructed and affixed to last     Note  A PV system cannot be turned off     terminals will remain live at all times  during daylight hours  It is important to ensure that anyone op
51. mended before the next inspection is stated on Page 1 under    Next Inspection        This Certificate is intended to be issued only for a new electrical installation or for new work associated with an alteration   or addition to an existing installation  It should not have been issued for the inspection of an existing electrical installation   A    Periodic Inspection Report    should be issued for such a periodic inspection  The Certificate is only valid if a Schedule of  Inspections and Schedule of Test Result are appended     Schedule of inspections     a  Protection against both direct and indirect  contact    0  SELV  note 1        Limitation of discharge ot energy   b  Protection against direct contact   note 2      6 insulation of ive parts           Barriers or enciosures  Obstacles  note 3   Placing out of reach  note 4           Prevention of mutual detrimental influence     te  Proximity ot non electrical services and other influences           Segregation of band 1 and band It circuits      band 11  insulation used            Segregation of satety circuits  Identification   I  w    LI  b  Presence of danger notices and other warning notices         Labeling of protective devices  switches and terminals       0 identification of conductors    Cables and conductors        a  Routing of cables in prescribed zones or within  mechanical protection            Connection of conductors          Erection methods          Selection ot conductors for current carrying capaci
52. n outside the equipotential zone  This is to prevent the  potential shock hazard should the supply neutral ever be lost        PV Installation Guide    Design          2 2 2 System earthing  d c  Conductor earthing     The bonding to earth of any of the current carrying d c  conductors is not  recommended  However as in the note below  earthing of one of the live  conductors of the d c  side is permitted  if there is at least simple separation  between the a c  side and the d c  side  including in the inverter     Note  In some countries it has been the practice to bond one part of the d c  current  conductors to earth  eg earth connection at midpoint of PV string or earthed  d c  negative   or for performance reasons on certain types of modules to  earth the d c  positive  Due to the increased possible earth fault paths  and  possible problems with commonly available European inverter types and  internal earth fault detection circuitry  such practice should only be made  when unavoidable  any connections with earth on the d c  side should be  electrically connected so as to avoid corrosion      2 2 3 Inverter Earthing    The inverter must be treated as standard electrical apparatus and  earthed as per BS 7671 if Class 1     2 2 4 Lightning and surge protection   Lightning can cause damage either from a direct strike or from surges due to a  nearby strike  Induced surges are the more likely cause of lightning damage in the  majority of installations  especially in rural areas
53. n proof   Array frame correctly fixed and stable  Roof fixings weatherproof  Cable entry weatherproof                            Protection against overvoltage   electric shock  Live parts insulated  protected by barrier   enclosure  placed out of reach or Class Il             Array frame equipotential bonding present  only relevant if required   Surge protection devices present  only relevant if required    RCD provided  only relevant if required    Frame correctly integrated with existing LPS installation                         d c  system       Physical separation of a c  and d c  cables   d c  switch disconnector fitted  to IEC60364 712 536 2 2    d c  cables   protective and reinforced insulation  only relevant if required    All d c  components rated for operation at max d c  system voltage  Voc stc x 1 25   PV strings fused or blocking diodes fitted  only relevant if required                             Address Location of distribution board        a c  system       a c  isolator lockable in off position only  Inverter protection settings to local regulations             Labelling  amp  identification   General labelling of circuits  protective devices  switches and terminals  to IEC60364 6 61   PV system schematic displayed on site   Protection settings  amp  installer details displayed on site   Emergency shutdown procedure displayed on site   a c  isolator clearly labelled   d c  isolator   junction boxes suitably labelled   Signs  amp  labels suitably affixed and 
54. ng  PV array cable output cable of a PV array    PV d c  main cable cable connecting the PV generator junction box to the d c   terminals of the PV inverter    PV inverter device which converts d c  voltage and d c  current into a c  voltage  and a c  current    PV supply cable cable connecting the a c  terminals of the PV inverter to a  distribution circuit of the electrical installation    PV a c  module Integrated module inverter assembly where the electrical interface  terminals are a c  only  No access is provided to the d c  side    PV installation erected equipment of a PV power supply system    PV Standard test conditions  stc  test conditions specified for PV cells and  modules  250C  light intensity 1000W m2  air mass 1 5     PV Kilowatts peak  kWp   units for defining the rating of a PV module where    kW generated at stc    PV self cleaning The cleaning effect on inclined PV systems from rain and wind  etc    PV Charge Controller A device that provides the interface between the PV array  and the battery    PV MPP Tracker Maximum Power Point Tracker     the d c  input stage of an  inverter designed to maximise the input from the array    Voc stg  Open circuit voltage voltage under standard test conditions across an  unloaded  open  PV module  PV string  PV array  PV generator  or on the d c  side  of the PV inverter    Isc stcy Short circuit current short circuit current of a PV module  PV string  PV  array or PV generator under standard test conditions    d c  sid
55. ng of the array and consequently at a poor  point on the inverter efficiency curve depending on the inverter  inverters are  typically less efficient at low power levels      PV array  inverter ratios from 1 1 to 1 0 8 are commonly applied in the UK   though in certain circumstances and depending on the inverter used  ratios    outside this are sometimes utilised  NB  Inverter power is taken to be maximum  steady state a c  power output      Guidance on inverter   array sizing can be obtained from the inverter  manufacturers     typically from system sizing software     Inverter mpp range   An inverter must be able to safely withstand the maximum  array voltage and current as stated in section 2 3 3  However  when chosing the  most appropriate inverter  for inverter performance purposes and when  considering the matching of an array to the mpp range of an inverter  an  assessment can be made as to whether a narrower temperature band  e g   10 c  to 70 c  maybe acceptable and appropriate for that particular site     2 6 2 System performance    The output of a PV system depends on many factors such as orientation  pitch   shading and geographical location     Estimating exact annual performance of a grid connected PV system is difficult   however as a rule of thumb   a south facing  inclined plane  unshaded array in the  UK can be expected to generate on average 750 kwh per kWp installed per year   Please note that this can be a conservative figure     Note  These figures are t
56. nies    Distribution  Systems      Electricity Association  1991   www energynetworks org dg01 asp  Note  This is the Electricity Industry Recommendation for connection of generators  It is  applicable if the inverter is not covered under G83 1        e IEC 61215 Building Control Approval    Crystalline silicon terrestrial photovoltaic   PV  modules     Design qualification and type approval     www iec ch  Note  This is the International standard for crystalline PV  It specifies requirements for the  design qualification and type approval of terrestrial photovoltaic modules suitable for  long term operation in general open air climates  as defined in IEC 60721 2 1  It       References       determines the electrical and thermal characteristics of the module and shows  as far as  possible  that the module is capable of withstanding prolonged exposure in certain climates     e IEC 61646    Thin film terrestrial photovoltaic  PV  modules     Design qualification  and type approval     www iec ch  Note  This is the International standard for thin film PV  It specifies requirements for the  design qualification and type approval of terrestrial thin film photovoltaic modules suitable  for long term operation in moderate open air climates     e        61730 1    Photovoltaic  PV  module safety qualification   Part 1  Requirements  for construction  amp  IEC 61730 2    Photovoltaic  PV  module safety qualification    Part 2  Requirements for testing     www iec ch  Note  Part 1 is F
57. nt  pvgis pv  PVGISOEuropean European Joint Research Centre  http   re jrc cec eu int   Communities  2002 2006 pvgis pv  PVGISOEuropean Communities  2002 2006    Shading     Shade makes a big impact on the performance of a PV system  Even  a small degree of shading on part of an array can have a very significant impact  on the overall array output  Shade is one element of system performance that  can be specifically addressed during system design     by careful selection of array  location and layout and in the electrical design  string design to ensure shade  effects only one string      Module temperature     An increase in module temperature results in a decrease  in performance  eg 0 596 per 1 C above stc for a crystalline module   Sufficient  ventilation must be provided behind an array for cooling  typically a minimum  25mm vented air gap to the rear   For building integrated systems  this is usually  addressed by the provision of a vented air space behind the modules  On a  conventional pitched roof  batten cavity ventilation is typically achieved by the use  of counterbattens over the roof membrane and by the installation of eaves and  ridge ventilation     Note  It may be possible to omit counterbattens with some integrated PV roofing  products   roof construction  This is acceptable where there is test data  showing that a specific integrated PV product and associated roof  construction provide a similar PV cell temperature performance to a roof with  a ventilated c
58. oc stc x 1 25                          Array positive  amp  negative 120V 250V 0 25 MO  shorted together  lt 600V 500V 0 5MQ   lt 1000V 1000V 1 MQ  Separate tests to Array 120V 250V 0 25 MO  positive and Array negative  lt 600V 500   Voc stc 0 5MQ   min  100V       lt 1000V 1000   Voc stc 1 MQ     min  100V                             Test voltage adjusted to prevent peak voltage exceeding module or cable rating    FURTHER READING    e BS 7671  2001  Requirements for Electrical Installations  IEE Wiring Regulations    Sixteenth Edition  incorporating Amendments   ISBN  0 86341 373 0   www iee org publish books WireAssoc    e IEE Guidance Note 7   Special Locations   2nd Edition   ISBN 0 85296 995 3   www iee org publish books WireAssoc  Note  IEE Guidance Note 7   Special Locations  Chapter 12 covers  Solar photovoltaic   PV  power supply systems  as a  special location  as defined in IEE Regs  The guidance is  based on IEC 60364 7 712     Requirements for special installations or locations      Solar photovoltaic  PV  power systems            e Part P  Electrical safety    Building Regulations   www odpm gov uk index asp idz 1130906  Note  From 1st January 2005  people undertaking electrical work in homes and gardens  in England and Wales have had to follow new rules in Building Regulations  Virtually all  domestic PV installations will fall under the scope of Part P   There are two routes to comply with the requirements of Part P     Notify the relevant Building Control dep
59. ogy  and can be downloaded from www theiet org publications  A schedule of items  inspected  together with a schedule of test results  are to be included as part of  this certificate           Accreditation Qualification       Address  incl post code        Form 2 FomNo  2    ELECTRICAL INSTALLATION CERTIFICATE  notes 1 and 2   REQUIREMENTS FOR ELECTRICAL INSTALLATIONS   BS 7671  IEE WIRING REGULATIONS   Telephone number DETAILS OF THE CLIENT  note 1     Contact person          Fax number       E mail address          Information to be enclosed       Final copy of system schematic       SSEG Test Report  Appendix 4  or web address if appropriate  not necessary if already    provided e g  under stage 2 connection  FON eg Va pirata          dian Hi ow iced un ta cota ny    Signatures below   particulars of which are described  above  n             e M my   eA fw dose      NUS Y PM                                   eter  tn bt ol puke ed nef rrr wih BS 7671   dato  except for the departures    any  detaled       Computer print out  where possible  or other schedule of protection settings    Details of departures from BS 7671  Regulations 120 01 03  120 02    Electricity meter s  make and model    The extent of ability of the signatory or the signatories is limited to the work described above as the subject of this Certificate              i    For the DESIGN of the installation    Where there is mutual                   lor the design   Declaration   to be completed by installer
60. ounterbatten space     Inverter ventilation     Inverters dissipate heat and should be provided with  sufficient ventilation  Clearance distances as specified by the manufacturer  e g to  a heatsink  should also be observed  Failiure to follow this can cause a loss in  system performance as the inverter will de rate when it reaches it s maximum  operating temperature  This should be highlighted within the O amp M manual and  perhaps with a label     not to block ventilation     placed next to the inverter     3 0 INSTALLATION SITEWORK   3 1 General   Standard health and safety practice and conventional electrical installation practice  must apply to the installation of a PV system  Issues such as working on roofs or  standard domestic a c  wiring are covered thoroughly in other publications  e g   see HSE website www hse gov uk  and are not detailed in this guide     3 2 PV Specific Hazards   When compiling a method statement and risk assessment for the installation of a  PV system  there are a number of PV specific hazards that need to be addressed   These will be in addition to standard considerations such as PPE  Personal  Protective Equipment   working at height  manual handling  handling glass and  the application of the CDM regulations     e PV modules produce electricity when exposed to daylight and individual  modules cannot be switched off  Hence  unlike most other electrical installation  work  the electrical installation of a PV system typically involves working on
61. part of a PV installation     whether as part of a true stand alone  off grid  system  or part of a hybrid  e g  grid linked  batteries  system     Note  The design and requirements of any of the load circuits within such a system  are outside the scope of this document     2 5 1 PV array charge controller   This provides the regulator dump interface between the PV array and the battery  so as to prevent overcharging of the battery  The unit may also provide other  functions such as maximum power point tracking  voltage transformation  load  control and metering                    Example Battery System ed R     D  5    i Isi a  f              TE    L               papapapa           EE  Z Ea 44         Ea 4414           L        8989 84 84                            ANTY   HHTIOHLNOO 30HVHO                                                                   e The charge controller must be rated for the current and voltage  maxima  see Section 2 1 2  minimum voltage and current ratings    e The charge controller must be labelled as per the d c  junction box  requirements in section 2 1 9    e The charge controller must carry a CE Mark     A full recharge is important for good battery health  A small size cable  between the charge control unit and the battery     with an associated high  voltage drop     may lead to the control system prematurely halting the  charge cycle  These cables should therefore be sized for a maximum  voltage drop of less than 196 at peak PV array output
62. ring special precautions  see  Regulations 413 04 and 471 10    7  Earth free local equipotential bonding   not applicable in  domestic premises  only used in special circumstances   see Regulations 413 05 and 471 11    8  Electrical separabon  see Regulations 413 06 and 471 12        Appendix C       Schedule of test results PV COMMISSIONING TEST SHEETS       Note  This form is subject to change as it is being worked on in the IEC    Technical Committee      2 58            5    PV system   Installation Check List       of    Installation address Inspection by        Page    Date Reference             General installation  electrical     ref IEC60364 6 61    Equipment compliant with standards  correctly selected  amp  not damaged  Equipment accessible for operation  inspection  amp  maintenance  Equipment and accessories correctly connected   Particular protective measures for special location   Equipment and protective measures appropriate to external influences  System installed to prevent mutual detrimental influence   Conductors connected and identified   Conductors selected for current carrying capacity and voltage drop  Conductors routed in safe zone or protected against mechanical damage  Presence of fire barriers  seals and protection against thermal effects                                                                        General installation  mechanical    Ventilation provided behind array to prevent overheating   fire risk  Array frame  amp  material corrosio
63. so see    Planning for Renewable Energy  A companion Guide to PPS22   which  provides additional guidance for PV in Technical Annex 6 Active Solar  Photovoltaics    ISBN 1 85112 7542     e BRE Digest 489        Wind loads on roof based photovoltaic systems      ISBN 1 86081 713 0  2004  www brebookshop com  Note  This Digest reviews the wind loading information appropriate for roof based PV  systems and gives recommendations and guidance for the design of roof based PV systems  for wind loads  It covers both PV tiles or slates integrated into pitched roofs and PV  modules mounted on or above pitched roofs                 e BRE Digest 495     Mechanical installation of roof mounted photovoltaic systems   ISBN 1 86081 869 23  2005  www brebookshop com  Note  This Digest gives guidance on installing and using photovoltaic systems on roofs   The guidance refers only to the mechanical installation of roof mounted integrated and  stand off photovoltaic systems  it provides best practice guidance on installation  requirements and does not constitute fixing instructions        References       1    Photovoltaics in Buildings     Safety and the CDM Regulations      BSRIA DTI Feb 2000   ISBN 0 86022 548 8   www bsria co uk bookshop system index html  Note  This covers larger systems  although most of the safety advice is also relevant to  small installations that may be exempt from the Regulations  It provides a simple guide  to the Construction Design and Management Regulations 1994  
64. tallation  use and maintenance    e PV modules are current limiting devices  which require a non standard  approach when designing fault protection systems  as fuses are not likely  to blow under short circuit conditions    e PV systems include d c  wiring  with which few electrical installers are familiar    e The installation of PV systems presents a unique combination of hazards     due  to risk of electric shock  falling and simultaneous manual handling difficulty   All of these hazards are encountered as a matter of course on a building site   but rarely all at once  While roofers may be accustomed to minimising risks of  falling or injury due to manual handling problems  they may not be used to  dealing with the risk of electric shock  Similarly  electricians would be familiar  with electric shock hazards but not with handling large objects at heights     1 4 Parallel Generation   A mains connected PV installation generates electricity synchronised with the  electricity supply  Installers are obliged to liase with the relevant Distribution  Network Operator  DNO  in the following manner     e Single installation covered by G83 1     notification at or before day of  commissioning followed by G83 1 paperwork  G83 1 appendix 3  within  30 days    e Multiple installation covered by G83 1     application to proceed  G83 1  appendix 2   On commissioning     notification and appendix 3 as above     Note  For single installations of slightly greater than 16A attention is drawn
65. terminals is higher than the  voltage at the consumer unit  This voltage drop must be kept to a minimum  in order to prevent the inverter nuisance tripping on over voltage    Note  New cables colours have been implemented under the current version of  BS 7671  These colour changes became mandatory on 1st April 2006  Colour  changes and the requirements for labelling in mixed colour installations can be  found in BS 7671 and from IEE technical publications     2 3 2 a c  switch disconnector    A manual a c  switch disconnector must be provided located in an   accessible position within the Customer s installation as in G83 1  e g    adjacent to the consumer unit or main distribution board   which is        in accordance with BS 60947 3   e must switch all live and neutral conductors       must be securable in the OFF position only  It must be simple to secure  using a standard padlock   devices that require a separate removable    adaptor or special key to enable them to be secured are not acceptable   e must clearly show the ON and OFF positions and be labelled as        system     main a c  isolator        Note  At the point of installation of any a c  switch disconnector  the public supply  Should be considered the source and the PV installation the load    If the a c  switch disconnector and the inverter s  are not in the same room   a local isolator should be installed adjacent to the inverter s   This is to   facilitate maintenance of the a c  cable run and inverter s   
66. this Cerificate is valid        when they are amached to      of Inspections and Schedules of Test Results are attached    Erie Quarto of schedis wae       Guidance for recipients  This safety Certificate has been issued to confirm that the electrical installation work to which it relates has been designed   constructed and inspected and tested in a cordance with British Standard 7671  The IEE Wiring Regulations      You should have received an original Certificate and the contractor should have retained a duplicate Certificate  If you were  the person ordering the work  but not the user of the installation  you should pass this Certificate  or a full copy of it  including the schedukes  immediately to the user     The    original    Certificate should be retained in a safe place and be shown to any person inspecting or undertaking further  work on the electrical installation in the future  If you later vacate the property  this Certificate will demonstrate to the new  owner that the electrical installation complied with the requirements of British Standard 7671 at the time the Certificate  was issued  The Construction  Design and Management  Regulations require that for a project covered by those  Regulations  a copy of this Certificate  together with schedules is included in the project health and safety documentation     For safety reasons  the elcetrical installation will need to be inspected at appropriate intervals by a competent person  The  maximum time interval recom
67. ting factors must also be applied  BS 7671      Cables should be sized such that overall voltage drop at stc between the  array and the inverter is  lt 3      2 1 4 2 Cable type and installation method   The cables used for wiring the d c  section of a grid connected PV system need to  be selected to ensure that they can withstand the environmental  voltage and  current conditions at which they may be expected to operate  This will include  heating effects of both current and solar gain     Note  Purpose designed    PV cables    are readily available  These are simple to use   comply with the requirements as above and allow simple and safe connection  via purpose made PV plug and socket connectors  It is expected most  installations would use these cables        Cables routed behind a PV array must be rated for a minimum  temperature of 80 C    Cables must be selected so as to minimise the risk of earth faults and  short circuits  This can be achieved by reinforcing the protection of the  wiring either through     a  Single conductor cable     both insulated and sheathed  eg    PV cable      HO7RNF cables    m p       b  Single conductor cable in suitable conduit trunking  typically non  conducting  however earthed metal trunking may be required where    additional mechanical protection is required   Alternatively  single core  SWA may be a suitable mechanically robust solution       A A  c  Multi core Steel Wire Armoured SWA  only suitable for main d c  cable  and typically 
68. ting voltage less than 207 V phase to neutral  m Operating frequency greater than 50 5 Hz  m Operating frequency less than 47 Hz    e Dual supply labelling should be provided at the service termination   meter position and all points of isolation to indicate the presence of  on site generation and indicating the position of the main a c  switch  disconnector for suitable label see ER G83 1 or see the sample  reproduced in    Example Signs    and on the back cover of this guide      e At the point of interconnection  the following information   is to be displayed  typically all displayed on the circuit diagram     m Circuit diagram showing the relationship between the inverter  equipment and supply    m A summary of the protection settings incorporated within the  equipment    m    contact telephone number for the supplier installer maintainer  of the equipment     NB It is also good practice for shutdown and start up procedures to be detailed on  this diagram     Note  the requirements for larger systems connected under G59 1  including  commissioning tests  which may need to be witnessed  are to be confirmed with the  relevant DNO engineer as part of the connection application process     4 4 Labelling  Requirements for labelling are contained within the relevant sections of this guide   Example labels can be seen below     All labels must be clear  easily visible  constructed and affixed to last and  remain legible for the lifetime of the system     Sign No  Example Signs  
69. ty   2 5 Battery systems  2 5 1 PV array charge controller  2 5 2 Battery overcurrent protection  2 5 3 Battery disconnection  2 5 4 Cables in battery systems  2 5 5 PV String cable and fuse ratings  2 5 6 Battery selection and sizing  2 5 7 Battery installation labelling  2 6 System performance  2 6 1 Inverter sizing  2 6 2 System performance    3 0 INSTALLATION SITEWORK    31 General  3 2 PV specific hazards    33      circuits   installation  3 31 Personnel  3 32 Sequence of works  3 33 Live working  3 3 4 Shock hazard  safe working practices     4 0 SYSTEM INSPECTION  TESTING  amp  COMMISSIONING REQUIREMENTS   DOCUMENTATION  amp  LABELLING    4 1 Inspection and testing   4 2 Array commissioning tests   4 3 ER  G83 1 and G59 1 commissioning  44 Labelling    45 Operational  amp  maintenance manual  Appendix A G83 1 installation commissioning confirmation form  Appendix B Electrical Installation certificate    Appendix C PV commissioning test sheets    Further reading    26  26  27  27    28  29  29  29  30  30  30  31    32  30  33    35    35  35    36  36  36  37  37    39    39  39  39  40  42    43    45    47    51    GUIDE TO THE INSTALLATION OF PV SYSTEMS    1 0 INTRODUCTION   1 1 Scope   The scope of this document is to supply system installers with information to  ensure that a mains connected PV system meets current UK standards and best  practice recommendations  It is primarily aimed at small scale installations  less  than 16A per phase  as per the scope of ER 
70. ty and    voltage drop         Presence ot fire barriers  suitable seals and protection  against thermal effects    General         a  Presence and correct location of appropriate devices for  solation and switch    LL      Adequacy of access to switchgear and other equipment    Oe  D       Ole                0 Choice and setting of protective and monitoring devices  for protection against indirect contact and or overcurrent    Ow  Le          Notes     E to indicate an inspection has been carried out and the result is satisfactory    to indicate an inspection has been carried out and the result was unsatisfactory    N A to indicate the inspection is not    applicable  LIM to indicate that  exceptionally  a limitation agreed with the person ordering the work prevented the inspection or    test being carried out   1  SELV An extra iow voltage system which is electrically  separated from Earth and trom other systems  The  particular requirements of the Regulations must be  checked  see Regulations 411 02 and 471 02    2  Method of protection against direct contact   will include  measurement of distances where appropriate   3   Obstacles   only adopted in special circumstances  see  Regulations 412 04 and 471 06    4   Placing out of reach   only adopted in special  circumstances  see Regulations 412 05 and 471 07     5  Use of Class II equipment   infrequently adopted and only    413 03 and 471 09    6   Non conducting locations   not applicable in domestic  premises and requi
71. undamental construction requirements  Part 2 is Testing requirements   These two international standards specify requirements for photovoltaic modules in order  to provide safe electrical and mechanical operation during their expected lifetime  They  address the prevention of electrical shock  fire hazards  and personal injury due to  mechanical and environmental stresses  Pertains to the particular requirements of  construction and is to be used in conjunction with IEC 61215 or IEC 61646     e IEC61215 Building Control Approval  www odpm gov uk index asp id 1130474   www labc services co uk buildingreas default asp  Note  For    integrated products    in the UK where the PV forms part of the building  envelope  eg PV roof tiles   proof of compliance with relevant Building Regulations may be  required by the local Building Control Inspector  eg compliance to   e Fire resistance standards  eg BS 476  part 3    gt     Relevant wind uplift and weatherproofing standards  eg BS 6399  BS 5534     See also BRE Digest 489  amp  495 below which are specific to PV     e PPS22    Planning Policy Statement 22  Renewable Energy  ISBN 0 11 753924 4  2004   www odpm gov uk index asp id 1143908  Note  UK Planning Consent  if required   PPS22 replaces UK Planning Policy Guidance  note  PPG 22  It sets out the Government s planning policies for renewable energy  which  planning authorities should have regard to when preparing local development documents  and when taking planning decisions   Al
72. up of units  connected in parallel  the units need to have the same thermal environment and       PV Installation Guide    Design          the same electrical connection resistance   In larger battery banks  fusing each parallel unit should be considered     A typical connection configuration for a small series parallel battery bank   take offs are on opposite corners        The following warning signs are to be displayed   e No Smoking or Naked Flames  e Batteries contain acid     avoid contact with skin or eyes  e Electric shock risk     xxx Vd c     Note  Circuit protection  and all points of isolation should also be labelled with   d c  Supply     xxx Vd c      All labels should be clear  easily visible and should be constructed and fixed so as  to remain legible and in place throughout the design life of the system     Protective equipment  including appropriate gloves and goggles     together with  an eye wash and neutralising agent     should be stored adjacent to the battery  installation     2 6 System performance    2 6 1 Inverter sizing   It is common practice for an inverter power to be less than the PV array rating and  safety considerations with respect to sizing an inverter are addressed in section  2 3 3  However  also to be considered is the system performance     For example  a 1kWp array connected to a 1 5kW inverter may be safe but not  energy efficient     with the UK climate  the inverter will be operating for much of  the time at less than the 1kWp rati
73. utilised where an underground or exposed run is needed     le    External cables should be UV stable  water resistant  and it is  recommended that they be flexible  multi stranded  to allow for  thermal wind movement of arrays modules     Note  To minimise the risk of faults  cable runs should be kept as short as  practicable  Where long cable runs are required  it is good practice to label  along the d c  cables as follows   Danger solar PV array cable     high voltage  d c    live during daylight   This is to inform personnel involved in  maintenance or alterations to a building at a later date  See also section  2 1 12  additional d c  switches for long cable runs     Note  Where modules are supplied with pre fitted single insulated tails  containment  should be installed   as described in  b  above        PV Installation Guide    Design       Note  New cable identification colours have been implemented under the current  version of BS 7671  see 2 3 1   The new identification colours for an  unearthed d c  circuit  typical PV circuits  are as follows    Positive cable   Brown   Negative cable   Grey    Note  BS 7671 requires that every core of a cable shall be identifiable by colour and   or lettering numbering at its terminations and preferably throughout its length   However  in the special case where there is no possibility of confusion  eg  where cables are pre fitted with purpose made polarised plug and socket  connectors        additional cable colour alphanumeric id
74. val from DNO to be  gained prior to works  Commissioning in conjunction with DNO  engineer  or as required by DNO     2 4 2 Planning permission   Guidance regarding the requirements for planning permissions for PV systems can  be obtained in PPS22    Planning Policy Statement 22  Renewable Energy       ISBN 0 11 753924 4  2004   available from www odpm gov uk      The relevant planning authority and building control should be consulted at an  early stage to determine any requirements that may apply     Note  Planning permission will be mainly concerned about the visual impact of the PV  system  Typically  for domestic installations  planning permission is not required   can vary where property is affected by restrictions such as a conservation  area  etc      Building Regulations approval may require the product to have passed the wind  uplift  water penetration and spread of flame tests  see section 2 1 1 2   These will  usually be applicable only where the PV is integrated into the fabric of the building     2 4 3 Building Regulations     Part P  Electrical safety     From 1st January 2005  people undertaking electrical work in homes and  gardens in England and Wales must follow new rules in Building  Regulations   Part P     The changes have been made to    e Ensure the safety of electrical installations   e Ensure records are kept of work done   e Provide electrical safety certificates that verify conformity of work       these may be integrated into property selling requ
75. with relevant Building Regulations   may be required by the local Building Control Inspector  eg compliance with    e Fire resistance standards  eg BS 476  part 3    e Relevant wind uplift and weatherproofing standards  eg BS 6399  BS 5534   BRE Digest 489      In future it is expected that all PV products will increasingly be covered by  International standard IEC61730  2004    Photovoltaic  PV  module safety  qualification        Note  IEC61730 Part 2        Requirements for testing    describes the testing  requirements for photovoltaic modules in order to provide safe electrical and  mechanical operation during their expected lifetime  It addresses the  prevention of electrical shock  fire hazards  and personal injury due to  mechanical and environmental stresses  It outlines the requirements of testing  and is to be used in conjunction with IEC 61215 or IEC 61646     2 1 2 d c  System   minimum voltage and current ratings   All d c  component ratings  cables  isolators disconnectors  switches  connectors   etc  of the system must be derived from the maximum voltage and current of the  PV array  This must take into account system voltage currents of the series parallel  connected modules making up the array  It must also take into account the  maximum output of the individual modules     Mono  and multi crystalline silicon modules     All d c  components must be rated  as a minimum  at   Voltage  Vocstey           X 1 15  Current  lsc stc  x1     Note  When considering th
76. ypical for the UK   up to    10  difference can be  expected depending on position in the country and type of PV cells used etc   it is  recommended that a PV simulation is carried out using one of the PV simulation  programmes available for an accurate estimation     Orientation Chart   Showing   of yearly output available for various orientation  tilts  as   of maximum             56        64   67   go   71   7 gi   7   6   65    58    Note  Near horizontal 0   inclinations are not recommended as the self cleaning can  not be relied on up to about 10          PV Installation Guide    Installation Sitework          Output varies with season  The shape of the daily insolation curves  and the  monthly and seasonal trend in system performance is shown on the graphs below     Bl Production per month Average Production per season   kWh season      July Global Irr  clear sky  Wim   October Global Irr  clear sky  Wim         April Global Irr  clear sky  W m      January Global Irr  clear sky  W m    1100  1000   900    S  8             c  9  2  o         Y go  800    700 5 60     600 E  Z 500 T 5  Bs t 20  300  200     0         58  amp  8553  0 2 4 6    10 12 14 16 18 20 22 24 Spring Summer Autumn   Winter  Hours of day Month Season  Example average daily isolation curves  Manchester  300 Example average kWh electricity generation bar chart   Inclination  due South  Ref  European Joint Research Centre  Manchester  30  Inclination  due South  750kWh yr Ref   http   re jrc cec eu i
    
Download Pdf Manuals
 
 
    
Related Search
    
Related Contents
Einbauanweisung für den Elektroinstallateur    ADATA HC500  Système d`infiltrométrie Renseignements : 01 71 16 17 00  JVC MX-GB6 User's Manual    Copyright © All rights reserved. 
   Failed to retrieve file