Home
implementation plan - University of Arizona
Contents
1. THE SUPERCAM ARRAY AT APEX IMPLEMENTATION PLAN Version 2 2 16 October 2014 Not Export Controlled Supercam at APEX Implementation Plan VERSION HISTORY Version Implemented Revision Approved Approval Description of Changes By Date By Date 1 0 Craig Kulesa 29 July 2014 First complete draft 1 1 Craig Kulesa 31 July 2014 1 Fixed Typos 2 Alignment to subreflector 1 2 Craig Kulesa 4 Aug 2014 1 Eliminated staging at Sequitor Instrument ships directly to the summit Advanced the schedule to allow for adequate time for staging and testing 2 First round of edits based on 31 July discussion 1 3 Craig Kulesa 4 Sept 2014 1 Numerous updates to laboratory action items 2 0 Craig Kulesa 12 Oct 2014 Updates to deployment plan 2 1 Craig Kulesa 15 Oct 2014 Added draft of detailed Brian Duffy schedule for sections 5 amp 6 2 2 Craig Kulesa 16 Oct 2014 Fixed typo in schedule dates in Section 6 there were two 24 Nov schedules the latter was meant for the 25 Page 1 of 33 Supercam at APEX Implementation Plan TABLE OF CONTENTS POV ERVIEW E 4 of This oe a A ers gps pce reed iM ei eee ER dala 4 1 2 Current Instrument State amp Target Goals for Delivery sse 4 1 3 Overview of Development and Integration 4 2 LABORATORY DEVELOPME
2. 1 make FTS go using pyroelectric detector This is mostly optical alignment and validation of operation 2 Accumulate all testing substrates 3 Order 30 liters of LHe 30 liters of LN Confirm bolometer battery operation cool bolometer perform substrate testing Team ASU will have the lenses CNC machined in Tempe Two weeks August needs to be allocated to the careful design of the lens doublet and 2 3 weeks for fabrication Sept leaving as much time as possible for AR coating and testing ELECTRONICS DESIGN AND INTEGRATION Most of the electronics components will ship as they are but several issues need attention regarding integration at APEX First each component needs to be tested and validated with single phase 230V for operation items that cannot or will not be transformed to European power must stay on a dedicated North American power strip which will get direct transformed to 115V at 50 Hz The electronics will be deployed in two rackmount racks as shown in Figure 2 2 and 2 3 The DC electronics will remain in the existing 18U half height rack the IF stack includes the Hammond box FFTS and IF processor The IF stack will be mounted on the M3 protection table Figure 2 3 does not show the many DC and IF cables crossing between the DC rack Figure 2 2 Proposed locations of the two stacks Figure 2 3 Baseline plan for installation of of support electronics for Supercam electronics showing DC electronic
3. 100K DSB 90K DSB Mixer temperature 5 5K 4 5 of IFs spectrometers 48 of 64 60 of 64 Mean beam efficiency n 0 7 on Jupiter amp Orion 0 75 Sideband ratio 1 0 2 1 sigma 1 0 2 21 sigma Allan stability time 1 8 seconds continuum gt 10 seconds continuum 30 90 seconds spectroscopic gt 120 seconds spectroscopic 1 3 OVERVIEW OF DEVELOPMENT AND INTEGRATION EFFORTS In order to achieve the desired level of performance before delivery two focused campaigns for Supercam will be performed The first is to improve the yield of good performing devices in the Supercam focal plane end to end from mixer to spectrometer and the second is to improve the thermal performance of the cryogenic system to drive mixer temperatures down by 0 5 1K These two efforts lie at the leading edge of the Supercam implementation plan during early Fall 2014 A parallel and following effort will focus on integration and testing for the APEX deployment both in hardware and software The final effort will be preparation for deployment including readiness review knowledge transfer from the laboratory team to the deployment team shipping and deployment Page 4 of 33 Supercam at APEX Implementation Plan In order to maximize the likelihood of success with the very minimum of telescope downtime a tiered testing and integration plan is proposed This plan begins with a thorough laboratory checkout procedure that
4. 2 20 2 21 1 32 2 07 0 00 2 13 0 00 8 0 00 2 30 2 16 2 19 1 96 1 93 1 84 1 56 Table 2 0 Typical Y factors achieved at the HHT Median in this case is 105 DSB 80 90 100 110 120 130 140 150 Trec K DSB Figure 2 1 Histogram of the noise performance of the nominal 48 pixels used in Supercam s March 2014 run at the HHT Median Tyee is 105K DSB in this case Page 5 of 33 Supercam at APEX Implementation Plan 2 1 1 Cryogenic Mixers and Low Noise Amplifiers Previous focused campaigns to improve the focal plane performance have been successful with the current number of live devices greater than 8096 and the number of excellent devices above 50 However it is also clear that a further campaign may be beneficial as we have not yet reached the point of regression Is there low hanging fruit which can represent the focus of our effort One indication might come from the distribution of live and excellent pixels separated by 8 beam mixer block Mixer 1 2 3 4 5 6 7 8 Block live 5 7 7 8 6 6 6 7 gt 2 0 4 7 6 8 3 4 4 2 Table 2 1 Number of live pixels and pixels with Y factors gt 2 listed by mixer block Based on the number of live devices alone mixer block 1 would be a candidate for removal and repopulation However special care should be taken with this block as the working devices in the block are excellent Blocks 5 7 are uniformly mediocre and none stand out as
5. November to accept instrument delivery and begin checkout see next sections for follow on schedules Table 2 3 Month by month coarse breakdown of major laboratory development prior to shipping Supercam Page 13 of 33 Supercam at APEX Implementation Plan 3 READINESS REQUIREMENTS PRIOR TO SHIPMENT 3 1 3 2 INSTRUMENT QUALIFICATION The following needs to be demonstrated via Readiness Review prior to shipment to Chile at a designated point presumably in the week of 13 17 October 1 Cold operation of the Supercam instrument at or above the level of performance sensitivity and stability achieved in March 2014 Section 1 2 Optical losses are quantified and an estimate of system performance at the telescope made to inform observing PIs 2 Clearly defined agreed and prepared interfaces for mechanical electrical and optical subsystems Full warm electronics system is operating from 230 VAC including a declared 115 VAC transformed circuit which SORAL will manage Supercam cryocooler compressors have an understood electrical interface at APEX that is either installed or ready to install at the telescope 3 Software interfaces C amp C and data flow are operating with the APECS simulator Any modifications needed on the APEX side are expected to be agreed upon at this point Continued software development will continue with the APECS simulator after shipping DETAILED CHECKLIST To be developed once a first pass of feed
6. Personnel Brian Brandon Paul Craig and Ruben Activities Continued from 18 November 20 November Instrument setup and testing day 3 Personnel Brian Brandon Paul Craig and Ruben Activities Brian Paul and Ruben scheduled contingency for the mechanical and electrical preparation of the Supercam cryostat mount amp compressors Brandon and Craig build cable and test the operation and stability of the Supercam IF system in its rack At the conclusion of this day the IF system is notionally ready to be installed Section 5 5 21 November Pre installation review amp walkthrough of installation activities Personnel Brian Brandon Paul Craig and Ruben Activities Brian Paul and Ruben scheduled contingency for the mechanical and electrical preparation of the mount amp compressors Brandon and Craig Scheduled contingency for remaining Supercam instrument preparations and testing Cryostat is disconnected and prepared made safe for installation Section 5 5 Craig Per Carlos Phase II observation preparations discussed and prepared Page 18 of 33 5 4 5 5 5 6 5 7 Supercam at APEX Implementation Plan FACILITY REQUIREMENTS FOR STAGING 1 Staging area of footprint 15 square meters recommended Larger amount of staging outdoors for unpacking crates 2 Access to 230VAC 50 Hz power up to 10A 3 Vacuum pumping station with KF flange coupling Supercam uses KF 50 to cryostat 4 APEX
7. all deploying personnel will be intimately familiar with before shipment This checkout will be repeated to the greatest extent possible when the instrument is unpacked into the APEX facility laboratory as a prerequisite to proceeding to installation into the C cabin The off telescope checkout will serve as the final readiness check and the instrument will be pre cabled to the greatest extent possible so that installation proceeds smoothly and efficiently once the go ahead for installation has been made 2 LABORATORY DEVELOPMENT AND INTEGRATION AUG OCT 2 1 IMPROVING YIELD OF GOOD PIXELS IN THE FOCAL PLANE The March 2014 state of the focal plane was generally in good shape Table 2 0 below shows the Y factor measurements between the ambient load 275K and a liquid nitrogen load eccosorb AN 72 at 80K A histogram of the 48 pixels with reasonable sensitivity is shown in Figure 2 1 This performance has been used to characterize the mean integration time estimates for APEX but improvement in three areas would benefit the overall instrument sensitivity This effort should be the initial focus of the laboratory effort before moving onward to APEX integration 1 2 3 4 6 7 8 1 1 61 1 97 2 27 2 25 2 14 0 00 1 89 1 32 2 0 00 2 26 2 27 1 97 2 21 2 19 1 85 0 00 3 0 00 2 20 2 28 1 87 0 00 1 85 2 14 1 87 amp 2 30 0 00 2 26 2 14 2 14 1 77 2 05 0 00 5 0 00 2 28 0 00 2 13 2 28 1 19 2 10 2 14 6 2 16 1 99 0 00 2 20 2 26 2 21 1 94 1 81 7 2 26
8. at zenith the telescope must be moved out of this position for a few hours near local noon Figure 6 1 below This implies that the morning shift must never put the antenna into an unmovable state Major activities that can lock out the antenna should be done in the afternoon after Sun avoidance and continue into the evening as needed Atacama Pathfinder Experiment APEX Sun avoidance prediction for November 2014 Antenna at Azimuth 0 Elevation 90 Sun rise gt Sun set Sun transit 30 Sun Limit 20 Sun Limit Qo ooeomg November 2014 8 o 1 LI jit t 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 UT Hours Figure 6 1 Sun avoidance plot for APEX during November 2014 Note that the 30 degree sun avoidance limit would imply that the antenna needs to be unstowed and parked safely just after 10 AM local time and remains locked out of the C cabin position until about 2 30 PM 6 4 SCHEDULE OF ACTIVITIES There are many parallel activities during installation that may require assistance or oversight from APEX staff Depending on how Thomas would like to schedule APEX manpower resources we can either split into two shifts to provide around the clock coverage or divide ourselves into many parallel workstreams on a single shift Comments on these prospects is solicited 22 November Mechan
9. ds quais dese E pe M Ies S UM d sU SOS MM 25 7 2 1 Single Pixel through APEX Backend uo t hy pee d edd 25 7 2 2 Full Array through Supercam Backend seen 25 7 3 Aperture Beam 25 7 4 Instrument Calibration usare etos eret Pr aon tec auanttas se Maan 25 149 Position teet o e Moto d 26 730 On The ees Tet os oa Nep ro NE 26 T sumarse Schedule coe o eau E ui I eT iS QU ME aman ME ea Tende 26 8 MAIN OBSERVING PROGRAM DATA FLOW 26 Sols Personne On 26 5 2 Observing Program eat Ee need dale tuu pas 26 8 3 Service Mode ODBSebVIp us oio ege pr va cabellos Qa Fun a E coU penis aus 26 84 Scheduling Philosophy kernon 26 8 5 Quicklook assessment tools and 2 9 POST RUN DATA MANAGEMENT DISSEMINATION 27 9 ES Data ACGESS podere eed Ru 27 9 2 Distribution of Data Reduction ped n 27 Ttf ATCHTVAL S eerte cot e 27 10 DE INSTALLATION OPERATIONS eere eee esee eo etos esee ense esse tane a seen ee ense 27 cm oto epo tena a arch 27 10 2 Procedure and Seledile eh
10. especially needing replacement Row 8 suffers from a lack of good devices however the LO pumping of this row or its operating temperature may be a contributing factor Recommendation Swap out devices 2 5 8 on mixer block 1 Swap out devices 23 5 in block 5 Explore the reason why mixer block 8 uniformly performs poorly even when LO pumping is seemingly adequate Is the problem thermal August 2014 update Mixer blocks to be left as is We will save Hamdi s time for any emergency fixes that need to be implemented at the last minute The best strategy is to make the very best of the existing devices The previous recommendation is maintained for reference 2 1 2 Warm IF processors and FFT Spectrometers Two Caltech IF processors remain problematic and must be repaired The first is SN7 which delivers unstable passbands The second is SN1 which has not been used at the HHT due to very little IF output Both must be characterized in the lab and repaired so that they can be used Even if we ultimately choose to not use all 8 IF processors one must be carried as a spare Two FFT spectrometer cards have a single dead IF input One of these is the infamous Schein board borrowed by the STO 1 flight A current effort to revive this FFTS board to use for thermal vacuum testing for STO 2 is underway If it passes testing it can be returned to Supercam to increase the complement of FFT boards This will increase the number of working FFTS channe
11. n a NEED RR es 24 Page 3 of 33 1 2 Supercam at APEX Implementation Plan OVERVIEW PURPOSE OF THIS DOCUMENT This Implementation Plan documents the step by step efforts needed to prepare and optimize Supercam prior to shipment from Arizona and provide a description of the packing and deployment effort It is provided as a counterpart to the Supercam APEX Interface Control Document ICD which provides a direct discussion of the instrument mechanical electrical cryogenic and software interfaces to the telescope itself This document provides a broader approach that includes metrics for instrument readiness checkout of the instrument at Sequitor San Pedro before delivery to the telescope and staging of the instrument prior to telescope downtime The recognition that APEX telescope time is a precious resource drives the need for a detailed thorough implementation plan that all parties are happy with The ultimate goal is that the Supercam instrument can be successfully installed commissioned and productively used with minimal downtime This is especially important since the late November and December observing window typically has observing conditions worsening with time Statistically the best weather will occur during installation CURRENT INSTRUMENT STATE amp TARGET GOALS FOR DELIVERY Parameter Achieved Performance Target Performance March 2014 October 2014 of live mixers 52 mixers 60 mixers Median DSB
12. 16 of 33 Supercam at APEX Implementation Plan Activities Short initial visit to high site for acclimitization and to re evaluate the plan for receiving Supercam discuss staging space with APEX staff 16 November Nominal Delivery of Supercam Personnel Brian Brandon Paul Activities This will be a critical day that establishes the staging of the instrument available initial workspace The goal by the end of the work period is to have all containers safely stored with all items that cannot be unloaded without mechanical assistance unloaded and staged in the APEX entrance module This would include the compressors transformer and cryostat All other components can be manually unpacked Offloading Requirements If a box truck is sent a FORKLIFT capability is required flatbed truck is sent a truck CRANE is needed unless it is certain that we can use the facility crane to offload equipment One concern is that the horizontal reach of the facility crane may not be adequate to offload a large truck The need to interrupt telescope operations is bound not to be popular either Advice is needed here Suggested flow of operations 1 Truck arrives Supercam and APEX staff await it 2 TOOLS and CARTS containers offloaded first TOOLS container is opened to make available components for rigging and staging CARTS container is unpacked to liberate air ride cart hand truck and scissor jack cart Early availability of these items eas
13. 1W K The current performance which shows the mixers at 5 5K and the cold tip at 4 9K indicates 1 5W of load at 4K This is nominally twice the design load The significant differential between the two indicates further that the Cold Work Surface CWS has an inadequate conductive path to the Sumitomo cold tip It also indicates that the CWS is guilty of carrying the heat load to the cold tip the thermal load is not at the cold tip itself There are two basic heat paths to characterize radiative loading and conductive loading While the radiation shield at the Sumitomo 2 stage is indeed 50K the opposite end is 75 80K The lids may be even hotter due to non ideal thermal conduction If they are gt 100 then thermal loading would become a significant contributing factor and better thermal strapping of the radiation shield is required This is a straightforward test of the cryostat It is likely that there are also unwanted conductive paths One known path to consider may be the DC wiring which represents a direct but low cross section heat path from 300K We should heatsink the harnesses carefully to either 50K or 15K both stages have plenty of lift capability but one of the two may be easier to access Finally the copper bracket that connects the Sumitomo 2 stage cold tip to the CWS should be investigated There is clearly a significant temperature differential that given the paucity of functional bolts in the interface is likely i
14. Description Language CDB Configuration Data Base SCPI Standard Commands for Programmable Instrumentation NTP Network Time Protocol Page 31 of 33 Insert appropriate disclaimer s
15. N SITE STAGING AND TESTING BEFORE INSTALLATION 5 1 5 2 5 3 4 Week 47 2014 Wedk 48 2014 Week 49 2014 Week 50 2014 Week 51 2014 Brian Duffy Paul Schickling Brandon Swift Ruben Dominguez Craig Kulesa Jenna Kloosterman Bill Peters Caleb Wheeler Umut Yildiz Jorge Pineda unpack i assemble amp test install prepare for install observe commission Figure 5 1 Deployment plan with personnel color coded by speciality Gray mechanical and installation Blue instrument hardware Red instrument software PERSONNEL ON SITE 15 17 November Brian Brandon Paul 17 22 November Brian Brandon Paul Ruben Craig OVERVIEW OF ACTIVITIES The Supercam deployment team will arrive be introduced to the facility and personnel receive the instrument unpack and setup the instrument in a workspace at the high site validate operation of the instrument and stage the instrument prior to the main installation on 22 November SCHEDULE OF ACTIVITIES All Supercam activities during the 15 21 November period are to minimize impact on scheduled APEX activities 14 November First wave of deployment team arrives in San Pedro Personnel Brian Brandon Paul Activities Arrival initial acclimitization at 2400m No impact on APEX operations as stated 15 November Deployment team gains first preliminary access to APEX site Personnel Brian Brandon Paul Page
16. NT AND INTEGRATION 5 2 1 Improving Yield of Good Pixels in the Focal Plane eee 5 2 1 1 Cryogenic Mixers and Low Noise Amplifiers sese 6 2 1 2 Warm IF processors and FFT Spectrometers sse 6 2 2 Improving Cold Performance of CEVOSEM Gs ecelesia eta nearest 7 2 3 Mechanical Mounts Design and nennen 8 2 4 Optics Design TESTING Inte EaEOD uiae arare eroe teneo exeat VR ved Re NP ERE RU 8 2 5 Electronics Design and Integration siio du rt iE pede tet dt e ee eri ud 9 2 6 Command amp Control IntesratiOt ite 10 26 1 TALC WAL Cc usa cut Ceu bara otto dient Obat uet esiste iis esteri ive erts 10 PANEM Tn Dir 11 2 1 Data Flow Integratiot c5 diesen yess 12 2 8 Schedule and Resources Required uiu accedi 12 3 READINESS REQUIREMENTS PRIOR TO SHIPMENT eeee eene eene 14 Iristrument Qualification D IER idea e stib eode A EDS E 14 M cm e da spp ees 14 4 PACKING AND 5 14 4 1 Overall Philosophy of SUEVIVabIlity 14 4 2 Existing Crate Availability reco err a sre SET mace SE RE Deb iat 14 4 3 Design and Fabrication for C Ele 15 4 4 Packing Plan and Manifest List
17. Supercam at APEX Implementation Plan APPENDIX B REFERENCES documents referenced in this document Add rows to the table as necessary The following table summarizes the documents referenced in this document Document Name and Version APEX Supercam ICD V1 6 4 Sept 2014 Description Interface Control Document for Supercam at APEX Location http loke as arizona edu c kulesa binaries supercam int V1 63 5 August 2011 egration APEX APEX MPI MAN 0011 APECS User Manual online V3 0 21 July 2014 APEX MPI ICD 0005 APEX SCPI socket online V1 0 29 March 2006 data stream format APEX MPI ICD 0004 APEX Instruments Generic online V1 9 3 April 2007 CORBA IDL Interfaces APEX MPI ICD 0003 APEX Standard Hardware online V0 5 6 September 2002 nterfaces APEX MPI DSD 0012 APEX Heterodyne Tertiary online V1 0 10 January 2006 Glas APEX MPI ICD 0001 APEX Nasmyth A Cabin online V1 1 1 October 2004 APEX MPI ICD 0002 MBFITS Raw Data Format online Page 30 of 33 Insert appropriate disclaimer s Supercam at APEX Implementation Plan APPENDIX C KEY TERMS The following table provides definitions for terms relevant to this document Term Definition C amp C Command and Control QA Quality Assurance UHMW Ultra high molecular weight APECS APEX Control System FFTS Fast Fourier Transform Spectrometer CORBA Common Object Request Broker Architecture IDL Interface
18. UBLESHOOTING What kinds of issues are possible and how will we respond This is the brainstorming section for worst case scenarios and should be added to as we consider the possibilities 1 Specification of number of live mixers end to end including bias cards mixers LNAs IF processors spectrometers in Sequitor This defines the go no go situation What is this number 16 32 48 2 Ship instrument with metal plate covering window UHMWPE spare window Ship spare bias card and TS 7200 with CF card ready to go for Supercam Small flatscreen monitor and USB keyboard for Supercam9 Include null modem cable and USB serial adapter to assess from laptop 4 Ship SORAL helium manifold in case compressor or helium lines are flat or damaged Bring spare CTI line spare Sumitomo line 5 Nightmare LO dead on arrival Emergency ship to VDI and return Can we get a spare Spacek amp from VDI Page 19 of 33 Supercam at APEX Implementation Plan 6 INSTALLATION INTO THE C CABIN AND EARLY COMMISSIONING 6 1 OVERVIEW OF ACTIVITIES Starting at the transfer of telescope time Supercam and its attendant subsystems will be installed onto the APEX telescope and prepared for commissioning observations 6 2 PERSONNEL ON SITE 22 26 November Brian Brandon Paul Ruben Craig Jenna Bill available remotely 6 3 SUN AVOIDANCE CONSTRAINTS Note that the C cabin is not available 24 hours per day Since the C cabin stow position points the antenna
19. VAC if necessary Need better solution for APEX Run from 115VAC from LO mini transformer LO cooling fans Table 2 2 Summary of electronics power compatibility for APEX and mitigation strategies 2 6 COMMAND amp CONTROL INTEGRATION 2 6 1 Hardware Two issues with the implementation of the TS 7200 macrocontrollers needs to be improved In practice the slow power on timing of the Acopian 5V rail sometimes confuses the TS 7200 which wants regulated 5V power We don t see this on any other TS 7200 systems but it appears to be common for Supercam upon a cold power up Once on if the power is cycled all macrocontrollers typically come up fine Recommendation bring out simple reset switches to an accessible front port In general this is a good idea in case one macrocontroller hangs it can be reset without powering down the entire focal plane While unnecessary in 2014 s run at the HHT it is nevertheless a good risk mitigation The no name CF cards that were originally purchased for the TS 7200 s are already showing signs of wearing out Two of the 8 systems have had corrupted filesystems again an issue not seen elsewhere Recommendation Replace them Use dd to generate a reference image of one of the TS 7200s say supercam1 and clone it onto 8 new Sandisk 4 GB CF cards Write a shell script to turn each supercam1 into the correct system IP address etc Supercam9 the 1U rackmount data acquisition comp
20. X m TOTAL WEIGHT 2250 kg 4 4 PACKING PLAN AND MANIFEST LISTS This section will be developed once the basic plan for crates has been vetted and adjusted accordingly 4 5 We will provide Karina Celedon ESO with a prospective load plan for the shipment from Santiago We will clearly identify mark the three pieces to be loaded last first off We should have Thomas s concurrence on this SHIPPING DETAILS SCHEDULE AND RESPONSIBILITIES I am book keeping 24 27 October as the shipping period for a 15 November delivery at the site From Carlos de Breuck l The Supercam team will be responsible for providing the adequate packing material crates protections insulation etc The Supercam team will be responsible that all parts of the instrument will be properly packed for transport also for the return shipment from APEX ESO will coordinate the customs clearance in Santiago Contact person is Karina Celedon at ESO Chile ESO and Sweden will share the shipping costs both international and within Chile This will be initially paid by ESO and reimbursed by Sweden for their part ESO does not take any responsibility for theft or damage to the crates during the transport or un loading during the entire shipment process Page 15 of 33 Supercam at APEX Implementation Plan 6 While help will be provided by the APEX team handling of the instrument at APEX will also remain the responsibility of the Supercam team 5 O
21. access to processed level 2 maps is needed One path to this is already underway using a highly reworked version of CSIRO s gridzilla package which natively speaks SDFITS SCHEDULE AND RESOURCES REQUIRED Table 2 3 shows the high level month by month schedule of laboratory activities and Table 2 4 TBD after initial feedback itemizes the detailed work efforts with a suggested responsible person and estimate of the work expenditure in hours Page 12 of 33 Month Supercam at APEX Implementation Plan Work efforts listed by type deadlines by end of month July Draft ICD and implementation plan developed discussed at site visit reworked accordingly August Mechanical Complete design of mounting interface completed including FEA of critical items and sent out for manufacture Mini milestones preliminary review 7 29 August critical review 8 September Optical Complete lens and AR coat design complete and sent out for manufacture Cryostat Reworked mixer blocks as recommended CTI 8200 compressor leak fixed unit purged and recharged Cold tests for radiation shield temps sans mixers Fixes for radiation loads as needed Fixes for CWS cold tip interface plate performed as needed Heatsinking for DC wiring IF SN1 and SN7 modules repaired and installed for operation Electrical New power supplies transformers UPS purchased for testing cables repaired C amp C reset switches serial consoles new CF cards b
22. am will get the needed help from APEX personnel to implement changes to that pointing model APERTURE AND BEAM EFFICIENCIES Total power measurements of Mars and Jupiter the moon Orion OMC can be used to estimate the beam efficiency in comparison to that expected from laboratory expectations INSTRUMENT CALIBRATION Basic calibration of the intensity scale to antenna temperatures will be done in the usual manner through the insertion of an ambient temperature calibration load at regular intervals typically every row or few rows of an OTF map The per beam gains will be calculated by OTF mapping a spectral line point source with all 64 beams the same map that will also generate the azimuth and elevation offsets for all beams relative to the fiducial pixel The receiver noise temperature will be evaluated through a hot cold sky calibration at infrequent intervals provided that the instrument configuration is stable Page 25 of 33 7 5 7 6 7 7 Supercam at APEX Implementation Plan Forward efficiency will be validated using the skydip technique in combination with the facility water vapor radiometer Reliable operation of the instrument s two position calibration load will be verified as a part of instrument checkout If the data is passed to APEX for processing by apexOnlineFitsWriter and Calibrator calibration load information such as temperature must be passed to APECS Otherwise Supercam s internal data pipeline must get the app
23. back on the ICD and this Integration document has been completed 4 PACKING AND SHIPPING PLAN 4 1 4 2 OVERALL PHILOSOPHY OF SURVIVABILITY Since most of the deploying Supercam instrument system is unique there are no backups or spares of many mission critical items bias electronics LO FFTS cards cryostat mixers IF processors etc This makes the safe and effective packing and shipping of the instrument absolutely critical All efforts to optimize the system in the laboratory will be lost if the deployed system is not functional in Chile Even the simple loss of the Supercam Local Oscillator LO would potentially doom the entire run Not only must we be extra cautious when packing to maximize survival potential in case forklift happens but the high site has very low relative humidity ESD can potentially be as deadly as it is in Antarctica EXISTING CRATE AVAILABILITY Numerous excellent crates are available from AST RO STO 1 and HEAT To minimize impact to ongoing programs it is recommended that we utilize as much from AST RO as possible Several large crates are or were available at Sunnyside that may be of value to Supercam now In particular we might especially consider the gray Hardigg rackmount cases that we formerly shipped Wanda and PoleSTAR dewars in for rackmount electronics or other hardware The canonical standard APL crate could be used for lab tools and other incidentals Update BLINC MIRAC Hardigg
24. cases and dewar crates located at Sunnyside have been green lighted for use with Supercam Page 14 of 33 Supercam at APEX Implementation Plan 4 3 DESIGN AND FABRICATION FOR CRATES The following crates are envisioned for shipping Please edit to suit We will utilize Phil Hinz s Hardigg cases to the greatest extent possible l Cryostat crate Includes most of Supercam mechanical mount Large Hardigg container Dimensions 1 4 x 1 1 x 1 5 m Weight 600 kg Compressor crate 1 CTI 8200 and Sumitomo Indoor unit Dimensions 1 1 x 0 9 1 Weight 325 kg Compressor crate 72 Sumitomo Outdoor unit Wooden crate Dimensions 1 2 x 0 6x 1 4 m Weight 300 kg Electronics rack Contents unloaded and packed into gray Hardigg WANDA crate and empty rackmount chassis disassembled and shipped flat same crate Includes all DC cables UPS amp coax Dimensions 0 8 0 8 x 1 4 Weight 350 kg Transformer crate 480 208 VAC 3 phase compressor transformer Hardigg case Dimensions 1 1 x 0 8x 0 7 Weight 125 kg M3 table and extruded aluminum subframe Hardigg case Dimensions 1 1 x 0 8 x 0 7 m LO module sold separately Batteries not included Weight 150 kg Tools and test equipment Hardigg case Dimensions 1 1 x 0 8 x 0 7 m Weight 150 kg Staging Carts hydraulic scissor lift cart and air ride cart for instrument transfer Wooden crate Dimensions 1 x 1 x 1 2m Weight 400 kg TOTAL VOLUME XX
25. computer network connectivity N ethernet ports IP addresses need to be known beforehand see ICD INSTRUMENT CHECKOUT PROCEDURE IN THE APEX LABORATORY 1 Unpack cryostat and install onto stand Visually inspect and check vacuum Intact Put on vacuum pump if necessary 2 Install Local Oscillator Verify multiplier bias voltages and currents Double verify output power with Golay cell or pyroelectric detector if available 3 Unpack support electronics rack Reinstall into half height rack if shipped in Hardigg crate Turn on DC bias electronics and computers and validate operation on 8 channel dummy dewar 4 When DC electronics check out very carefully connect cables to cryostat and check out warm device state Compute number of live SIS devices magnets and LNAs relative to state of instrument prior to shipping 5 Install cables for and verify operation of IF processors and FFT Spectrometer 6 Prepare IP addresses and software state for C cabin installation as needed ASSEMBLY AND INTEGRATION STATE BEFORE ENTERING C CABIN Prior to installation it is envisioned that the cryostat is under rough vacuum and ready to install as a clean unit The extruded aluminum subframe will be installed once the cryostat is mounted in the U mount The bias electronics rack is integrated and cabled as is the IF processor rack The cryostat hermetic connections remain safe until the instrument is fully installed RISK ASSESSMENT AND TRO
26. d between the APECS Observing Engine and the existing Supercomm module for the HHT This module must turn Page 11 of 33 2 7 2 8 Supercam at APEX Implementation Plan APECS notifications into the relevant HHT messages and pass them onto SuperComm for actioning Testing of this system has as its prerequisite the installation and operation of the APECS simulator Both of these tasks are significant efforts DATA FLOW INTEGRATION The baseline approach to Supercam s data acquisition processing distribution and archiving is depicted in the APEX Supercam ICD in Section 7 and summarized in Figure 7 3 The augmentations needed to complete this implementation are as follows 1 The level 0 processing engine scooper will write two parallel data streams The first is the nominal SDFITS file which is written to supercam9 s SSD The second will be a new UDP streamed raw data interface to the apexOnlineFitsWriter module running on display2 This stream will consist of 64 x 900 channel structures of 16 bit data This will give the standard APEX interfaces access to data from Supercam s FFTS and a parallel data interface to the Supercam pipeline 2 Both SuperComm and scooper need access to basic information about the observation being performed This information comes through apex2hht Section 7 of the ICD describes the theory of operation 3 Archiving scripts that will push data from supercam9 to Sequitor are needed 4 Much more rapid
27. e 23 and any non specialist items from Shift 1 Then they will 1 Atthe start of the shift turn the cold heads on and begin cooling 2 Re evaluate the focal plane confirm no regressions in pixel count or in DC monitor noise Essentially we perform the on site testing Section 5 again to confirm nominal operation 3 Begin integration with APECS calibration wheel operations and all instrument related callbacks Try to push data from the Supercam FFTS to FitsWriter and see what breaks It would be good to have Bill online for this 4 Remove pump at 8 AM in preparation to be able to move the telescope before Sun avoidance If possible leave early the 25 and thereafter will be a tough slog for Shift 2 who will bear the brunt of commissioning 25 November Install day 4 Cold system validation and optical alignment Back to a single shift again perhaps Cold Testing and Focal Plane Performance Optimization Initial cold testing and instrument setup and commissioning will involve basic focal plane array setup optomechanical alignment of the LO module to the focal plane and assessment of the system performance using hot and cold loads Sensitivity The target deliverable is up to 60 IFs with a median noise temperature of 90K DSB or lower The minimum acceptable limit will be rather less presumably equal to or less stringent than the shipping laboratory state at the Readiness Review Stability The target deliverable is a media
28. es the offloading of further cargo 3 COMPRESSOR wooden containers offloaded The following items must be craned onto the ground where they can be rigged and hand trucked or carted for storage INDOOR SUMITOMO UNIT OUTDOOR SUMITOMO COMPRESSOR CTI COMPRESSOR TRANSFORMER 4 CRYOSTAT amp MOUNT container offloaded The CRYOSTAT must be craned from the container and lowered onto the air ride cart to be transferred to the orange hydraulic cart at the door jamb of the instrument laboratory The SECONDARY MOUNTING RING is then craned and rolled to storage The crate then partly unloaded is then forked or transferred to its permanent storage location remaining items in this container can be manually offloaded later 5 ELECTRONICS container offloaded into entrance module Forklift and slide into position Or crane to ground and use scissor lift cart or big wheeled dolly to roll to entryway 6 If all containers are staged into their respective semi permanent locations and all remaining items can then be manually offloaded the truck can be dismissed 7 Manual offloading and staging of materials can proceed until the work shift ends or facility space allocatable to Supercam is filled 17 November Manual unpacking and staging into instrument lab if available or appropriate workspace Personnel Brian Brandon Paul Craig and Ruben arrive Page 17 of 33 Supercam at APEX Implementation Plan Activities Manual offloadin
29. g If at least 0 5K improvement clean up all interfaces and reinstall mixers warm IV check with cryostat open When ready to cool re perform Sumitomo load curve and test thermal and RF performance with a full focal plane MECHANICAL MOUNTS DESIGN AND INTEGRATION Suggestions Tasking Ucryo and or Steward shop with the construction of the cryostat mount mount as it will classify as capital We could include all component purchases for the extruded aluminum optical subframe chopper wheel motor etc as part of the work effort The aluminum subframe and LO mount will be built at the University of Arizona as we will have the cryostat Design needs to be complete by end of August construction in September installation in the lab in October Most of the issues involving the mechanical mount are in the corresponding ICD The basic action item list 15 1 Complete final detailing in preparation for ordering machining and welding 2 Construct the upper octopod structure down to the secondary mounting ring Once tested ship to APEX as soon as practical so that it can be test installed on the telescope 3 Build U frame separately and install onto cryostat Test cryostat mount adjustability 4 Install calibration load at top of U mount OPTICS DESIGN TESTING INTEGRATION At present the cryostat camera lens is no longer coincident with the dewar window so the light path from the beamsplitter to the mixer blocks remains unchanged fro
30. g of remaining containers and staging of APEX workspace The goal at the end of this day is that the Supercam workspace is configured for operations and items needed for Supercam initial testing are made available and staged for operations If time permits the Supercam LO subassembly and Supercam electronics rack will be constructed and populated with items from the Hardigg shipping rack Configuration of workspace Work table and chairs ethernet and power as per ICD Workspace needed to hold cryostat and LO module on cart Electronics Hardigg container and Supercam half height rack box of Supercam DC cables 18 November Continued staging Instrument setup and testing day 1 Personnel Brian Brandon Paul Craig and Ruben Activities Brian Paul and Ruben construct the Supercam mount in standalone configuration Build the vibration isolation mounts and the M3 table Unpack and stage compressors and transformer and discuss their implementation and interfacing with APEX staff Is everything still clear for install Brandon and Craig focus on the Supercam electronics rack construction and preparation initial testing of the electronics with the Supercam dummy dewar and if time permits warm testing of the cryostat devices IV curves Section 5 5 19 November Continued staging Instrument setup and testing day 2 the end of this day the warm instrument has been tested IV curves and compared to the pre shipping warm state
31. ical Install Day 1 Infrastructure Personnel Brian Brandon Paul Ruben Craig Jenna arriving Page 20 of 33 Supercam at APEX Implementation Plan Activities Changeover at local noon 16 30 UTC Telescope at craning elevation away from Sun Paul Brian Ruben will work on installation of the compressors and transformer with APEX staff as needed First stage will be to crane the 3 compressor modules to the instrument platform and the transformer to the lower compressor level Compressors and lines will be transferred first They will be carted to the crane position and then lofted to the instrument platform hand truck will be used to transfer the compressors through the instrument room to the opposite side where they will be staged At this point items can be installed into place Can we turn the compressors on briefly to ensure that they operate Brandon will work with APEX to install helium lines power cables fiducial IF cable in the new cable tray Craig will work with APEX to install the UPS in the instrument rack and then help Brandon Once these items are underway it is then possible to begin to move towards the C cabin When the telescope can be slewed to zenith 18 30h UTC access to the C cabin will be possible Once two Supercam team members become free the first steps to install the Supercam mount in the C cabin can take place The installation steps idealized for the 22 are as follows At the conclusion of each s
32. ker The total power of the fiducial pixel through the APEX IF system and the full array through Supercam s IF system would be monitored while a cold load is waved in a 5 point pattern across the secondary The fiducial beam centroid should lie near the center of the secondary and the corners of the focal plane array should not spill onto cold sky in any measurable way At horizon pointing the cold eccosorb load should present a significant contrast to the atmospheric temperature Testing Supercam APEX Software Interfaces 1 Scooper to apexOnlineFitsWriter Does data transparently flow into the standard APEX interfaces Are calibrations sane Are data properly archived 2 Instrument SCPI configurations 15 Supercam recognized as a facility receiver system Can observations be prepared and executed with the proper signals being sent through apex2hht to the relevant Supercam subsystem 3 Does Supercam s own pipeline correctly see the telescope configuration and harvest necessary data to fill its SDFITS headers 26 November Install day 5 continuation of items from day 4 as needed Otherwise continue with commissioning Section 7 6 5 Uu we soe opa ds RISK ASSESSMENT AND TROUBLESHOOTING This section is difficult to mitigate but the likely and obvious issues to be worried about are Unforeseen issues in basic mechanical installation Difficulty installing mounts and or cryostat Difficulty aligning Supercam to the APEX seco
33. l line calibrators could be used in a pinch Jupiter is available during the run transiting near dawn Mars is available in the afternoon and early evening with a Sun distance of 45 50 degrees 7 2 2 Full Array through Supercam Backend 7 3 7 4 Likely to do pointing and focus using the scooper exported data interface to apexOnlineFitsWriter it is available Pointing and focus can then be carried out using facility software using one or more Supercam beams with the others used for validation Pointing for all beams is needed to get the per beam pointing offsets correctly input to the Supercam pipeline One of the first tasks once the fiducial beam is located on sky is to establish the az el offsets to all of the other beams relative to the fiducial beam This can be done by OTF mapping a centroidable source continuum or spectral line so that each beam eventually sees the source We must quickly process the map to calculate the offsets We need to figure out how to get this information into the FitsWriter derived CLASS files in addition to the nominal Supercam pipeline As a part of commissioning we need to switch to the A cabin configuration and determine if we can reliably return to the same Supercam pointing offsets A pointing run will need to be performed over the entire sky to establish the pointing parameters for Supercam I presume that we would start with one of the bolometer pointing models and that the Supercam te
34. l partners What is the role of the Supercam team in working with the Scheduler and the various PIs to ensure that the instrument is maximally utilized for best science throughput Page 26 of 33 Supercam at APEX Implementation Plan 8 5 QUICKLOOK ASSESSMENT TOOLS AND MITIGATION This and all following sections to be filled out in detail once the first draft of this Implementation and the APEX Supercam ICD is discussed and agreed upon For now the overview of the data flow as shown in Figure 7 3 of the ICD is shown below for reference 9 POST RUN DATA MANAGEMENT DISSEMINATION ARCHIVAL 9 1 DATA ACCESS MECHANISM 9 2 DISTRIBUTION OF DATA REDUCTION EFFORT 9 3 LONG TERM ARCHIVAL Supercam Supercam FFTS LevelO Level 0 5 64 beam FFTS data SDFITS Level 0 5 raw stream Level 1 MBFITS updated hourly Level 0 5 Level 1 nb paniy archive i seqdr lastarria daily daily Santiago Tucson ENA SDFITS esodata MBFITS Level 0 soral CLASS Level 1 web archive FITS hee P ee Garching biannual Pasadena data release a MBFITS 5 ESO Archive class i Ye A IPAC Archive CALIFORNIA REPUBLIC eve EE 10 DE INSTALLATION OPERATIONS 10 1 PERSONNEL Team of 3 Brian Brandon and Paul 10 2 PROCEDURE AND SCHEDULE Supercam will remain installed immediately after its 20 December end of observing It will remain in place thro
35. ls to 60 from the current 54 Finally the current splitting of the FFTS backplanes across the SORAL and Caltech chassis must end All SORAL boards need to be returned to the single 3U SORAL chassis to reduce power consumption and installation footprint This will involve removal of the Caltech backplane and reinstallation in the SORAL chassis as the 2 SORAL backplane is currently installed in STO 2 s XPV and is difficult and time consuming to extract Page 6 of 33 2 2 Supercam at APEX Implementation Plan Two additional issues need to be ironed out with the Omnisys FFTS One is the perpetual generation of single channel spikes which appear to be spurious bit errors When they happen to high order bits a spike is noted The level 0 scooper process can flag the worst offenders but it would be best if we can isolate and bury this problem both for Supercam and STO 2 s benefit The final issue which has been a continual problem at the HHT has been the occasional and aggravating lockup of the internal FFTS control computers While we hope to solve this problem in the lab it is vital to implement a watchdog or deadman switch to automatically cycle the AC power to the FFTS in the event that it becomes unresponsive IMPROVING COLD PERFORMANCE OF CRYOSTAT It is abundantly clear that the mixers are not at the design temperature of 4 5K The Sumitomo cold tip unloaded is about 3 0K The load curve of the RDK 415D indicates a slope of about
36. m the HHT Thus one set of optics need to be constructed for the sky beams Both sky and LO lenses should be AR coated The AR coating prescription assuming a teflon to UHMWPE match needs to be 1 4 wave 6 9 mil with an index of refraction that corresponds to 4596 pore volume of zitex 1 Zitex G108 is 8 mil 45 pore volume This is slightly thick and moves the band center to 304 GHz It will perform OK at 345 GHz additional 2 loss This is the best match possible using stock Zitex 2 3 4um pore size G108 is available on Amazon as fine grade zitex part number D1069175 We have a few small sheets available 3 Default sheet size is smaller than our lens diameter but larger than the nominal radius One possibility is to match triangular sheets to a given lens like filling a pie pan with individual pie slices This would require experimentation on a sample piece of HDPE Alternately we need to find larger sheets 4 The master reference for coating HDPE with Zitex is Hargrave amp Savini 2010 Proc SPIE 7741 Cardiff group They use a vacuum housing to pull the zitex tight http loke as arizona edu ckulesa binaries supercam optics Hargrave AR Coat HDPE pdf Page 8 of 33 2 5 Supercam at APEX Implementation Plan 5 We need to use the N135 FTS to verify the losses in lenses and window materials for calibration There are already many materials requiring testing for STO 2 HEAT and Supercam Action item list here
37. mprovable Does it need to be reworked If one reduces the heat load on the CWS the temperature differential to the cold tip will automatically go down This may be as much a symptom of the problem and not the primary cause The ideal goal is to see the cold tip at 4 4 2K and both the CWS and mixers around 4 5K I would define reasonable success as seeing the mixers below 5K Action items 1 Open cryostat remove devices to safe storage for testing 2 Cooldown 1 radiation shield temperature testing Move temp sensors to lids and recool Measure Sumitomo load curve with mixers removed determine 4K load to achieve performance delivered in March 2014 run If low Sumitomo cold head is sick If high then we have an excessive heat leak at 4K 3 Postmortem to cooldown 1 Calculate radiative heat loading MLI between 4K CWS and 15 50K surface contact Phil Hinz and or Manny Montoya for access to the mother lode of MLI on the 4 floor Calculate UT85 SS SS conductive load should be low and should match coax data and empirical data If radiative loading not a Page 7 of 33 2 3 2 4 Supercam at APEX Implementation Plan concern isolate conductive paths heatsink DC wires to 15K Any other thermal pathways that are bridged when we plug in mixer modules 4 Implement fixes determined in Step 3 and perform Cooldown 2 sans mixers Start Sumitomo only to compare with cooldown 1 and then add the CTI 350 after initial testin
38. n spectroscopic Allan variance time of 120 seconds or preferably more The minimum acceptable limit may be shorter presumably equal to or less stringent than the shipping laboratory state at the Readiness Review Alignment of Supercam to APEX Secondary Once Supercam is installed the primary optical alignment issue is to steer the 64 beam bundle to the secondary The radio beams can be walked out from the cryostat window using small eccosorb HOT loads to ensure that they come to their respective locations at the f 8 Cassegrain focus Note that we use hot loads as the antenna is looking at the zenith sky which should be quite cold at 345 GHz The beam positions can be carefully measured at two distances and from that angle projected out to the secondary This assures that the alignment is close Page 23 of 33 Supercam at APEX Implementation Plan To adjust the tip and tilt of the instrument the dewar will be adjusted within its mount Note that direct visual inspection of the secondary is not possible from the C cabin as it is from the tertiary cabin at the HHT A Goretex diffuser in the way Thus laser alignment onto the secondary is not practical Therefore we must do a very methodical radio beam alignment within the C cabin using warm eccosorb loads against the cold sky at zenith At the end of initial testing of alignment within the C cabin verification at the secondary should be undertaken if possible using the facility cherry pic
39. ndary Issues with transformed power for compressors e g compressors won t stay on Software issues in the many APEX and Supercam interfaces data flow Supercam pipeline not getting headers or tracker pointing SuperComm not following the APEX observing sequence correctly data archiving or transfer problems 7 ON SKY COMMISSIONING TESTS AND QA These sections are tersely written in the expectation that they will be completed by the time of the Readiness Review At the moment we have neither experience with the APECS system nor the typical observing software that is available for instrument checkout to complete this section Here I assume the basic integration that one would assume for any telescope Page 24 of 33 7 1 7 2 Supercam at APEX Implementation Plan PERSONNEL ON SITE 27 November Brian Brandon Paul Craig early Ruben Jenna Bill remote 28 29 November Brian Brandon Paul Jenna Bill remote on 28 enroute on 29th POINT AND FOCUS 7 2 1 Single Pixel through APEX Backend Self explanatory if the Supercam fiducial pixel is used with a facility FFTS Pointing and focus can then be carried out using facility software using the fiducial Supercam beam Normally we use both line and continuum sources for pointing and continuum sources for focus We understand that at APEX it 1 typical to rely on line sources most This is OK We do need access to at least one planet to assess beam efficiencies though spectra
40. ought and sysgen d New remote interfaces enabled New biasServer and midlevel scripts Install and understand APECS simulator Prepare design for apex2hhtf and interface for RA DEC stream for scooper Prepare test scripts for CORBA SCPI handling Data management Write level 2 pipeline using rewritten gridzilla Test with 2014 HHT data September Mechanical and Optical interfaces manufactured and assembly begins Cryostat All cryogenic reworking completed this month Mixers reinstalled Electrical Full system operating from 230VAC or established 115 VAC strip new server racks assembled and tested for deployment C amp C apex2hht development and testing with APECS simulator GUI and mid level script development Replace supercam9 s HDDs with SSDs Data management Continue work on gridzilla Export data via scooper to apexOnlineFitsWriter Can this be adequately developed and tested October Development FREEZE by 15 October Full system testing follows Readiness review and documentation of shipping system around 17 October All deploying personnel must be able to go into the lab and bring up Supercam to a fully operating state by themselves Deconstruction and packing starts 20 October Shipping no later than 24 27 October by air Continued software development with the APECS simulator after instrument ships November Continued software development Instrument is en route and deployment team arrives 15
41. ropriate hints that the needed calibrations for beam switching position switching and OTF mapping are being performed so that level 1 processing can automatically happen POSITION SWITCHING List any assumptions for position switched data for Supercam s pipeline not already in ICD ON THE FLY MAPPING List assumptions for OTF data for Supercam s pipeline not already shown in ICD SUMMARY SCHEDULE 26 27 November Basic commissioning point amp focus runs 27 28 November Beginning of main observing program 8 MAIN OBSERVING PROGRAM DATA FLOW QA 8 1 8 2 8 3 8 4 To complete this section the Supercam team needs Description of all awarded observing time programs and their requirements Understanding of how the time may be scheduled PERSONNEL ON SITE 30 November 8 December Brandon Jenna Bill Caleb and Umut arriving Paul and Brian leaving 8 December 13 December Brandon Bill Caleb Umut 14 December 20 December Brandon Caleb Umut Jorge OBSERVING PROGRAM SUMMARY Titles and short descriptions of all awarded observing programs and their relative priority goes here SERVICE MODE OBSERVING The observations will be performed by the Chilean ESO and Swedish cognizant observers in collaboration with the Supercam team to reduce the data in real time so that assessment of the data can be done effectively SCHEDULING PHILOSOPHY The scheduled time will be allocated by the individua
42. rovided by the existing onboard TS 7200 macrocontrollers or at the point of use with an add on Arduino 2 6 2 Software Switch over to the new version of BiasServer It has many new features that should make Brandon s mid level scripts much simpler and faster The goal is to reduce the amount of intermediate Perl Python code and the volume of network socket server calls to the hardware This will speed up receiver tuning and enable new features below A number of software interfaces need to be written The first set are for general tuning use and laboratory work A proper interface to quickly optimize the setpoints for the electromagnets is urgently needed This interface logic could be quite straightforward since access to the I V data and total power is available A second would be to assess and optimize the stability of the LNA settings A simple graphical interface to call the requisite mid level scripts and view the state of the instrument would be welcome This GUI could nominally run on supercam9 viewed remotely A remote web page to unobtrusively monitor the state of the instrument in North America would be desirable also To perform this the instrument state would be synchronized with a computer in the North e g soral to provide a view of the instrument without direct access to supercam9 The second set of interfaces involves APEX command and control As shown in Figure 7 1 of the APEX Supercam ICD the apex2hht module is require
43. s eei eie deett tace etse ode raten ea vs 15 4 5 Shipping Details Schedule and Responsibilities sse 15 5 ON SITE STAGING AND TESTING BEFORE INSTALLATION eere e eere eene 16 Personnel on eee at e eset Pe ORAE 16 22 5 of FA CULV IIE bee arte nde 16 Schedule OF ues tastes p cd umi Besides rend cM di 16 5 4 Facility Requirements for Sta Gig eerte ert eet eden 19 5 5 Instrument Checkout Procedure in the APEX Laboratory sese 19 5 6 Assembly and Integration State Before Entering C Cabin esses 19 5 7 Risk Assessment and Troubleshooting sue int 19 6 INSTALLATION INTO THE C CABIN AND EARLY COMMISSIONING 20 6 1 Overyiew of oco rer e Xe sas DIA DRE 20 6 2 Personnel Onde i oeste torti ud Meg Ea Rae 20 6 3 Sun Avoidance Consttamis isset rd ob ROGO QU cuba NO MINER ERE Tae EROR neta canta RN 20 Page 2 of 33 Supercam at APEX Implementation Plan GAA Schedule GF AGE VIDES 20 6 5 Risk assessment and n 24 7 ON SKY COMMISSIONING TESTS AND QA eese eene eene teen eene ense en esten e et ene setas sena 24 T Persone C nos eU occisi aec coU In he dete 25 TA Pointand POGUS dau sa eee
44. s stack in the 180 rack by the C cabin door and IF rack adjacent to the cryostat A list of items in the electronics rack and its compatibility with APEX is shown below in Table 2 2 Of these items the most significant effort and expenditure 1 the power supply for the bias electronics cards and preamps three linear supplies in the bias card power supply box are incompatible with 230 VAC The most straightforward solution is to replace the three gold bricks with their exact 230 VAC counterparts and reinstall Finally the RF interfaces for the 10 MHz reference and DC interfaces for synchronization need to identified and suitable SMA BNC coaxial cables fabricated labeled and set aside for testing and shipment Page 9 of 33 Supercam at APEX Implementation Plan Item Compatible w Mitigation plan 230VAC 50 Hz CTI cold head controller Run from unswitched non UPS 115V circuit assume 50 Hz ok Bias cards amp preamp Precede with 2 kW transformer for 115VAC IF processors Omnisys FFTS 1U acquisition PC 16 port Ethernet switch Fiducial pixel amp Run from 12V IF processor supply Edwards vacuum gauge Bring out power on BNC from IF processor VDI LO power supply Run from 115V circuit standalone transformer Rack cooling fans Run from unswitched non UPS 115V circuit IF processor cooling fans 12VDC Run from power brick to 230VAC or 115
45. tep the telescope can still be slewed in elevation Hence each step represents a stopping point for operations which can spill into the 23 1 Install wooden Protection Table and bolt to floor Can be done by anyone on the team 2 Install octopod members onto invar ring removing one M12 bolt at a time and installing the Supercam M12 bolts and octopod members in turn Paul and or Ruben should be present 3 Install cross member rod and chain hoist Hoist secondary mounting ring into position and clamp into place Mark holes for octopod and match drill while in place Install bolts washers and nuts This step requires the core mechanical team Brian Paul and Ruben At the conclusion of work efforts on the 22 the telescope can still observe after the team departs 23 November Mechanical Install Day 2 Supercam is installed Personnel Brian Brandon Paul Ruben Craig Jenna Activities Leftover infrastructure items will have highest priority and then all work will then focus on the C cabin If we are ahead of schedule we may start solidly in the C cabin If so and because a limited number of people can work in the C cabin today may well be a day where we divide the Supercam team into shifts and go for around the clock coverage Shift 1 2 30 PM local to midnight Brian Paul and Ruben start the first shift with the aim of installing the Supercam mount and having the dewar in place Picking up from the 22
46. the remainder of the mount must be installed Page 21 of 33 Supercam at APEX Implementation Plan 1 Install quadrupod vertical support structures into place minus one 2 Transfer Supercam cryostat into position if it is not already in position e Cryostat will be staged on the hydraulic cart inside the instrument laboratory and then rolled to the door The air ride cart waits outside The hydraulic cart is positioned for transfer of cryostat to air ride cart at the door The hydraulic cart then runs ahead of the cryostat and is hoisted to the instrument level in advance of the instrument transfer Air ride cart is transferred with cryostat across parking lot to crane transfer area e Cryostat is craned to instrument level where it will be lowered onto the orange hydraulic cart The orange cart with cryostat can then be transferred into the C cabin 3 Transfer cryostat onto M3 protection table 4 Hoist cryostat into position and fasten into place with 1 2 bolts 5 Install fourth vertical support leg Now might be a good time to move the telescope and validate the mount Drive back to Sequitor and inform shift 2 Shift 2 midnight to 9 30 AM local Brandon Jenna and Craig work to complete any remaining items from shift 71 that are not too specialized Then even if the cryostat is not yet installed they will 1 Hoist Electronics rack and IF system onto instrument platform Roll support electronics rack s in
47. to room and bolt to floor and M3 Protection Table respectively 2 Verify safety of system under telescope motion Ensure that DC electronics rack is internally wired and attached to 8 channel dummy dewar building power and ethernet 4 Power on DC electronics rack and validate basic operation on dummy dewar Zero biases and install all cabling very carefully to cryostat if available IF coaxes first then DC cables 24 November Install day 3 Final installations validation pumpout cooldown Personnel Brian Brandon Paul Ruben Craig Jenna Activities Again a double shift may be the desired mode of operation today Shift 1 2 30 PM local to midnight Brian Paul and Ruben start the first shift with the aim of a completed Supercam system If they have not completed their tasks from the 23 they will do so here And then they will 1 Bring in the facility vacuum system and pump on the dewar 2 Install LO module and beamsplitter module Page 22 of 33 Supercam at APEX Implementation Plan Install Calibration wheel and stepper motor plus wiring harness Install Lens 1 at secondary mounting ring Install helium lines and cold head controllers ipe ce Briefly turn on both compressors and cold heads to ensure that they work if not done on the 22 Shift 2 midnight to 9 30 AM local Brandon Jenna and Craig work to complete any remaining items they they were not able to finish from th
48. ugh the closeout of the observing season and de installation will occur in the first week of January An estimated 2 3 days on site are recommended for the removal of all items from the C cabin An additional 1 2 days will be required to remove all Supercam components from the telescope Once removed from the telescope 2 days are required to Page 27 of 33 Supercam at APEX Implementation Plan pack the instrument Heavier items such as compressors and cryostat will need to be craned into their respective containers A total of 5 days is requested from January 5 to January 10 inclusive The de installation procedure is identically the reverse order of the installation procedure and all lessons learned during the actual operation of the former will be used to guide the latter The same Supercam team will be involved in the mechanical deinstallation as well Page 28 of 33 Supercam at APEX Implementation Plan Appendix A Approval The undersigned acknowledge they have reviewed this document and agree with the approach it presents Changes will be coordinated with and approved by the undersigned or their designated representatives Signature Date Print Name Title Role Signature Date Print Name Title Role Signature Date Print Name Title Role Page 29 of 33 Insert appropriate disclaimer s Insert the name version number description and physical location of any
49. uter has two spinning 2 TB hard disks These must be replaced with solid state drives and the system re imaged and re installed Page 10 of 33 Supercam at APEX Implementation Plan Room must be made to restore the system onto the smaller SSDs I recommend two 600 GB Intel SD3500 drives which we can also use for the GUSSTO flight system qualification once Supercam is done at APEX A few cabling issues need to be sorted out The Microlambda synthesizer cable connection is dodgy and needs to be repaired While undergoing surgery we need to add the 5 line for DATA OUT so that all of the synthesizer diagnostics can be monitored Remote sensing augmentation We need to add a number of AD590 or comparable temperature monitors to one or more IF processors the Spacek amp on the VDI LO and other temperature sensitive items This requires a 12V interface to each sensor and an analog return to an ADC This can be provided by one or more TS 7200 macrocontollers on the bias cards or by a USB connected standalone microcontroller such as an Arduino This could absorb the Microlambda communication as well See Figure 2 2 for clarification Microlambda AD590 MLSN 10 12 GHz synth temperature sensors oon 12 VDC sen sclk sdi sdo busy lock analog outputs Figure 2 4 Additional remote sensing information and augmentation of digital I O DIO for monitoring of the Microlambda synthesizer The ADC and DIO functionality could be p
Download Pdf Manuals
Related Search
Related Contents
Delta 76261-BN Installation Guide Owner`s Guide - Free PDF hosting, PDF file sharing and PDF 730-0439 - The Grill Services Corporation Configuring and Troubleshooting Identity and Access Hoover Domestic Appliance User Manual 取扱説明書 鞄用セキュリティベルト(重量測定機能付き) MedCork - Manual do Utilizador v1.2.1 Elegante brief Copyright © All rights reserved.
Failed to retrieve file