Home

THOR User Manual v2.0

image

Contents

1. AN Groundline Port INDUSTRIES THOR Pole Tester User Manual Operator Version 2 0 Final July 2015 THOR Pole Tester User Manual Operator CA 7 Groun ean THOR Pole Tester User Manual Operator Table of Contents 1 Introduction to the THOR Pole Tester annrrnnnnennnnennnnvrnnnnennnvennnnennnnvennnvennnnuennn 3 2 Principle of the THOR Pole Tester rrannrnnnnnnennnnnnrnnnnnnnnnnnnnnnnnennnnnennnnnennnnnvennn 4 5 SENG UD eee E E e a Ea 5 3 1 Joer DA EEE E E ET 5 3 2 SOMME STING COMA 00 11 1 SEE A EE EE E 5 A AP ee 6 Ds TeSuUNO POET SE ctacawcteasdawct e EE 7 PortaCAT Industries Pty Ltd 2015 dline ENGINEERING Page 2 A Groundline ENGINEERING ea THOR Pole Tester User Manual Operator 1 Introduction to the THOR Pole Tester The THOR Pole Tester is an instrument designed for a fast and effective safety assessment of timber power poles It is designed to test from essentially the top of the pole through to the base in a matter of seconds providing the operator with a simple response as to the fitness to climb or to subsequently test further The equipment comprises The handheld electronics unit geophone An impulse force measuring hammer the hammer carrying case AC Power Adaptor USB to LEMO connector Handheld Electronics Unit r oaa THOR POLE TESTER Data Cable PortaCAT Industries Pty Ltd 2015 Page 3 N 7 Groundline ea THOR
2. Pole Tester User Manual Operator INDUSTRI 2 Principle of the THOR Pole Tester The instrument detects analyses and records the signal of a series of stress waves entered into the pole by the hammer On board processors analyse the signal based on the duration of the wave form against the impulse force and provides the operator with a visual clue as to the state of the pole When the force is applied to the pole from the impulse hammer the stress wave travels up to near the top of the pole and down to near the base The location of the test is important so that the waveform for the signal results in the most effective analysis i i i Height of Test Zone Signal Response In presenting this response the THOR Pole Tester doesn t provide the end user with an engineering analysis of the pole but a general indication of the pole condition An important feature of the THOR Pole Tester is that the recorded wave form is able to be re assessed as algorithms and analysis tools improve Where the expected duration of the wave signal relative to the force is within a particular range the THOR unit provides the operator with a traffic light signal response of either green amber or red The on board analytics will be improved as more pole information is recorded and analysed PortaCAT Industries Pty Ltd 2015 Page 4 5 7 Groundline OS ENGINEERING Porta INDUSTRIES THOR Pole Tester User Manual Operator Eh
3. NN 3 Setting Up There are several items that need to be completed before an operator is able to progress to using the THOR Pole Tester in the field Once set up there is limited requirement to maintain these files Do not delete any of the system CSV files as all are critical to the operation It pays to charge the unit prior to their operation and a power adaptor is provided for this purpose It generally takes an hour or so to fully charge and the unit will advise when charging is complete With an efficient power management system on board a fully charged THOR unit will operate for at least a couple of days Power Supply Socket Pa C2 3 1 User Data User data in a comma separated value CSV format is able to be updated by Groundline Engineering with specific information or generic parameters e g UTILITY01 Otherwise a person can revise the User csv file themselves but they must keep the same format Any variation to the file will corrupt the operation of the THOR unit 3 2 Connecting Components First make sure that the rubber end of the hammer is attached firmly Continue to tighten every 4 or 5 poles to make sure the energy transfers properly through the bolt The components provided with the THOR Pole Tester are straightforward with the cables from the geophone and the hammer fastened into the base of the unit into the respective colour coded adapters These are not interchangeable between the hammer and geophone and no forcin
4. SC button to return to the Main Menu without making any changes PortaCAT Industries Pty Ltd 2015 Page 12
5. e roughly enough to bounce back the hammer to the original position with a loose hand Any force applied that is too hard or too soft will result in flawed result Hammer value indicates too soft or too hard Make sure the geophone is held tightly and firmly in position against the timber pointing to the centre of the pole whilst swinging the hammer Keep the geophone and hammer strike at the same level when testing the pole e If you are unable to test on either side of the pole then place the geophone in the appropriate location and use the hammer as close to 180 as you can PortaCAT Industries Pty Ltd 2015 Page 6 N K Dy P Groundline THOR Pole Tester User Manual Operator z o Cc wn a m wn 5 Testing Procedure For routine testing follow below operating procedure I Connect the components and turn on the THOR Pole Tester by pressing the power button G 2 The firmware loads and the introductory information displays Press any key on the keypad to progress to the Main Menu 3 The current user and the menu options available are displayed Note the serial number for the Hammer and the Geophone these should match the items that come with the kit 4 Wait until the GPS position is determined PortaCAT Industries Pty Ltd 2015 Page 7 N K Dy 7 Groundline ENGINEERING Port T INDUSTRIES THOR Pole Tester User Manual Operator 5 If you want to see the pr
6. g is required There is no particular order required when connecting the components Connect the BNC connector end of the cable to the base of the hammer PortaCAT Industries Pty Ltd 2015 Page 5 7 Groundline SZ ENGINEERING Port INDUSTRIES THOR Pole Tester User Manual Operator A 8 Note the raised bumps at the end of each connector These are specific to each socket and grooves are located that match the pattern of the connector The cables are also colour coded to the sockets yellow for Hammer and red for Geophone There is a red dot on both the socket and the connector to line up the grooves to the raised bumps 4 Application The general rules of applying the THOR Pole Tester are to Place the geophone on one side of the pole within 100mm of ground level where possible For reinforced poles the effective ground line is at the top of the steel Choose an area of the pole that is solid and has no sapwood separation In general the hammer is used on the opposite side of the pole to the geophone If unable to reach around then go as far as possible so that the hammer blow is not affected by the shortness of the cable It is not important what orientation you use the geophone and hammer around the pole although inline is preferred When swinging the hammer only go back about 30 40cm and swing at the pole with only moderate force Generally the force applied to swing the hammer should b
7. iffness S and Mobility M from the top down respectively If the hammer blow is insufficient then the words Soft Hit Striker Harder will display You have 4 attempts for each of the 4 recorded readings to obtain a valid result If the hammer blow is insufficient hit the ESC key and start again 10 A result that can be analysed will show as Valid Test Result and you will then be progressed to the next reading 11 If you have either a poor hammer strike result or a geophone error then hit the ESC key and start again 12 Continue through the remaining hammer strikes and each will give you an output summary for the reading with additional graphs for Force Velocity and Mobility that show each of the results Further Insrection Reauired SC or F2 to save PortaCAT Industries Pty Ltd 2015 Page 9 7 Groundline TG R ENGINEERING Porta T INDUSTRIES THOR Pole Tester User Manual Operator D 13 Once the four readings are successfully returned the THOR Pole Tester will advise the overall result and indicate whether anomalies are detected or not e g FLAWS DETECTED ENERGY FORCE N B If 3 of the 4 readings are each all green for Hammer Stiffness and Mobility then treat the result as No Flaws Detected 14 Press the ESC key to return to the Main Menu or the F2 key to save the result You can then choo
8. ogress of the satellite connections press the A button and go back to main menu by pressing ESC vr rm F a 6 l gner p UA Hl ii ey th k 5 a EC 7 The reading will display HIT POLE WITH HAMMER 8 Position the geophone in the appropriate location Technique Place the geophone firmly against the pole pointing straight to the centre and level Also make sure the timber is not laminated as it needs to be placed on a good clean and firm surface Place about 100mm from the ground and if on a slope then place in a situation where the geophone is on the same level as the hammer strike PortaCAT Industries Pty Ltd 2015 Page 8 AQ P Groundline THOR Pole Tester User Manual Operator 9 Swing the hammer against the pole Note that you don t have to hit the pole hard but firmly You will immediately come up with a result and each result will display along the top left of the screen The vertical bar that has the green area displayed is the amount of energy recorded by the hammer blow Technique Swing from about 300 400mm out from the pole so that the round rubber end of the hammer hits the surface as perpendicular as possible The display will show you how hard you have hit and use this to gauge whether you need to go softer or harder on the swing Each of the three vertical squares will display green amber or red for Hammer H Dynamic St
9. se to retest the pole or move to the next pole and start the process again 15 Once the testing is completed then press the power button again It will present the following display then power down PortaCAT Industries Pty Ltd 2015 Page 10 I 2 P Groundline THOR Pole Tester User Manual Operator z o FR a id an mf 6 User Setup on Device There are several items that need to be completed before an operator is able to progress to using the THOR Pole Tester in the field Once set up there is limited requirement to maintain these files Do not delete any of the system CSV files as all are critical to the operation PT1000 aoe nE pe D u G ag BR THOR POLE TESTER 16 When the start up screen and the introductory information displays press any key on the keypad to progress to the Main Menu 6 1 Changing User When the THOR Pole Tester is first loaded on the Main Menu screen it shows the current user selected To change the user press the F2 button to Edit the Sample Config uration PortaCAT Industries Pty Ltd 2015 Page 11 QI P Groundline INDUSTRIES THOR Pole Tester User Manual Operator It will display the following menu items To run through available users press the UP and DOWN buttons A new user is displayed similar to below If you want to select this user press the F1 button or otherwise the E

Download Pdf Manuals

image

Related Search

Related Contents

Dataflex Projecter/Beamer Stand 350  NV-VP30 / NV-VP25 - Instructions Manuals  Manual del usuario    Kenwood CD-224M Stereo System User Manual  StarTech.com 2m (6ft) Angled Black Apple 8-pin Lightning Connector to USB Cable for iPhone / iPod / iPad  Guide Nikon de la photographie numérique avec le    Managed Express Switch  AR6210 User Guide AR6210 Bedienungsanleitung  