1. 7 Inside view of the bezel Bezel alignment guides ge eran eee ee ee ee ee G ee ee eee eee ee eee eee ee eee ee ee ee ee ee ee ee eee ee ee ee a eee fee i i No NE a ee eee em ee eee ee eee i No EE ee re re rs nd or rs rs re or se ser re Foer H HA HA RS ENN RR ERE ER EE EE EEE tl ra rand Gr re Fr re re rs re re rer Dr rs rs rs rs and sr rs rss re J mm m um mn a EN ON YA EE KE KN ME KN KE ME KE ss us vi un En KE KE ME ME EE EE o EE ee vw un un un DE KE KE ME EEE DP or I or re re fr re re fr For For fr fe fr fr fr ee rd sr se ee ee ee el re re re re As oss rs se or se rss re re se N see re eee Ao or rs eee rs see rss rs eee eee ee ee re ee re ee eee EE E E E m m VE VE KE KE E a EE ee ee E mn mn mn eee V KE KE KE MO ON ee ee a EE EE re ee eee eee eee ee eee eee eee ee ee ee rs ee ee Go eee a ee an ee ee ee ee ee EE ee ees Zee ee eee ee Go ee oe ee fee eee eee eee ee m E E fA on N l es fa m m eee eee ee es ee ER i ee ee ee ee KE M ee ee ee ee ee ee ee EE 4 eee eee ee eee ee ee es ee A ee ee ee ee MER ee ee ee PE eee eee eee eee ee ee es A Lightpipe assembly This side down 4 Insert the screws through the ears on each side of the J930s unit Two screws on each side Ge
2. support promise com
3. 5 Anchor the rail to each side of the J930s unit as shown below using a single screw See Figure 3 6 Lift the J930s unit and place it in the rack with the guide blocks on top of the rails This action removes some of the weight while connecting the rails from the rack to the enclosure See Figure 4 Figure 4 Guide blocks rest on top of the side rails Top of rack rail Enclosure guide block 7 Carefully engage the enclosure rails into the rack rails and slide the J930s unit into the rack in until you hear a click See Figure 5 The click indicates that the enclosure rail tabs are locked into place Figure 5 Enclosure and rack rails Enclosure rail Latch release tab 8 Push the J930s unit all the way into the rack This completes mounting your J930s unit in the rack Task 2 Installing the Front Bezel To install the bezel onto the front of the J930s unit 1 Squeeze the two release tabs on the front of the J930s unit See Figure 6 2 Carefully pull the J930s out of the rack until the enclosure rail tabs engage Figure 6 Front of the J930s unit without bezel Bezel alignment pins ooo PERRETE nannnnnnn eccce BERR EERE BERR o 600o O Release tabs Bezel alignment pins 3 Hold the bezel with the lightpipe assembly at the bottom Position the bezel so the alignment pins on the J930s unit slide into the alignment guides on the inside of the bezel See Figure 7 Figure
4. See Figure 22 You can cascade up to two J930s units in this manner Figure 22 A redundant cascading DAS connection SAS EXP port SAS EXP port VTrak RAI Subsyste SFF 8088 external I ST 4X to 4X SAS cables HOST 3 port HOST 1 port HOST 1 port gt HOST 3 port VTrak J930s HOSTEN HOST 1 port Cascade Configuration 1 Cascade Configuration 2 This completes the data cable connections Go to Connecting the Power Task 6 Connecting the Power The VTrak J930s ships with clip assemblies to secure the power cables The clips attach to the Power Supply Cooling Unit PCM To secure the power cables 1 Insert the barbed end of the band into the hole until it snaps into place 2 Attach the power cables to the PCM 3 Place the clip over the power cables slide the clip to the end then squeeze the clip to tighten it See Figure 23 2012 Promise Technology Inc All Rights Reserved Figure 23 Securing a power cable with the clip assembly Power supply switch Slide the clip to the end of the power cables Pull this tab to release the clip Pull this tab to position the clip Insert the barb into the hole To reposition or release the clip pull the tabs as shown Power up Sequence Single Unit To power up a single VTrak J930s unit 1 Switch ON both PCMs of the J930s unit 2 Wait at least
5. Warning Before you begin read the VTrak VTJ930s Warning and Caution Notice document Task 1 Mounting the J930s Unit in a Rack The VTrak J930s unit installs into your rack using the supplied mounting rail kit Before you start verify that you have these rack mount components e Rack rails one left and one right e Rail installation hardware screws guides and bars e Enclosure rails one left and one right The rails are marked R for right and L for left viewing from the front of the enclosure Mounting the Enclosure in a Rack To install the J930s enclosure into a rack 1 Loosen the screws on the left and right rack rails and adjust the lengths accordingly to match the depth of the rack Then re tighten the screws 2 Secure the rack rails to the front and rear supports of the rack using the screws and hardware as shown below Figure 1 Left rack rail front view Rack rail attached at the front the rack Figure 2 Left rack rail rear view Rack rail attached at the rear of the rack 3 Tighten all screws securing the rack rails into the rack 4 Position the enclosure rails on each side of the J930s unit with the rails over the five keyhole tabs Then slide the enclosure rails into place See Figure 3 Figure 3 Side rails attached to the J930s unit Keyhole tabs J930s unit ov lt Attaching screw l ORY NI D TECHNOLOGY ING Trak J930s Quick Start Guide
6. letes drive carrier assembly See Figure 13 Figure 12 Drive carrier with a 3 5 inch drive Release rail Handle Pivot rail Slot B Mounting Reece Mounting screw Tab A Mounting screw i Mounting Pa screw Physical drive a Data power connector Figure 13 Assembled drive carrier with a 3 5 inch drive Pivot rail Physical drive Release rail Data power connector Installing the Drive Carriers To install the drive carriers into the J930s unit 1 Squeeze the two release tabs on the front of the J930s unit See Figure 14 Figure 14 Rack release tabs on the J930s unit Release tabs 2 Carefully pull the J930s unit out of the rack until the latches engage 3 Pull up on the release handles of the drive bay doors to unlock them See Figure 15 Figure 15 Drive bay doors Pull up here Release handles 4 Open the drive bay doors Figure 16 Drive bay open Drive bay doors Drive bay Release handles 5 Pick up a drive carrier assembly and press the release catch to release the handle See Figure 17 Figure 17 Drive carrier assembly Handle Release catch 6 Slide the drive carrier assembly into a drive slot until the carrier contacts the baseboard Carefully press down on the handle until it locks the drive carrier assembly into place See Figure 18 Figure 18 Sliding the drive carrier assembly into a slot Handle down and locked Handle open Front Drive carrier assembl
7. nnect the HOST 3 SAS OUT port on the same I O module of the first VTrak to the HOST 1 SAS IN port on the second J930s unit You can cascade up to two J930s units in this manner Figure 21 A cascaded DAS connection SAS EXP port TSOP VTrak RAID Subsystem SFF 8088 external 4X to 4X SAS cable HOST 3 port HOST 1 port VTrak J930s HOST 1 port VTrak J930s This completes the data cable connections Go to Connecting the Power Redundant Cascading DAS Connection To setup a redundant cascading DAS connection 1 Connect a SAS EXP port on the VTrak RAID subsystem to the HOST 1 SAS IN port on the first J930s unit See Figure 22 Use a SFF 8088 4X to 4X external SAS cable supplied with the J930s unit 2 Connect the HOST 3 SAS OUT port on the same I O module of the first J930s unit to the SAS IN port on the second J930s unit 3 Connect the other SAS EXP port on the VTrak RAID subsystem to the HOST 1 SAS IN port to the other I O module on the first J930s unit 4 Connect the HOST 3 SAS OUT port on the same I O module of the first J930s unit to the HOST 1 SAS IN port of the other I O module on the second J930s unit 5 Connect the remaining J930s units in the same manner Do not cross connect the I O modules Maintain a separate cascade configuration from the VTrak RAID subsystem to the last J930s unit
8. ntly tighten the screws See Figure 8 Figure 8 Attaching the bezel to the J930s unit Screw 5 Press the green rail tabs on either side of the J930s 6 Carefully push the J930s into the rack until the two release tabs engage Task 3 Installing the Cable Management Kit The J930s unit includes a cable management kit to organize your and SAS and power cables in the rack The cable guides enable you to slide the J930s unit out of the rack without disconnecting or tangling your cables You must install the J930s unit in the rack before you can install the cable management kit To install the cable management kit 1 Attach one end of each cable guide as shown below to the rear of the enclosure using the attached thumbscrews See Figure 9 Figure 9 Cable guides attached to rear of a J930s unit J930s unit Thumbscrews 2 Cable guides 2 2 Attach the other end of cable guides to the rack rails using the pins from rack rail kit See Figure 10 2012 Promise Technology Inc All Rights Reserved Version 1 0 Part Number G6102J93S000000 Figure 10 Cable hardware attached to rear of rack Mounting pins Rack rail 1 on each side 3 Route the SAS and power cables through the cable management rails as shown below The cable management rails have slots for plastic ties or Velcro cable wraps to hold the cables in place See Figure 11 Ties and wraps are not included Figure 11 Cable guide with SAS and
9. one minute and then power up the VTrak RAID subsystem Power up Sequence Multiple Units In the power up sequence the first J930s refers to the J930s unit connected to the VTrak RAID subsystem The last J930s refers to the J930s unit at the end of the cascade To power up the multiple VTrak J930s units 1 Switch ON both PCMs of the ast J930s unit in the cascade See Figure 24 2 Wait at least one minute and then switch ON both PCMs of the next J930s unit in the cascade 3 Wait at least one minute and then power up the VTrak RAID subsystem Figure 24 Power up sequence for cascaded units Step 3 VTrak RAID lt subsystem Step 2 first J930s Step 1 second J930s When boot up is finished and the J930s unit is functioning normally e The Power LED shows green e Other LEDs are dark See Figure 25 Figure 25 J930s front panel LED display Power POWER ON SYSTEM FAULT SYSTEMID USI HDD FAULT USER DEF SYSTEM FAULT SYSTEMID HDD FAULT COVER OPEN USER DEFINE 1 USER DEFINE 2 USER DEFINE 3 If any other LEDs are lit see Chapter 3 of the VTrak J930s Product Manual Need assistance and more information PROMISE On line htto www promise com support support_eng asp Web site E mail Support http
10. power cables installed Power and SAS cables Install cable wraps here 4 Test the cable management system by sliding the J930s unit all the way out on the rails Ensure that the unit moves smoothly and that there are no cables loose or binding when the system is slid back into the rack This completes the installation of the cable management kit Task 4 Installing Physical Drives The VTrak J930s JBOD expansion unit supports e 93 5 inch and 2 5 inch form factor e SAS drives 6 Gb s and 3 Gb s e Hard disk drives HDDs and solid state drives SSDs e Supports any mix of SAS and SATA drives simultaneously in the same enclosure For a list of supported physical drives download the latest compatibility list from the PROMISE support web site Assembling Drive Carriers for 3 5 inch Drives For 2 5 inch drives see Chapter 2 of the VTrak J930s Product Manual The drive carrier consists of two parts a release rail and a pivot rail plus the attaching SCrews To assemble a drive carrier 1 Attach the release rail to the physical drive with two screws as shown in Figure 12 The drive s data power connector is at the bottom 2 Position the carrier pivot rail to the physical drive so that Tab A on the release rail inserts into Slot B on the pivot rail 3 Attach the pivot rail to the physical drive with two screws 4 Tighten the drive carrier screws to 4 to 6 inch pounds 0 45 to 0 67 Nm Do not over tighten This comp
11. y 7 Repeat Steps 5 and 6 for all remaining drives 8 Close the drive bay doors and press the release handles to lock them into place 9 Press the green latch release tabs on both sides of the J930s unit 10 Carefully push the unit back into the rack until the front latches engage See Figure 19 Figure 19 Latch release tab i Latch release tab When you have finished installing your drives go to Making Data Connections Task 5 Making Data Connections You can configure your VTrak J930s unit as e Basic Direct Attached Storage DAS Connection e Cascading DAS Connection e Redundant Cascading DAS Connection Basic DAS Connection To setup a basic DAS connection e Connect the SAS EXP port on the VTrak RAID subsystem to the HOST 1 SAS IN port on the J930s unit See Figure 20 e Use the SFF 8088 4X to 4X external SAS cable supplied with the J930s unit Figure 20 A basic DAS connection SAD VTrak RAID Subsystem SFF 8088 external 4X to 4X SAS cable VTrak J930s HOST 1 port This completes data cable connections Go to Connecting the Power Cascading DAS Connection To setup a cascading DAS connection 1 Connect the SAS EXP port on the VTrak RAID subsystem to the HOST 1 SAS IN port on the first J930s unit See Figure 21 Use a SFF 8088 4X to 4X external SAS cable supplied with the J930s unit 2 Co

Download Pdf Manuals

image

Related Search

Related Contents

user instruction manual 8510140 truck hitch mount  2 Create the questionnaire  KOHLER K-1647-PC-G Installation Guide  Manual de instrucciones para el compresor de aire Eheim  PNP202 - Textfiles.com  762A_PSC Rev 1_1 - Comune di Valenza  MANUAL DE SERVICIO - Electro-Frig  15. Reporting  EQUIPMENT Operation Manual Loctite® SD10 Digital Syringe  Guida alla Progettazione FLX Series  

Copyright © All rights reserved.
Failed to retrieve file