Pablos guide to estimation - Logica 1996
Contents
1. PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd Of course your chart will just be for the code unit test bit at present in the real example above I just have three code unit test C amp UT teams who are 39 66 covering generic specific and test tools parts of the project In dividing the code test work among a number of teams remember that You shouldn t have more than six in a team including the team leader Team leaders should not be assigned any code unit test work unless the project is very small or the team is very small Each team member should have a continual diet of work throughout the project There should be the minimum of dependencies between one team and another All tasks must be complete within the overall code unit test time available Allow 18 days in a month Allow for development team overheads walkthroughs reviews etc I usually allocate 0 5 days week This does not apply to team leaders who are usually full time overheads anyway You should use the with contingency figures for the Gantt chart By this I mean the individual task contingencies At this stage I recommend ignoring the overall project contingency because it is more likely that this will be met by applying additional resources rather than extending the timescales logica Pablo s Guide to Estimation 37 Issue 4 0 26 June 1996 However on proj
2. Functional Authority Assume V C Analysts Logica Intermed BA Client Technical Architect Logica Senior Consultant Technical Designers Logica Intermed TA Client System Management Client Forte Consultant M O Senior Developers Logica Senior Cons Client Developers Logica Intermed Imp Client Development Support Logica Intermed Imp Client Senior Test Designer Logica Senior Test Client System Integration Testers Logica Junior Test Client User Acceptance Testers Logica Junior Test Client Database Design amp Maint Logica Senior TA Support Co ordinator Logica Senior Test Support amp User Training Logica Junior Imp Client BSF Infrastructure R O D Team Profile Total 6043770 Flat Client Rate Contingency Contingency 1140885 With Cont 7184655 PABLOS_GUIDE 2 DOC 1996 Logica UK Ltd Pablo s Guide to Estimation 51 Issue 4 0 26 June 1996 9 Reviews 9 1 Tidying Up At this point you should clean up your documentation As always presentation is important and gives your estimate the look of authority At this stage you should have 1 A spreadsheet with all the tasks and overheads plus an estimate and contingency for each one with task specific assumptions listed A spreadsheet for the Do It Yourself Fu
3. Of these the first is the most relevant The main reason projects fail is of course badly managed changes to the specifications But why were they badly managed Could the changes have been foreseen These are the sort of questions you should be asking in your post mortem Here is a short check list of the sort of things that should be covered logica Pablo s Guide to Estimation 56 Issue 4 0 26 June 1996 Did the project meet the timescales budget if not by how much either way Was the estimated team structure maintained if not why Was the list of tasks in the original estimate correct If not what was added removed and why e Were the assumptions met If not was the contingency sufficient to cover them Were the raw estimates for each task correct If not why It is possible to answer these questions without personal acrimony so long as the post mortem is kept within the team It is not necessary to write anything down Just get the facts and remember them That way your estimates like Gary Player s putting will continue to improve PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 57 Issue 4 0 26 June 1996 11 And Finally That s all there is to estimation You may think having read this paper that you still don t know how to go about doing the estimates for your next project You re right There is no magic formula no easy way no algorithm no
4. base figure of 3000 days i e 33 This can also be calculated by the spreadsheet The other figures I m afraid you have to work out for yourself A Genuine Example Here are a couple of pages from a recent estimate I undertook logica Pablo s Guide to Estimation Issue 4 0 26 June 1996 15 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd Bucket Task Days Cont Days Comments PHASE 1A Implement Point of Sale Facilities Code amp Unit Test 1l SMART Interface 15 40 21 File handoff every 15 mins 1 SMART Adapter 8 50 12 Converts fields to internal formats rules 1 Record Trade 12 15 14 No validation Generic Format 1 Cancel Amend 12 40 17 Doubtless problematic 1 Validate Trade 10 15 12 1 Fix Validation Failures 10 15 12 Screen s Only what is needed for POS Facilities Probably not RRD so 1 Basic Enrichment 4 15 5 need to set up our own database or access another 1 Fix Enrichment Failures 4 15 5 Screen Ditto Possibly redundant Only what is needed for POS and CSP May be RRD Or another database or something we set up ourselves Possible 1 Access External Reference Data 20 50 30 comms problems Screen Almost the final thing Equities only status limited 1 Trade Enquiry 12 25 15 Problems with REPOs Screen Will feed final splits into Record Trade Manual entry 1 Enter Splits 8 15 9Jonly anthing from ETC must
5. s just a couple of special cases at the end of the month Let s say it ought to take 20 days Assume that these special cases aren t too difficult say 5 days or 25 You see what I mean about the estimation of contingency being more difficult than the task Look back at my genuine example earlier and you will see that I have placed 15 contingency on nearly all tasks This reflects a standard level of doubt I had at the stage I undertook the estimate The 15 could have been logica Pablo s Guide to Estimation 27 Issue 4 0 26 June 1996 3 9 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd assigned as project wide contingency if I had wanted but would have disadvantages if I later wanted to reduce or remove the contingency for a particular task Where my contingency estimate rose above 15 I have noted why in the Comments column Some areas always worry me external interfaces itty bitty details of screen behaviour agreeing things with clients acceptance testing and support during initial live use for example Some undoubtedly reflect my own skills or lack of them for example comms is not my strongest area so interfacing always tends to get a big contingency I do not believe that contingency can be measured to a greater accuracy than 5 As I said I tend to use 15 as a minimum if the functionality of the system is known to a reasonable degree more if it isn t less if it has been frozen I rarely find
6. But what you do need is a list of functional doable chunks and I would say this should be 10 items at the very least regardless of the size of the job in hand If the project is in the concept stage and we are following the normal Logica project lifecycle then the chunks will be something like Feasibility Proof of Concept Functional Specification Prototype Technical Specification Code and Unit Test subsystems A B C Integration Test Specification Integration Test including time for fixes System Test Specification System Test including time for fixes Acceptance Test Specification Acceptance Test including time for fixes User Documentation Help Text User Training Cutover Rollout Post Acceptance Support Project Management Overheads If the project has progressed a bit and there is a list of functions e g a Functional Specification has been written or can be extrapolated from the client s requirements then the Code and Unit Test elements can be broken down to a further level This is the normal situation in my experience Of the Technical Specification has been written then of course the logica Pablo s Guide to Estimation 12 Issue 4 0 26 June 1996 functionality can be broken down to the level of individual software components More bits so a more accurate estimate We are thus in a position to follow Pablo s Bloody Obvious Rule of Estimation Number 5 Draw up a list of tasks The
7. Could the task be done in a day No way A day Never A week Well if a miracle happened Six weeks Well unless something went badly wrong And now from the other direction Could the task possibly take five months Surely only if disaster struck One month Very difficult to see how Six weeks Aha 3 3 Assumptions Okay let us assume that you now have a figure or at least a range But whether you guessed a figure in an instant or struggled for three days you will inevitably have made a lot of assumptions Feel is all very well but a You are going to be asked to justify those numbers sometime b You will probably change them once you start thinking about the assumptions c You will need to estimate the contingency in a minute So the hard bit now is to apply Pablo s Bloody Obvious Rule of Estimation Number 7 Write down your assumptions Now this is tricky It s this old problem about the mysterious workings of the brain again Can we really ever know what subconscious assumptions we are making Well no But we can at least make a list of the conscious ones So don t forget here things like PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 22 Issue 4 0 26 June 1996 Quality and depth of the documents you have seen the stability of the requirements Quality of potential available staff and prerequisite knowledge Availability of tools and suppor
8. System Integration Acceptance Test team PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 43 Issue 4 0 26 June 1996 Test spec writers User manual writers For each role you must ask yourself How many people are needed When they will be needed How long they will be needed for Who they are going to report to Could they be used at any earlier or later points in the project e g can Technical Spec writer No 3 become Team Leader No 4 Obviously all this all needs considerable thought To have an extra person on the project for the duration can push up the price considerably Conversely to forget that someone is needed can eat into the project profits very quickly As an example I have for many years just assigned one junior person or less to system management tasks having a mental picture of backups and the occasional call to the manufacturer s service engineers However projects are now often done using lots more third party software for instance for networking database configuration management and 4GL The poor old system manager is then considered responsible to the smooth operation of all this a considerable task particularly at the start of the project So think about all these roles in depth and need I say it relate them to the particular needs and quirks of the project in hand Consideration of the project roles should enable you to sub divide or re draw
9. anyone who is foolish enough to name a figure is immediately picked on by the rest of the team who want it increased Needless to say the eventual estimate spirals to be so over cautious that it is useless I don t believe estimates can be done as a team unless it is by a 9 2 3 Combined Walkthrough and Estimate Each task is described by someone and then two or more people write down their figure These are then compared discussed and agreed The process allows concerns to be raised and fully discussed in context These are often factors not previously considered at all which shows one of the advantages of this method The process does not suffer the disadvantages of the team review because the function under consideration is so fresh in everyone s mind and no one has a previous view to defend In my experience this method works very well I have even undertaken a joint client Logica estimate in this way The only snag is that the exercise can take several tiring days 9 2 4 Two Separate Estimates Obviously the crunch point comes when the two are compared This can have the advantage of showing up tasks concerns or assumptions that were forgotten by the other person particularly true if the two people use different methods of estimation One useful technique is to agree the task list first then go away and undertake the separate estimates The snag arises when there are widely differing views on the effort required for a partic
10. completeness of this list is vital Your estimate is far more likely to be inaccurate because you forget some piece of work or some project role than because you put an incorrect figure by each task The list of tasks will also be useful in the review process Logica standards demand two independent reviews before an estimate can be quoted Agreeing the list of tasks with your fellow estimator will allow the two sets of figures to be compared more easily Also it is possible to agree the task list with other team members people who have undertaken similar jobs in the past or even the client Such people are usually far more willing to discuss the task list than to undertake any other part of the estimation process Your list of tasks should be entered into 2 3 The Spreadsheet Although one of the computer world s leading Luddites I do like to use a spreadsheet for estimates Usually the spreadsheet is in two parts one for the code unit test tasks and one for the overheads such as project management testing and specifications My spreadsheets look something like this PABLOS_GUIDE 2 DOC 1996 Logica UK Ltd logica Pablo s Guide to Estimation 13 Issue 4 0 26 June 1996 2 3 1 Code and Unit Test Task Input of beers wines and spirits Display signs of inebriation Removal of traffic cone from head Total for Sub System A GRAND TOTAL 2 32 Overheads Cont Initial project lunch 33 E
11. database entities to be read a few lines of calculation to be done the results to be displayed screen input accepted and validated and a couple of PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 20 Issue 4 0 26 June 1996 3 2 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd database entities to be written Similarly we might pick a smallish report that needs a few entities to be read with a bit of calculation and formatting to be done So two types of task and two typically simple functions A couple a few lines I know it all sounds pretty vague But this is where your knowledge of the job as a whole comes in Remember that you are looking for are typically simple tasks in terms of your particular project Maybe a typical transaction would call for one entity to be read maybe six What is the typical amount of calculation needed Maybe two lines of code maybe ten pages Maybe your system is nothing like this process control perhaps where you are looking for a typical task in terms of the number of inputs and outputs and the complexity of the interrelationships between them I can t help you choose but what I do know is that nestling in your list of functions or tasks are one or more which are typically simple and that these will be the baseline the cornerstone of your estimate The Moment of Truth In theory the full code unit test process consists of the fol
12. excuses is no help to anyone It is clear however that if we don t know a great deal about the project than the estimate is not going to be very good And this leads us to Pablo s Bloody Obvious Rule of Estimation Number 3 The quality of your estimate depends on your familiarity with the task Because I believe in estimating entirely by feel there is no short cut here I always want to know everything about the job the history the relationship with the client the person who wrote the proposal the quality of the specs the performance requirements even the names of the people currently off charge who will be staffing the thing The human brain works in a mysterious way Try to think of the qualities that attract you about your friends for example the circumstances under which you met what was said how the relationship grew You ended up with an accumulation of feelings achieved from a myriad of disparate pieces of information At the time most of these facts seemed irrelevant unrelated or even irrational but somehow they were synthesised to produce a policy relevant to each friend So when you are making your estimate nothing is unimportant it all contributes to your overall feel about the project PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 10 Issue 4 0 26 June 1996 2 Breaking the Problem Down 21 Familiarisation with the Project So the first es
13. filled in and these should be reflected in your Gantt chart PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 42 Issue 4 0 26 June 1996 6 Project Roles It is time to approach the problem from the other direction and apply Pablo s Bloody Obvious Rule of Estimation Number 12 Make a list of project roles All project roles require different mixtures of skills and experience It is important that we assign the right levels of staff to each task so that the estimate is correct in money terms We could either treat the estimate as an academic exercise and price a hypothetical ideally qualified person to each logical role and then price the job from that or we could assume continuity of staff between the different phases of the project presupposing a set of ideal staff each with the right mixture of skills The first is often easier although possibly less accurate the second should be used if a significant number of the team members have already been nominated Some possible roles to consider are Project Manager Keeper of the Vision Functional Authority Technical Manager QA Database design experts Test database maintenance System management Team leaders Experienced analyst programmers Other analyst programmers Consultants with specific knowledge Performance analysts Prototype developers Programmers User interface experts Screen designers Test team leaders
14. glad of an excuse to do so knowing that he won t have to justify the increase and BANG The project never starts A worse scenario is where the estimator sticks grimly to his figures and the reviewer then is left as a Cassandra muttering I think it s all hopelessly underestimated but no one will listen To avoid these situations such a review should be treated as a chance for the reviewer to raise queries and points that the original estimator may need to consider This gives a chance for the estimator to take these factors on board if they wish without the ability to shift the responsibility on to the reviewer If the reviewer still has serious doubts about the figures then they can be raised with management However the person with the in depth knowledge should really take the responsibility here Team Estimate from a List of Tasks This also has its problems In my experience there are two scenarios One person in the team dominates the effort and takes the key decisions e g estimation of the baseline task The rest of the team then breath a sigh of relief and fill in the easy bits In times of trouble it is then all the fault of the pathfinder and everyone else can claim to have raised doubts at the time which were not heeded The benefit if there is one of teamwork is thus negated logica Pablo s Guide to Estimation 53 Issue 4 0 26 June 1996 Everyone is too estimid to venture any opinions The result is that
15. great help to know how long each phase of the project will last and what the team size looks like Hence Pablo s Bloody Obvious Rule of Estimation Number 10 Sketch up a Gantt chart How you do this is up to you You may prefer to use a drawing package but I have never found one friendly towards the large amount of amendments and corrections that need to be made You may also be a fan of PMW or a similar package it will come as no surprise to learn that I don t know how to use any of these although I have sat next to people while they struggled and cursed in attempting to enter a simple modification Hence I tend to either use pencil and paper or Excel as in the following PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 36 Issue 4 0 26 June 1996 Month 1 2 4 5 6l 7 8 o 10 m 12 13 14 15 16 17 18 19 20 21 Task PM TM FA Team Leaders SM DB Admin Tidy FS TS PoC AT Spec Ptype Test Tool Des Specific C amp UT Generic C amp UT Test Tools Int Test Specific System Test Specific Acc Test Specific Generic Test Int amp Ext Workstation Variants Doc Installation cutover
16. isn t specified but it can t possibly be too complicated so we ll push the contingency for this task to 35 Alternately you may say The matching algorithm has no similarity to logica Pablo s Guide to Estimation 28 Issue 4 0 26 June 1996 the baseline task it must be 6 or 8 times as complicated as that so we ll call it 75 days with a contingency of 25 If you are not an intuitive type you ll have to do it the hard way But before we think what this might involve let s look at the software tools available to the estimid PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 29 Issue 4 0 26 June 1996 4 1 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd Function Point Analysis and COCOMO Science or Mysticism At every stage in my method if that is what it is I am telling you to draw up lists of tasks assumptions rules and weightings which are specific to your project And this can only be done by gaining as much information as you can about the tasks which make it up and then using the brain s natural abilities for analysis and synthesis to allow you to use your intuition your knowledge your experience together with a rational approach so that you feel comfortable with your estimates By contrast function point analysis is a wonderful exercise for the dull witted There are lots of forms little bits of detail hours of painstaking work and at the end a number A
17. logica Pablo s Guide to Estimation 47 Issue 4 0 26 June 1996 7 2 73 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd day figure in the spreadsheet As for the task contingency you should be prepared to reduce this if someone can set your mind at rest as to the assumptions you have made Client Staff There is an increasing trend for joint projects which tosses yet another unknown into the estimation stew At one extreme the business knowledge of the client staff and improved relations generally may result in less work and less risk At the other extreme the client may put in inexperienced people with the aim of training them up resulting in a distinctly negative effect on progress despite the nominal addition of manpower My inclination in these circumstances is not to assume any change from an estimate which assumes an all Logica team However the use of client staff must be considered as a risk It may not be politic to present it to the client as such but they must be made aware that the supply of ineffective staff will cause delay The contingency for the risk may include bringing x client staff up to speed plus and allowance for replacing y client staff who prove completely ineffective Allowances for Reuse Pressure often arises from salesmen or clients to reduce estimates in order to take account of what they see as positive factors These include use of client staff reuse of existing code similarities betw
18. maintain the Technical Specification All too often when new staff start on a project they are given this document or the equivalent and told that it gives a good idea but is not up to date This is inexcusable but acts as a reminder that time should always be allotted to keep all project documentation valid Testing Testing is consistently under estimated for two reasons Firstly there is a need to write a test specification Obviously this needs to be created before the testing begins which usually means that it must be kept in synch with changes to the code which are made during development Failure to do so means that the testing is constantly stalled by disagreements between the testers and the developers In the case of the Acceptance Test Specification which is usually written at the start of the project all changes must be agreed with the client So you have documents which are very long and boring to write and which must be kept up to date All very time consuming Secondly an allowance must be made for fixes to the code which arise as a result of testing This is often forgotten or under estimated As testing is largely proportional to the amount of code and should decrease at each stage you may like to enter this into the spreadsheet to be calculated automatically For example logica Pablo s Guide to Estimation 39 Issue 4 0 26 June 1996 5 2 3 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd Total Code and U
19. some other unforeseen circumstance PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 49 Issue 4 0 26 June 1996 8 Estimating the Project Cost This should be simple to derive from your Gantt chart Get the rates for each person or role enter these as a new column in the spreadsheet multiply up total the lot and hey presto an estimated price will emerge An example spreadsheet is shown at the end of this section For Logica staff and contract people this process is easy because the man day rates Logica UCR are known Clients have more of a problem because they usually have not calculated how much each staff member really costs It is not just a question of salary but also of support staff buildings equipment costs and so on This is a major reason why Logica s rates or indeed those of any software suppler always appear so large clients have no realistic internal costs to compare them against It also leaves a serious problem where Logica is trying to provide an overall cost for a joint development Usually the best we can do is quote a number of person days If you don t have the actual names of nominated project staff then fill in an ideal person who you know could do the job It doesn t matter if they are on site in Bangalore and unlikely to be free until doomsday Just say to yourself we need a Fred Smith sort of person here and a Bill Jones sort of person there As the
20. sort of Do It Yourself approach whereby all the factors and weights are assigned by you Well my simple answer would be that it takes too long However I do acknowledge that there are people who blanch at the thought of just producing numbers from thin air and demand some sort of mumbo jumbo on paper to justify the result to themselves It is very much like writing down the a long division sum when you know full well that you could do the arithmetic mentally So here is how you could go about formalising the method of converting your estimate for the baseline task into estimates for every remaining task a Identify the variables which will make any of the tasks more or less difficult than your baseline one if you have more than one type of baseline task then you re going to have to repeat this process for each one b Decide whether these variables are part of the task or part of the contingency logica Pablo s Guide to Estimation 32 Issue 4 0 26 June 1996 c For the task variables weight each of these using an arbitrary points system making the baseline task equal 100 d For the contingency variables estimate a range of percentage increases that will need to be added on or taken off if the specified variable does or does not occur e Calculate the points total for all the other tasks relative to the baseline task f You have already estimated the number of days the baseline task will take so you c
21. your Gantt chart to show the assignment of each individual to each task The times allowed for all the project overheads can also now be added into the chart The result may be something like this PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation Issue 4 0 26 June 1996 Year 1996 1997 Month Aug Sep Oct Nov Feb Mar Apr May Jun Jul Aug Sep Oct Nov J Dec Jan Role Team Project Manager Development Team Leader Functional Authority Analysts Technical Architect Technical Designers System Management Forte Consultant Senior Developers Developers Development Support Senior Test Designer System Integration Testers User Acceptance Testers Database Design amp Maint Support Co ordinator Support amp User Training BSF Infrastructure Team Profile 7 8 25 10 25 13 25 17 25 19 5 20 5 19 5 14 5 11 5 16 5 75 7 25 4 25 7 25 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd 44 Total Days 198 198 126 414 108 252 270 49 5 288 324 90 108 216 234 180 126 234 135 3550 5 log
22. 30 46 As well as technical architect full time 1 Database Design 100 15 115 Physical and Logical models Full time role 1M Team briefings 70 0 70 1M Development System setup 15 30 20 Includes Forte Repository management This will be a full time role as the project expands and complete familiarisation 1 System Management P1 60 20 72 is important hence assume full time from the start 2 System Management P2 40 20 48 1 Forte Guru P1 15 40 21 2l Forte Guru P2 5 40 7 SMART simulator Compare settlement records with existing 11 Simulators Test Tools 15 30 20 system 1 Test Data Maintenance 0 0 O Job of database man 1D External Data 0 0 0 Support is job of databse man otherwise out of scope 1D Data Take On 0 0 0 Support is job of databse man otherwise out of scope 1 Project Director P1 60 15 69 2 Project Director P2 40 15 46 1 Dev Project Management P1 60 15 69 2 Dev Project Management P2 40 15 46 1 Functional Authority P1 60 15 69 2 Functional Authority P2 40 15 46 1 Technical Architect P1 60 15 69 2 Technical Architect P2 40 15 46 1 Team Leading P1 0 0 0 Assume senior staff for this phase 2 Team Leading P2 0 0 0 Walkthroughs Reviews etc Assume senior staff allows 1 Team Overhead P1 0 15 O overhead to be absorbed in C amp UT time 2l Team Overhead P2 0 15 0 il Manuals Help text 2 15 2 Some help text in this phase No manual 1D Failover performance 20 30 26 Support testing 11 S
23. Pablo s Guide to Estimation V N es a pE 7 E A er NN y US oe dd La A HH S Cl fo TS Ses 7 _ N LN A EN N ON ff x a by Se Ed x EN NA Nothing is so useless as a general maxim Lord Macaulay 1998 Logica UK Limited Logica UK Limited s prior written consent is required before any part of this document is reproduced logica Pablo s Guide to Estimation 2 Issue 4 0 26 June 1996 11 1 2 1 3 1 4 1 5 1 6 2 1 2 2 23 2 4 3 1 3 2 3 3 3 4 3 5 3 6 3 7 3 9 4 1 4 2 5 1 5 2 5 3 7 1 22 73 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd Table Of Contents Intro duiChON sacas iearcensais tes sseusuvsndaunnactestaausanactucactsseusduactanseadusstasoaseoseauseyans 4 Estimidity and How it is Manifested 4 Whiy Estimate cs sesssasarm supino ada rena e Ere babel Aa EAE e EO EAEE fes a valas 5 The Accuracy of Estimates rr E ins aae aE 6 Who Should do the Estimates ana 7 Can a Job Be Over Estimated e ie eereeererereerenrena 7 When Can An Estimate Be Provided c irei 8 Breaking the Problem Down sscssccsssscssccssccsscscsscsescssscssscsssscsosssseses 10 Familiarisation with the Project 0 0 0 eee cesceeccseeceeeeeeecseecnaeceaeeeseeesaees 10 The Estimatable Entities 2 00 0 cccccceccccssecesececeeeecesneeeeeeeeeeseec
24. a figure of over 100 is needed it is usually easier to cut out the task altogether and state The estimate does not include X Y and LZ The Remaining Code Test Tasks We ll assume now that you have an estimate for the baseline task and a level of contingency for it The next bit is a little easier because we can estimate the remaining code test tasks in terms of their difficulty relative to this What I do not condone is the method commonly seen of dividing tasks into easy medium and hard and making the same estimate for each type This is lazy and produces enormous inaccuracies Typically the easy task is over estimated leading to lists of similar routines being allocated say 3 days each Alternatively some real ballstranglers are listed as difficult and given a single usually underestimated number of days such as 12 If you know enough about the tasks to classify them then you ought to know enough to give a considered evaluation to each based on your estimate for the typically simple task If you are an intuitive sort of person then there is no mystique in my recommended method Suppose we said our baseline task took 10 days with a contingency of 25 then we might look at another task and think something like There s a few more fields on the screen maybe another couple of entities to read from the database and a bit of calculation so call it 15 days The algorithm for the calculation
25. actual names are added keep an eye on the rates and skills of the staff involved cheaper or unknown staff may cut down the cost but maybe the estimate or contingency should be upped Conversely it is wrong to assume that better grade staff will do a faster job They may do a better one you may care to reduce the contingency but coding speed is not a function of seniority Remember too that if the project crosses a year boundary then you will need to guess at next year s rates Much of all this is handled automatically on Logica s QMS form which in any case is an essential part of an internal Bid Review However I don t intend to cover the QMS in this Guide The following is the prices part of a spreadsheet for a three phase mixed team project with the different costs and contingencies for each phase being shown Man day rates were difficult here as some roles were specifically assigned to the client some specifically to Logica and the remaining man days divided equally Hence the need for a unified rate which combines the Logica rates with a flat 400 a day which the client wished to use to cost their own staff PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation Issue 4 0 26 June 1996 50 Month L Rate Unified Rate Comments Role Team Discounted Rate O Project Manager Client Development Team Leader 483480 Logica Senior PM
26. ample most of the code might be a get some screen input do some database access do some calculations put the result on the screen type or a get the report parameters access the database print the report lines calculate and print the totals type If tasks can be grouped like this then the best approach is to select a typical task spend some time in estimating this and then determine the rest pro rata This is further discussed below If the task set is completely disparate then you will have to undertake a unique estimate for each one Hard luck But usually we can follow Pablo s Bloody Obvious Rule of Estimation Number 6 Identify and estimate a baseline task first Select a task or a function any one from your list that seems to you to be typically simple If the list contains a number of different types of task then choose one of each type Well of course typically simple is a relative term and very dependent on the job you have in hand and the stage in the project at which the estimate is made How can you choose Let s take an example We are at the proposal stage in the project and there is a requirements spec to work from We know that the solution requires a database and that there are transactions to set up data do enquiries and produce reports For our baseline task we are looking for a run of the mill transaction which we ll say for this particular project calls for a couple of
27. an now put a number of days by all the other tasks g Calculate the contingency percentage commensurate with the contingency variables for each task and add it on h Sit back and admire results Now at this point you probably would rather go back and join the group who can call figures from the vasty deeps For it seems that there are actually more things to guess at using this method Indeed this is so but each of these stages is relatively easy to attempt break it into little bits remember and you will have the satisfaction of a methodology that at least looks scientific even if every stage of it is guesswork So let s try an example and assume our baseline task has an estimate of 8 days with a contingency of 25 a Firstly we must identify the variables here s a typical list 1 Number of fields on the screen 11 Number of these fields that are inputtable iii Number of fields that need some calculation before output iv Difficulty of this calculation v Amount of calculation that is needed when the user hits enter vi How well the algorithm for the calculations is known vii Approximately how many data entities we ll need to read write viii How good a mental picture we ve got of the data structures entities that will be involved ix Are some lookup tables going to be accessed if so how many PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Est
28. archive of statistics nothing that will make your task any easier What I have hoped to do is to make you realise that you do have all the experience that you need and that you can produce a set of figures that you feel good about Nobody can ask more than that And once you have succeeded you can at least have the personal satisfaction that many of your contemporaries would have shrunk away from such a task But having done the best job you can and maybe once the project has ground into action with your estimates and your plan firmly in place there may be moments when the full horror of what you have done sweeps over you in a tidal wave of apprehension So there is one universal rule which I have stolen Pablo s Bloody Obvious Rule of Estimation Number 15 Don t panic And happy estimating 11 1 Further Information Please feel free to contact me if you want any further advice or help with your estimates Paul Coombs Logica UK Ltd 75 Hampstead Road London NW1 2PL Tel 0171 637 9111 Email coombsp logica com The views expressed in this Guide are those of the author and should not be interpreted as Logica s policy or methodology in any way Yet although a Process Improvement Team under the Logica Cortex initiative is working on this PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica
29. assumptions into the contingency for each code and unit test task As we will see it is easier to cater for these at the end For example let us say that you don t know if the user interface for your system is to control the screen directly or to use a package that will make the user interface relatively easy The raw estimate for your baseline task assumes the package is available If the assumption is false and there is no suitable package then there is a separate task to write your own This is project wide estimatable task in its own right It may become zero days if the package route is eventually chosen but in the worst case at least we can estimate a figure for the other eventuality The net result should be that you have a list of project wide assumptions and a list of those which are specific only to your baseline task Your project logica Pablo s Guide to Estimation 24 Issue 4 0 26 June 1996 3 6 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd wide assumptions are risks and will form a part of the project wide contingency that I will discuss later Contingency is intimately connected with our lists of assumptions but first let me digress and discuss the concept of contingency in general Contingency The word contingency is often misused Managers affect to presume it is something that techies build in to their estimates in order to ensure an easy time during the development Worse still they a
30. ation 7 Issue 4 0 26 June 1996 events which will affect its progress and probably change it out of all recognition No one can be expected to foresee what will happen to such a beast and if anybody did then it can only be by sheer luck Hell if I could guarantee to undertake 100 correct predictions I would not be wasting my time on estimating computer projects I d take the easier option of the National Lottery results Of course ours is not the only business to be governed by wild guesswork although in most organisations this is left to the management Fortunately a sort of Parkinson s Law seems to apply to many projects They eat the estimated cost they eat the contingency they eat the profit and then almost exactly then they stop Maybe this is an argument against estimation we could just set some arbitrary target and let the inevitable happen But then how would the target be set 1 4 Who Should do the Estimates This is one of the shortest sections in this paper because the answer is obvious Estimates should be undertaken by those most qualified to do them and the best candidates are the people who are actually going to do the work Clearly the estimators must have some sort of experience or they are going to have nothing to compare the new work with so we are not talking about fresh faced codewallahs straight from University There can be no such thing as a professional estimator because the experience of such a pers
31. be entered manually 1 Display Accumulated Trades 6 15 7 Screen A form of enquiry 1l Logon Off 2 15 2 Screen Internal static data for users privileges 11 Maintain Static Data 8 15 9 Screens Includes users To CSP Assume file handoff May require additional 1 Settlement Interface 12 50 18 enrichment data from RRD or wherever 1 Fix Settlement Problems 4 15 5 Screen Fixes to enriching CSP data Possibly redundant Access by function greying some fields read only etc 1 Permissioning mechanism 10 15 12 Establish mechanism for entire application Assume part of the functionality above Trades carry history of events plus user name if manually adjusted Can examine 1 Audit Trail 0 15 OJaudit trail by one off enquiries not budgeted for here 1 Operator Display 5 15 6 Screen BSF status C amp UT Total 211 logica Pablo s Guide to Estimation Issue 4 0 26 June 1996 16 Overheads 1M Initial Factfinding 10 15 12 Making the infrastructure production quality Plus known 1M BSF Infrastructure 80 25 100 improvements 1M BSF Maintenance 0 40 O Included in above 1 Functional Specifications 20 15 23 As well as Functional Authority full time Screens Assume final screens carried forward to 1 Prototype 4 15 5 implementation 1 Agree FS Prototype 4 25 5 1 Technical Designs 35
32. blo s Bloody Obvious Rule of Estimation Number 4 The more bits it s in the longer it gets It is quite remarkable the way in which breaking a task down into smaller and smaller pieces causes an estimate to increase in size Of course this is due to the fact that you are thinking about the task in more depth so more problems emerge and so more time needs to be added in Furthermore there PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 11 Issue 4 0 26 June 1996 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd is the minimum size factor whereby no task can take less time than what one month half a day so the whole total is inflated It was fortunate that I was not suffering from estimidity when I gave my estimate of compiler size to the manager Had I subsequently sat down and tried to do a design and then break that up into routines and then estimated all those I would undoubtedly have had to make an embarrassing call beginning You remember that estimate So the rule is to break it into smaller bits Whatever the stage of the project lifecycle at which you are having to do your estimate you must be able to decompose the task into some manageable and more estimatable chunks Obviously there is a limit to the level to which you can go down and this will depend on what you have to start with you can t start conceiving routine specs if all you have is a feasibility study
33. client that a fully comprehensive guide will be supplied Check what sort of guide the client might expect given good on screen help text for instance In the worst case the guide will need to be properly laid out and printed like the Microsoft documentation but usually a good word processed document will suffice Again this can be estimated by taking the number of documentable functions and estimating say half a day to describe the operation of each Don t forget things like operator s instructions and explanations of messages logica Pablo s Guide to Estimation 40 Issue 4 0 26 June 1996 Additional technical documentation should be a thing of the past Up to date Technical Specifications and well commented code should be sufficient in most cases but make sure the client understands this 5 2 4 Support and Warranty These sort of tasks can be estimated as a number of people for a number of months or weeks For example we may say 4 people to help out the users and solve small problems for the first two months followed by 1 person for the next year Or more likely we may say we are offering 90 days warranty so allow one person 1 day a week to provide support and solve bugs total 18 days of the most junior person 5 3 How Long Will the Project Last There are two possibilities here 1 The end date has already been determined e g the client has stated that the system must be up and running by a certain date This ma
34. ction Things like common routines interfaces to hardware interfaces to third party software packages testing tracing tools harnesses simulators system start up shutdown backups archiving programs in SQL macros shell scripts 2 4 1 Familiarisation By familiarisation I mean for each team member Getting familiar with the project as a whole Getting familiar with the bit of the project that they are responsible for e Finding out about the project environment e g what exactly they have to do to compile something PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 18 Issue 4 0 26 June 1996 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd Learning to use any tools or methods with which they are unfamiliar not formal training but actual hands on use for this particular project All techies know that these tasks are significant at the start of a project and should be allowed for If they are not then the project tends to find itself behind schedule within the first month Despite this I have always found it difficult to get an allowance for familiarisation through a management review of an estimate I think they say striking a firm line through the spreadsheet that we can always get suitably skilled staff And if not then we will train them up as part of the company overhead But it never happens The staff arrive direct from a
35. cy 71 Risk Analysis Earlier we identified our project wide assumptions and defined them as risks A typical risk is TP Monitor will introduce an unacceptable performance overhead The correct approach to these is to produce a Risk Analysis which discusses each one under the following headings Risk A brief description Actions What steps are being can be undertaken to mitigate the risk Impact Number of days or percentage increase to the estimated project time that will be incurred if the identified risk actually happens For example Risk Object oriented design when not all designated staff have completed an OO development of a similar size Actions Try to get as many experienced OO people involved as possible Training may help a bit Impact Assume 20 inexperienced staff and a delay of 1 month each to get things sorted Total 360 days There are some risks which apply to nearly all projects A general under estimate Requirements not sufficiently tied down Unrealistic timescales Doubts about bought in software Doubts about the architectural solution Performance and sizing constraints Staff experience or capability Untried development methodology Poor contact with end users Inadequate development environment or tools The end result of the Risk Analysis will be a number of days which represents the overall project contingency to be added on to your total man PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd
36. d other major projects do not take place in isolation To return to Sizewell the engineers did not complete the reactor and then decide to order some fuel rods which take three years to make They didn t make the roof first and then start on the walls Okay they actually did do that but I m sure there was a good reason Like computer projects the work of different teams must be synchronised hardware must arrive at the right time users must be trained cabling and air conditioning needs must be met And if each of these parallel strands is not estimated and controlled then the logica Pablo s Guide to Estimation 6 Issue 4 0 26 June 1996 timescale will start to stretch and the costs to rise All too quickly the justification of undertaking the project in the first place have begun to disappear For projects are only worthwhile if they are cost effective and timely If a new system saves 1 million a year but costs 30 million to develop then it is not going to start If the software is to display the general election results or control a satellite then it better be finished on time or the entire effort is wasted I can think of very few cases in history where a major engineering development took place without any regard to costs or timescale The pyramids Stonehenge The Apollo programme Perhaps But in most cases someone will want to know if commencing a project is justified And they will continue to want to know this while the c
37. e 4 0 26 June 1996 10 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd The Post Mortem The only thing we learn from history is that we learn nothing from history A project goes bad loses millions causes sweat and heartbreak for the team and at the end everyone breathes a sigh of relief and gets stuck into the estimates for the next one What are its chances Well not too good really No one will want to repeat their recent unpleasant experiences so the estimates are going to be cautious really cautious cautious enough so the project never starts in fact And as for that idiot who did the estimates well we d better make sure he gets nowhere near the estimation for this one This is the wrong use of some valuable experience You are a better estimator after some failures not a worse The way to exploit that experience is to be constructive And the way to do that is to analyse the estimates by means of a post mortem So this is Pablo s Bloody Obvious Rule of Estimation Number 14 Hold a post mortem Of course this should be done for projects that go to plan as well as those which go badly there is just as much experience to be gleaned there The reasons a post mortem is so rarely held are The project changed out of all recognition during the development so making the original estimates redundant It would be difficult without pointing the blame at individuals Everyone is fed up with the bloody thing
38. e done 10 Difficulty of testing e For the contingency variables I am going to say 5 20 For not understanding the calculations too well 10 60 For not having thought out all the data structures 10 70 For not understanding how this function integrates with the rest of the system Incidentally these are additions to the contingency percentage for the PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd baseline task not percentages of it logica Pablo s Guide to Estimation 34 Issue 4 0 26 June 1996 f So now we approach the estimation of each task Lets say that the first one relative to the baseline task has Twice as many inputtable fields Has no more calculation Will need twice as many entities to be read written Has no particularly flashy screen stuff Will be about 50 more difficult to test This leads to a points score of 155 40 30 60 10 15 g We estimated 8 days for the baseline task so this one will be 8 155 100 12 5 to the nearest half day hell this method isn t that accurate h Turing to the contingency The calculations are about the same as the baseline e We have a fairly good grasp of how we want the data to look in this area e But we are a little vague but not totally baffled about where or why this function is used So the additional contingency is 0 0 say 10 Adding this to our baseline contingency of 25 we get 35 1 And there we are task 1 ha
39. e lopped off This is your estimate remember and the aim is to keep you happy with it So present it straight If however someone can set your mind at rest about the assumptions you have made then it is quite valid to reduce the contingency Apart from this problem some estimators think they are in some way at fault if the contingency goes above a particular figure 100 is often quoted After all what sort of a crummy estimate are you doing if you can t tell if a typical task will take three months or six So the temptation again is to inflate the base figure which tends to remain inviolate during reviews and have a less frightening contingency figure by it But be brave If the situation is one where the unknowns are great and the risk is high then management ought to know about it So hang on to your list of assumptions and the contingency you have applied these will be accompanying your baseline estimate Estimating Contingency To estimate the contingency you are going to have to put a percentage risk figure by each of your task specific assumptions We will be covering the project wide assumptions later There is no magic formula for this I may look at a task and say well I don t really know the algorithm by which the number of input widgets becomes translated into the monthly production target of truss flanges It can t really be too tricky because I phoned the guy who does it by hand at present and he says that there
40. ects where the end date is really fixed space shots or general elections for example a slab of naked and unadorned contingency just before that date might be seen as prudent 5 2 Overhead Tasks Let us turn then to the phases of the project other than code and unit test Some such as proof of concept exercises are too specific to make general guidelines practical However there is one rule which applies to all documents in particular Functional Specifications Pablo s Bloody Obvious Rule of Estimation Number 11 You can t write a document in less months than you have people If you have estimated 16 man months to write your masterpiece then it cannot be done well in less than 4 elapsed months Try and you will end up with holes inconsistencies and a general level of quality which will take longer to put right than you saved by rushing the original task However if the document really does split into separate pieces or there is only a small amount of overlap then a team may be allocated to each part and the rule applied to each But you must be very sure that this assumption is correct certainly Functional Specifications are a highly risky area 5 2 1 Functional and Technical Specifications In general the time taken to construct the Functional Specification is proportional to the code and unit test time you have already allocated The lazy way is to take a percentage of this say 20 and then modify it acco
41. eeaeeeeeeeeseeees 10 THES preadsheet aeisi eiar e Ea e EEEa EEE N E EEEE 12 Tasks Easily Forgotten eee eeerecencenaaea 17 The Estimation Process siisessssscsseascasssscsssvsnssuasusneshsusespoeauscasesseveosepiiuaieecibdes 19 Definins a Typical Tasks cs sssceocsresscesssbessseotivsuegovtsedonsatgesvetaaetenatiatysssces 19 The Moment of Truth oeeie io eae E ea Ee E aE EEEE t ai 20 ASSUMP ONS esae e Sea ape A wad elec EEr E e 21 Reducing the List of Assumptions er 23 Identifying Project Wide Assumptions seseeeeeesesereereeressereereereeresse 23 CoONtingENCY aent oea e ee a e SALTO ote a Eea Ta EER 24 Separating Contingency and Task Estimates cccceesccesteeeeteeeeneeees 25 Estimating Contingency eeen en EE i Ea e ek o Ei 26 The Remaining Code Test Tasks 27 Function Point Analysis and COCOMO cscccsscsssscsscsssssssccscscssesessses 29 Science or Mysticism aeneon reo na eaa iiie SET 29 Do It Yourself Function Point Analysis s 31 The Project Time Scale eesocsscsocesessossocsccsocesesocsoocosesocsssssssoscsscsocesesssssseso 35 The Gantt Charte aaa E a foes od aap asa ds E aT 35 Overhead TaskS iciccccccsscisscsseeseccancdsvaatchesscecanssavsaccesdasepabevasidesseededahnavieneess 37 How Long Will the Project Last 40 Project ROMS wi vascscsescszstvcesseccsscedcactsees ssuseSeassgecesssdeccercaesvecstecesetesacivecdseucsessde 42 P
42. een different parts of the system reuse of knowledge and expertise from other projects and use of packaged solutions Sometimes such factors are undeniably true or the pressure to see them as such is severe and an allowance must be made This should be done when drawing up the task by task estimates not by applying some blanket rule such as reduce by 25 to account for reuse of code from the XYZ project Usually however there is something of a grey area Will these factors reduce the development time or not After all it can take longer to understand and make use of existing code however well it is documented than it does to write the actual code you need Will these two routines which seem so similar now actually turn out to be so in 9 months time And will we actually get these so called experts from the ABC project which is due to finish just as this one starts logica Pablo s Guide to Estimation Issue 4 0 26 June 1996 48 If I do make an allowance for such things then my inclination is to assume the reverse as a risk So I may accumulate 100 days off the code estimates to cater for reuse of some existing software but then add all or most of it back as contingency to cover the risk of this code being inappropriate If possible therefore I prefer to let it all cancel out and ignore the positive factors If there eventually proves to be a benefit then the project gains some time but this is bound to disappear through
43. en if everything goes wrong principle The Business Manager chops off or adds on a bit and that is what ends up bid A very satisfactory situation all round everybody thinks they ve worked hard on the estimate and it s nobody s fault if we lose out to a rival or if we win and it all takes twice as long Naked and unashamed estimidity in action For the beauty of these methods is that you have only turned the handle and if the estimates turn out to be thickly sliced baloney with extra pickle then it s not your fault it s the methodology One sunny day when we put the experience gained from projects back into the model it will be perfect Not in my lifetime I suspect In the immortal words of Sam Goldwyn include me out A friend of Einstein once noticed a horseshoe hanging in the great man s lab Surely he asked you don t believe in such pseudo scientific nonsense No replied Einstein I don t But they say it works even if you don t believe in it And so it is with function point analysis and COCOMO Nobody really believes the numbers they comes up with do they but they still keep running it just as a cross check Well why not That s what this paper is all about making you feel good about your own estimates You know the answer really the hard part is justifying it to yourself and then steeling yourself to write it down and present it to someone else PABLOS GUIDE 2 DOCO 1996 L
44. ful estimate can result in long hours for the project team disruption to their lives and careers sticky explanations to managers and clients and above all enormous financial loss For example if a Logica project loses a million pounds then it might take ten million pounds worth of successful work to regain the break even point Everybody remembers the name of the person who estimated a loss making job but no one ever can recall the one who estimated a project to the nearest day it is just put down usually with good reason to the abilities and dedication of the team If you want glory don t do the estimates So there is an understandable reluctance for anybody ever to provide any estimates There are many often quite senior people in the computing world today who will vacillate delegate or even at the last resort flatly refuse to provide a decent estimate with their name appended I call this attitude estimidity In this guide I shall discuss how estimidity is manifested and how it can be overcome The aim is not to provide a method by which reliable estimates can be obtained indeed it is my belief that no such method exists or will ever exist So you won t be able to appease your estimidity by saying I followed Pablo s method and the thing was still a year late I may have overcome estimidity for my own projects but I m not taking yours on as well Instead of defining yet another methodology my aim is to make y
45. ica Pablo s Guide to Estimation 45 Issue 4 0 26 June 1996 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd In this example the project is in two phases For each role the number of people needed is entered into the Excel cell allowing the overall team profile to be seen at the bottom The number of days for each phase is calculated separately and totalled These totals can be compared with the task by task estimate as a cross check Inevitably there will be some slack time for some team members One view on this is that the roles and timescale are purely hypothetical at this stage and hence the slack time should not be included in the estimate A more pragmatic view is that people do not enter and leave projects at the desired times and tend to hang on for the duration hence this time should be included I side with the first view on the grounds that in practice no project has ever proceeded in accordance with a plan drawn up at the estimation stage It is unlikely that people will be idle they will either be doing estimated work or additional work which should have been covered by the overall contingency Hence the slack time should not be included You should now also be able to build up a diagram of the team structure at each phase in the project This may consist of logical roles several of which may be filled by one actual person logica Pablo s Guide to Estimation 46 Issue 4 0 26 June 1996 7 Project Wide Contingen
46. imation 33 Issue 4 0 26 June 1996 x Is there any flashy screen manipulation to be done xi Are there any complexities about the screen navigation to from this function xii How many error messages may be issued xiii Is there any tricky validation or cross checking involved xiv Is this function going to be particularly difficult to test for some reason xv How well do we understand how this function integrates with the rest of the system But of course the list you draw up will be specific to your project and draw on your knowledge of the system what documents you already have and so on b Now we determine which variables affect the time taken to code test the task and which affect the contingency Looking at the list above it would seem that points vi viii and xv are to do with the contingency and the remainder is to do with the code c The next step is to take the task variables and give them a points weighting The quickest and most intuitive way is to award exactly 100 points to the baseline task and then divide these among the variables Easy It also helps if you drop all the unimportant variables and just add on a few points if needed for a particular function d So I may decide on a points weighting for my particular project of 20 Number of inputtable fields 30 Amount difficulty of calculation 30 How many data entities we ll need to read write 10 Amount of flashy screen manipulation to b
47. kes life easier for now because you have figures for the number of days for each task you know the dependencies between them e g you can t start coding until the specifications are complete and can split the available time up pro rata Then you can see how many people are needed for each task At this point you might decide that the project just can t be done in the time for example PBOROE 11 might be broken or the coding phase needs more people than the computer industry currently employs Prepare your arguments neaten up your Gantt chart and prepare to brave the storm that will greet your announcement that the desired end date cannot be met 2 The end date is up to you This is a little more difficult as you need to decide on a logical division of work among the teams Often there is a logical split for instance between the generic and specific parts of the project in my example Gantt chart Bear in mind of course that someone is bound to say can t it be done any quicker so you need to think about what sort of timescale will make the whole thing impossible If the pressure is on for a quicker delivery then the logical plan will have to be abandoned It probably would never have happened that way anyhow PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 41 Issue 4 0 26 June 1996 So now your spreadsheet should have all the overhead tasks other than the management overhead
48. lowing stages Understand the function and interfaces to the code unit using the Technical Specification with help from the Team Leader Write the code Write a Unit Test Specification Write any test harness needed to undertake the unit test Submit code for review and undertake changes required Submit Unit Test Specification for approval and undertake changes required Undertake the unit test correcting faults which arise and re test e Submit the completed module for integration testing This may seem a lot and you will have to use your judgement as to how much of it you expect to happen in practice but remember that a day is quite a long time and that some of these processes are a matter of a few minutes So now you can estimate the time it will take to code test the baseline task At this point the readership will divide into two groups those who read the last sentence and plucked a number from the air and those who could not We will return to the first group shortly but let us examine the second logica Pablo s Guide to Estimation 21 Issue 4 0 26 June 1996 There are two possible reasons why you can t come up with a figure either you have a terminal attack of estimidity or else there are too many unknowns The first case I cannot help other than to point out that you have to do this estimate sometime and it s no good just gibbering at it Come on now let s at least find a range of possible numbers
49. much will the requirements change as the project develops I wish I knew But in COCOMO you ve got to say And are its 16 cost drivers really the only things which affect how long a project will take logica Pablo s Guide to Estimation 30 Issue 4 0 26 June 1996 As with function point analysis I can t say I have much faith in the weighting factors For instance under the reliability driver a slight inconvenience if a fault develops is rated as multiplying the effort by 0 75 while any risk to human life will multiply it by just 1 40 A human life finally valued at less than twice a slight inconvenience Tell that to NASA And these factors are multiplicative so by a judicious manipulation of the cost drivers you can alter the time taken for your project between 0 08 and 117 times the base value A base value which let s remember has more than likely come from that other wet digit function point analysis A guess multiplied by 16 guesses and this is supposed to be a scientific method Frankly if I knew how may lines of code would end up in a system really knew as opposed to having an estimate from function point analysis then the estimates would be easy The list of cost drivers in COCOMO is a useful guide but ll make up my own list and weighting factors thank you The temptation with COCOMO is to bump all the cost drivers up to the max under the COCOMO says it can t take longer than this ev
50. nction Point Analysis if you chose to use this method A Risk Analysis resulting in a total project wide contingency A Gantt chart which hopefully is now in synch with the spreadsheets A team structure for each stage of the project A profile of the team size at each month during the project A list of roles and rates giving a project cost ex expenses hardware etc Right or wrong at least it will look like you have given some thought to your estimate 9 2 Types of Review Some sort of review of your estimate is essential not to spread the blame and reduce your estimidity but just to get someone to point out the tasks concerns or assumptions which you have left out So PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd Pablo s Bloody Obvious Rule of Estimation Number 13 Have someone else review your estimate logica Pablo s Guide to Estimation 52 Issue 4 0 26 June 1996 9 2 1 9 2 2 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd If a review cannot be done for some reason then this is a new risk and should be added to the project contingency There are several approaches to the review process Peer review of an existing estimate The snag here is that the reviewer usually does not have the in depth knowledge of the original estimator This gives the reviewer a panic attack of estimidity and he then suggests that all the estimates are bumped up a bit The original estimator is then only too
51. nd of lunch celebration 10 Overheads Total 25 Code and Test Total 50 Carried forward GRAND TOTAL 33 Plus Overall Contingency 10 FINAL TOTAL The Reference column is usually a cross reference to the requirements document or whatever you are working from If there is nothing suitable then make up your own reference system or leave it out PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 14 Issue 4 0 26 June 1996 2 3 3 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd Sometimes I like to add a Bucket column which contains a code allocating each task to a particular class e g PIINIT P2TEST This allows the eventual man day totals to be broken down in several different ways e g by phase by subsystem by stage in the lifecycle which is required by some ITTs Use the SUMIF instruction in Excel for this The Notes column usually contains remarks about what is included or not included in this line or any particular reason why the number of days or contingency is unusually high or low Cont stands for contingency I will be discussing this later For the present just note that it is a percentage added on to the Days column to give the Total column Round to the nearest day not up or down The contingency in the Grand Total row is the overall figure in the example this is 1000 days of contingency expressed as a percentage on the
52. nit Test With Contingency Integration Test Spec 10 of Total C amp UT Integration Test Incl bug fixes 15 of Total C amp UT System Test Spec 8 of Total C amp UT incl Bug fixes 10 of total C amp UT Acceptance Spec 5 of Total C amp UT Need I tell you that the percentages are dependent on your own project Integration testing is dependent on the complexity of the software subcomponents and the amount of integration needed e g with bought in software System testing is more dependent on the amount of functionality and the amount of interrelationship between the software subcomponents Acceptance itself always takes longer than you think because it is often the first time that some of the client staff have seen the system This inevitably leads to what might be termed a training session under the guise of disputes about functionality I often include a dry run of the complete acceptance procedure so that the team is sure that there will be no problems User Guides and Help Text Another task often forgotten is help text for the screens This may include help for individual fields messages and even on line documentation Again this can be simply estimated for example by taking the number of screens and estimating that say four can be done in a day Check the tools available for help file creation and editing User Guides are another contentious issue It is tempting to estimate a couple of weeks while reassuring the
53. ogica UK Ltd logica Pablo s Guide to Estimation 31 Issue 4 0 26 June 1996 4 2 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd Another friend of Einstein once asked him how he approached the knotty dilemmas of everyday life Oh he replied I usually just toss a coin What replied his questioner You the great exponent of the scientific method just toss a coin No said Einstein Let me finish I toss the coin and then I ask myself if I am happy with the result So tot up some function points and after you have determined the number of lines of code ask yourself what this estimate feels like For instance if the method comes up with approximately 14 256 6 lines of code ask yourself how many pages this would be with headings comments and so on Imagine this pile of listings on the table Do you really think the whole project can be done in this much code Do you really think it will take as much as this pile Are you happy with the result And if not what are you going to trust the methodology or your intuition Do It Yourself Function Point Analysis So no I don t think you should rush up to your nearest PC and start using whatever estimation tools some journal reading fools have installed for the estimid However don t let s throw the baby out with the bathwater if you have estimated your baseline task as I suggest and have got a good list of assumptions then why not use a
54. on would soon become so out of date to be worthless Even though I do a lot of estimation I have to match that with actual project work or else by now I would be mapping mainframe dumb terminal assumptions on to OO Windows SQL applications Similarly managers who have not personally undertaken any project work since dinosaurs ruled the earth should not be allowed anywhere near an estimate So the ideal estimator is a senior techie likely to work on the job 1 5 Can a Job Be Over Estimated Hopfstader s Law states Everything takes longer than you think it will even if you take Hopfstader s Law into account There s many projects which have seen the truth of that But the downside is the belief that it is never wrong to over estimate This is seen at its most cynical in the widely quoted rule that the person with the largest estimate is most likely to be right Even if this rule is true it does not make for a positive attitude towards estimation Over estimates ensure that Logica fails to win a PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 8 Issue 4 0 26 June 1996 competitive tender or make a client decide that a project is not cost effective after all It s no use claiming it s not your fault and that you just did some estimates and it wasn t you who decided not to go ahead The fact is that although managers clients and decision makers may review and question your estimates they
55. osts mount and the timescales lengthen For there is always a point on any project where continuation is no longer worthwhile So at every stage of the project life cycle from the vague idea to the post mortem something is needed to provide a direction for the project and line management And some sort of estimate a plan a timescale does make the job finish quicker But an estimate is an aim not a rigid timetable a project and its staff still need to be managed and motivated if any sort of success is to be achieved The estimates and plans should help not be seen as a constant threat Good projects and good managers are those who use such methods not those who are slaves to them 1 3 The Accuracy of Estimates There are a number of bloody obvious rules defined in this paper I have called them that because they are not rocket science not precise results from years of scientific research not even truths only someone as experienced as myself could have realised They are rules we all know And the first and most fundamental one is this Pablo s Bloody Obvious Rule of Estimation Number 1 Your estimate will be wrong How can it be otherwise You are being asked to predict the future And it is not the future of something with so limited a count of contributory factors and end results as a horse race It is a IT project comprising any number of PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estim
56. ou feel good about your own estimates by ensuring that they really are your own and that they are the best that could be done at the time I have undertaken many estimates And I have also spent time studying a single routine looking for some sign of why it took ten times longer to code up than its equally sized brothers Estimates are about experience I do not just mean experience of other estimates but experience of projects both successful and unsuccessful I am reminded of a story about Gary Player who once won a tournament with an amazing fifty foot putt on the final hole As they walked back to the clubhouse his partner remarked on Player s fortunate last shot Yes replied Player It was a lucky one But you know I find that the more I practice the luckier I get Estimates are like that too logica Pablo s Guide to Estimation 5 Issue 4 0 26 June 1996 1 2 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd Bad estimates lose us the good jobs and land us with the impossible ones But they have to be done and done to the best of our ability So no more estimidity let s go to the gallows at least informed if not actually laughing Why Estimate It is a curious fact that most software engineers assume that their profession is immune from the rules of other types of engineering and indeed of life itself I spend most summer weekends not far from Sizewell and have watched the progress of the new power station over
57. r word I don t know why he wanted this number and probably never will I have seen no sign of the job The point is that he didn t know possibly not even if it would take one or one thousand man years He could have been on his way to a meeting where that lack of knowledge could have made him and our company look so inept as to be unemployable Now many techies would not have given that manager a straight answer to his question and I can see why what machine where what version of C what have we got to start with But that was not the requirement the salesman wanted a number that minute To have not given one would be estimidity in action So we come to PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 9 Issue 4 0 26 June 1996 Pablo s Bloody Obvious Rule of Estimation Number 2 You can always provide an estimate I don t care if there are hundreds of things about the project that you don t know what it does what the performance requirements are what the platform is what methodology you re using what the language is what level of testing is needed it is always possible to come up with some number regardless of the number of caveats you may care to set with it Yes I know that the number will be extracted the caveats forgotten and it will then be treated as is carved in stone That is not your problem Yet But to chicken out of the task under a smokescreen of
58. rding to your view of how difficult it is going to be to write the specification One consideration here is whether to include screen prototypes they may take a while to do but they are unambiguous can be agreed with the potential users and sometimes may be recycled for production use Remember that Functional Specifications have to be agreed with clients or users and this process is often iterative and time consuming Technical Specifications are also dependent on the amount of code and unit test time and may be tackled in the same way as the Functional Specification There is often a long initial period of discussion design and PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 38 Issue 4 0 26 June 1996 5 22 PABLOS_GUIDE 2 DOC 1996 Logica UK Ltd walkthroughs before the details of each routine can be written so it may be preferable to estimate this separately All projects should have someone assigned to be the keeper of the vision Functional Authority and general guru on what the system should do This role which may be full time depending on the size of the project involves processing change requests and clarifying the functionality of the system to the project team and more usually the client It is a particularly important role during the construction of the Functional Specification Similarly I would recommend a single person is assigned as Technical Authority whose remit is to
59. really think the job ought to take that long What is not okay is if you think it might take that long Mixing up the estimate with the contingency is a very common habit and the reason is very simple Pablo s Bloody Obvious Rule of Estimation Number 9 Its harder to estimate the contingency than the task Why Well you are an experienced sort of person which is why you were given this estimate to do in the first place You know that all being well this typical task would take you X days Max But it s probably not going to be you and anyway what if what if what if That s the hard bit But everybody falls into the trap of bumping up the base estimate rather than the contingency Why Well managers are partly to blame they can t PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 26 Issue 4 0 26 June 1996 3 8 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd understand why all the contingency levels are so high and arbitrarily axe them Contingency they nobly say chins out and mouths hardening to a determined line while the Dambusters theme swells in the background is theirs to bear Lies all lies The estimate is still yours and if the things you thought would go wrong do go wrong along with the things you never thought of who do you think will end up getting blamed But the way out is not to just inflate the base estimates to cater for the contingency you know is going to b
60. remain unknowns but anything which you can establish as a fact will help Eventually your list of assumptions will be accompanying your estimate It is an essential part of it Indeed some of these assumptions may be placed into a proposal However others may show you your co workers or your company in too bad a light to make explicit You can t put we assume that we ll be able to find someone who has used SQL before in a proposal It might be one of your assumptions but let s keep it to ourselves But there are some you can do something about Don t you know enough about the hardware platform Well ask Ask the client get help from other people in the company get some manufacturer s literature if there s time Is it important that a Project Manager is experienced with this size of project Get some names of possible candidates Again the rule is to split things up as much as possible If one assumption is for some skilled technical help from the client then ask yourself which functions this will be needed for and what skills are needed at each stage Identifying Project Wide Assumptions Some of your assumptions such as assumes that message handling will be provided by the TP Monitor might be considered project wide while others such as assumes this module can reuse some code from the last one may be specific to a particular task We need to separate these two groups so we don t have to build the project wide
61. roject Wide Contingency ssscccssscccssccssccccsssccscsssssscsscesssesceseossees 46 Risk Analysis iat a a a E E a ETE aE a 46 Client Stafi oneri aria i r EE E E EEEE aeianados 47 Allowances for Reuse essessessssssessesressessssstestesressessssstenteseessessesntenees 47 Pablo s Guide to Estimation 3 Issue 4 0 26 June 1996 9 1 9 2 9 3 10 11 11 1 PABLOS_GUIDE Estimating the Project Cost scccsccssssccssscsscssscssccsscsscsscssssssssssseeseess 49 REVICWS sissscdiesssiecesencSenssconssacedecssacceoseassesentseshcannsnneasSesosanteacseseasbessecnssvecescesos 51 Wid yin ga Upuris esliveatanteitest ove dae ditada ralada a ee eal oat 51 Types OE REVIEW Ses iss cuia Sainte tein alo detonado dona d aa A Bet eta peat Uia Ea 51 Now Do the Project re a e a 54 The Post MOrtem cccccscccssccsscessccscscescceecssscssncssnsssscssscessscssscssssesesees 55 And Finally sita SEAT datos Pestrsavocenesesanaa S 57 Further Information sacas iss eliveccess so crente din ata patas id oa oras ai kE neoini 59 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 4 Issue 4 0 26 June 1996 1 1 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd Introduction Estimidity and How it is Manifested No one wants to do the estimates It is the most thankless task our industry can impose a responsibility out of all proportion to the difficulty and risk of the work An unsuccess
62. s an estimate of 12 5 days and a contingency of 35 Now repeat for the remaining 165 Now this may all look complicated and worse still subjective But I would contend that the individual steps are fairly easy so long as you have a good grasp of the overall project It is a methodology designed for the estimid because you end up with lots of individual little figures why you could even put them on a spreadsheet and in turn this will give you a warm glow of faith in your figures However unlike real function point analysis every factor and weight has been assigned by you However it must be said that I would never use this method myself I have needed to adopt it on one occasion because I was working with people who had no faith in intuition Well they may call it intuition I call it experience Even if I did use this method Id still fix the results to align with my personal perception of the task But then I believe estimation is an art not a science PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 35 Issue 4 0 26 June 1996 5 The Project Time Scale 51 The Gantt Chart Okay by one means or another I will now assume you have estimated the code and unit test figures for each task along with the appropriate contingency You can now fill in your spreadsheet and calculate an overall code and unit test figure for the project We can now tum our attention to the overheads To do this it will be a
63. s is a reasonable maximum to allow at this stage There are actually two sorts of contingency and it is important not to get these confused One sort is dependent on the assumptions specific to each task It represents how confident you are about the number of days you have allocated to that particular task The other sort is the project wide contingency which represents the risks applicable to the estimate as a whole This is dependent on the project wide assumptions In either case logica Pablo s Guide to Estimation 25 Issue 4 0 26 June 1996 Pablo s Bloody Obvious Rule of Estimation Number 8 The contingency is the sum of the risks estimated for each assumption So our project wide contingency is depenent on the project wide assumpriosn which we have identified and the contingency for each task depends on the assumptions particular to it All we have to do is estimate the amount of risk as a percentage increase associated with each assumption add it up and there is our contingency figure Easy But these percentages mount up in no time you seem to have 300 contingency on every task You must try to get as many of the assumptions as possible resolved in some way because this will increase the validity and credibility of your estimate 3 7 Separating Contingency and Task Estimates Earlier you may have made a sneaky upgrade to your estimate having drawn up your list of assumptions That s okay so long as you
64. sential is to arm yourself with every relevant document you can and to see all the people who are involved Ask questions and get to know what the task you are being required to estimate is all about Maybe it is something you are already familiar with in which case this won t take long But usually such familiarisation is the most important step in the estimation process However you only have a limited time to do your estimate Hell I didn t do all this stuff when the manager asked me about the C compiler But in normal circumstances I would maintain that at least 50 of the time available should be taken up with research and with the all important period to allow your natural instinct for evaluation abstraction and yes estimation to get to work I would like to allow more than 50 but I know how long it takes to assemble all the figures and charts for presentation You may well also be asked to come up with the ideal solution the magic idea which will set our proposal apart from the competition or get the all important funding for your pet project And this you must admit is not going to occur to you unless you have absorbed all the facts and set the subconscious to work 2 2 The Estimatable Entities So let s assume you have now got a good nose for the project have ascertained everything down the inside leg measurement of the Project Manager and are thirsting to begin your estimate You now need to consider Pa
65. spell on site in Bromsgrove thinking in terms of a good rest and are immediately confronted with something completely strange to code up The training never happens or is delayed so long that the staff know more than the trainers I ve tried using every buzz word I know training ramp up familiarisation learning curve briefings but it s no use No manager seems willing to admit that their staff are unable to start coding on a new project at the drop of a hat The only alternatives are to add this ridiculous assumption to the list or secretly to weight the estimate somewhere unobtrusive The situation is even worse when the client is able to see the task breakdown Why should Logica staff get trained up at my expense is often their argument Even though we all know that the problem would still be there even if the project were staffed by the client themselves the pressure is often to remove or hide this overhead logica Pablo s Guide to Estimation 19 Issue 4 0 26 June 1996 3 The Estimation Process 3 1 Defining a Typical Task Usually we will want to estimate the code unit test tasks first This will either allow us to estimate the overhead tasks on a pro rata basis or at least give us some sort of idea that our estimate for these is correct It is often the case that the code tasks are all of roughly the same type or that there are a number of groups of tasks of the same type For ex
66. ssume it is in some way synonymous with or additional to the profit made by a project It is not It is your estimate of the percentage error on your raw estimate The important things to note are firstly that the contingency is another estimate and secondly that it must always accompany any raw figure It is a little like the way in which resistors are always quoted as being say 100Q with a 1 tolerance The difference with contingency is that it is always on the upwards side the resistor may be 99Q but a task estimated at 20 days with 50 contingency is never going to take 10 days What this pair of figures says is that even if all our assumptions are incorrect then it is unlikely to take more than 30 days to do the task At the very least you ought to be able to guess a couldn t possibly be more than that sort of figure But I am not saying that this is the one you should use It is the with contingency figures are the ones you are going to be using from now on and which will make up your final estimate In a reasonable world some of the assumptions may work out for the worst while others may just disappear The idea is not to take the gloomiest possible view but a considered risk You can never cater for every possible situation or else the contingency will always be infinite So to go back to our example we are not saying it would be impossible for the task to take longer than 30 days All we are saying is that thi
67. still believe them and if you have just gratuitously upgraded them and persistently stick to these inflated values just because of naked and unashamed estimidity then it really is your fault if new and interesting projects never seem to get started up But for developments that do start over estimation is also a possibility If you have seen a project where all the paperwork was done a project where the staff had all their holiday when they wanted it a project where no overtime was needed a project where system testing showed up no faults a project where a score of eight million was racked up on Tetris or a project where every desk was free from listings manuals half eaten burgers and polystyrene cups containing something Alexander Fleming would have given his right arm for then you have seen an over estimated project In the heyday of computing i e the early 70 s such things were the norm you think all those Snoopy calendars were done in people s spare time today s world is more competitive and we can no longer afford to bid projects that will easily run to time and budget So we need precision in our estimates not just a it can t possibly take longer than that attitude 1 6 When Can An Estimate Be Provided I was passed in the corridor a few years ago by a salesman How long do you think it would take to do a C compiler he asked by way of greeting I gave a number of man years and we passed without a furthe
68. t software Dependence on bought in packages Level of testing needed e g will we need to do written unit test plans results Development environment technical and site considerations Availability of knowledgeable people Size of project and possible time pressures How much interference you expect number of changes that may be needed Any constraints on reliability storage performance quality etc Must meet dates Your list will be very different from this longer and unique to your project Make your list and see how hot that figure you plucked from the air or wrestled over still feels Remember that the aim is to make you feel good about your estimates and one way to do that is to know what it is that you are worried about But don t cheat Don t put down such a great long list of assumptions that it s almost certain that some will turn out to be untrue This is another manifestation of estimidity I don t want to see something like Assumes that the staff are all very competent in your list you know what the average is you may even know who the proposed staff are so your estimate must embrace that PABLOS_GUIDE 2 DOC 1996 Logica UK Ltd logica Pablo s Guide to Estimation 23 Issue 4 0 26 June 1996 3 4 3 5 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd Reducing the List of Assumptions Of course you must do all you can to reduce your list of assumptions Some are and will always
69. the last few years I hasten to add that this is not the main reason I spend time there most of the area is still very beautiful I couldn t help noticing that the methodology was not to dig a huge hole in the ground and then say Hmm what will we do now Nuclear gas or coal fired Pressurised water or gas cooled Only software engineers work like that Let s build the easiest cheapest flashy interesting beneficial cost effective quickest bit first has come the cry from a thousand different projects And we ll worry about the rest later And of course it is taken for granted that serious changes to functionality can be introduced at any stage and all within the same timescale Any other types of engineers would laugh at such requests software people accept them as a fact of life This same unworldly approach is applied when considering estimation The argument seems to run that accurate estimation won t get the job done any quicker so let s just plough on until we re through But how many times in work in life in general do we get this luxury We use estimation every day in calculating when to leave for work in order to get to our desk on time but not too early in deciding if there s space in the tube carriage for just one more body in determining if there s enough Banana Bubbles left to last the week It is just one factor in the thousands of judgements which govern our everyday lives Life software an
70. ular task The coward s way out is to take the highest each time Usually one estimate is consistently higher than another so the loser naturally feels his work has been in vain An even worse scenario can arise when some decision maker decides to take the lowest from each set of figures out of expediency All this must be fought If the concept of doing two separate estimates is to be of use then the comparison must be thought out on a task by task basis possibly monitored by a third party Again it is usually the case that one of the estimators has a greater depth of knowledge of the situation than the other and should ultimately take the responsibility PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 54 Issue 4 0 26 June 1996 9 3 Now Do the Project Once the estimate has been reviewed and revised then there is nothing more to be done In Logica the next stage is the Bid Review during which some assumptions may be questioned and the contingency altered Rarely in my experience are the raw estimates affected Assuming the project goes ahead there is nothing more to do than sit back and acknowledge the plaudits of your colleagues as they undertake a well planned and well estimated set of tasks and your superiors as they appreciate the precision with which they were able to plan and control its costs PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 55 Issu
71. wonderful mystic magical number that has been divined by a method involving no imagination no guesswork and the minimum of involvement with the individuality of the system But is such a measure complete or accurate Are these factors and weights relevant to Logica projects Everything about function points seems to me to be based on mainframes and files and inputs and outputs and all the rest of the stuff I threw out with my flowcharting template It is certainly not appropriate for anything involving lots of calculation real time processing or communications But anyway this part is harmless A measure any measure of function size and complexity may have its uses The hard part is converting this into a measure of the time it will take to implement the function or even into lines of code Here there are any number of formulae but even less science One example is the COCOMO tool much touted within Logica While can understand the motivation of those who enjoy a consultation with the cauldron on the blasted heath I do not understand the use of a method which is far more difficult to employ than the simple task by task educated guess which I advocate For in COCOMO you need to estimate all sorts of difficult things Like the programmer capability come on now are they in the 15th percentile or the 90th percentile A mixture Sorry COCOMO can t handle that Or the requirements volatility well yes just precisely how
72. ystem Integration Test Specs 25 15 29 1l System Integration Test 80 20 96 Includes fixes by dev team 1D Parallel running 20 30 26 Support 1D Acceptance Test Spec 25 15 29 1D Acceptance Test 35 30 46 Including bug fixes 1D User training 10 15 12 Not much to demo although quite a few users 1D Live system support 25 30 33 Overheads Total 1323 Phase 1A Total 1534 PABLOS GUIDE 2 DOCO 1996 Logica UK Ltd logica Pablo s Guide to Estimation 17 Issue 4 0 26 June 1996 2 4 Tasks Easily Forgotten As I said the omission of tasks is more critical than the estimation of each one Some which are regularly ignored are Familiarisation see below e Time it takes to get documents agreed with the client or users often causing delay Design and agreement of the user interface e Integration simply building a large system can be a slow process every day Processing of change requests and the effect of these on the developers Test data set up and maintenance Operator facilities to monitor and run the system Testing of fallback procedures Help text on user screens Setting up and understanding bought in packages Testing that performance and sizing requirements are met Setting up the development environment Moving from the development environment to the target Correcting problems found during testing Bits of code to be written that are not directly attributable to any one fun
Download Pdf Manuals
Related Search
Related Contents
9 May 2008 9 May 2008 - Faculty Home Garmin Software Version 0321.23 System Maintenance Manual Modèle de la charte graphique du gouvernement GBS 75 AE Professional 機器仕様一括ダウンロード(PDF形式) mode-emploi-arrete-s.. ES_TVPlayer150_COMPLETO. REV.indd FAQs : Analyseurs NomaSense O2 A13000503 1300 IMPRIMACION YP Keracem® Pronto Copyright © All rights reserved.