Home

AT697F Summary Report - ESA Microelectronics Section

image

Contents

1. cache ON shows the performance of the FPU of the processor compare to the software FPU The result of this test is 2 9 Paranoia second with software FPU The result of this test is 75 8 Paranoia second with hardware FPU The ratio between the hardware FPU and the software FPU is around 26 All regfile with and without EDAC protection Instruction and data caches interrupts and trap memories ROM SRAM and SDRAM UART tests have passed successfully The PCI validation has been done by Atmel and not any more by Ayrton as for AT697E PCI validation subcontractor Atmel does have all necessary software and hardware to perform the tests Power consumption was monitored and characterized under different application and at different CPU clock frequencies Performance Summery at 100MHz SRAM with 2 wait states 85 MIPs Dhrystone 2 1 76DMIPS Whetstone Double precision 22 3 MWIPS 7 MFLOPS Whetstone Single precision 27 4 MWIPS 10 2 MFLOPS Functional Validation Summary BUGI Odd numbered FPU register dependency known since tape out No new bug found by validation The Applicative validation report 34 has been sent to agencies end of March 2012 AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 24 AMEL T O G 5 4 WP 8 Contractor Internal Space Qualification The main activity of this work package was to define and perform the qualification tests Characterization electrical test Probe test Assembly Final test E
2. Value Max value Unit ICCSB_Array Max 5 0 993 0 103 0 858 1 12 mA ICCSB_ Buffer Max 5 1 18 0 873 1 04 1 27 mA The maximum value measured is less than 1 5mA for both Array and Buffer for a specification at 5mA The AC characterisation tests have been performed on the two different packages and with Natural and Maximum Skew The dynamic parameters are in line with the Static Timing Analysis for a typical lot Only a very small number of minor deviations were noticed All the values have been updated in the datasheet 35 The final electrical characterisation report 32 has been sent to agencies end of November 2010 In conclusion static and dynamic parameters measured on the chip are in line with the data sheet 5 3 2 2 Application validation For the validation a logic analyzer was used to acquire the chronograms and clock for the AT697F processor was injected by a generator with 3 3 V of amplitude and variable frequency The DSU interface was used to program the AT697F processor All internal modules have been tested with different test benches and configurations The bypass configuration switch was used for tests to frequency up to 80 MHz and for higher frequencies the internal PLL was used For example the FPU module was tested with specific benchmarks paranoia linpack and whetstone with different configurations at different frequencies A test performed at 40 MHz with the software option MSFLOAT WS3
3. 2010 at HIF UCL Heavy Ion Campaign on 20 of November 2010 at HIF UCL Protons Campaign on 29 of September 2010 at LIF UCL These three SEE test campaigns have allowed to assess the Single Event Upsets Single Event Transients sensitivity for the AT697F and to check the protection against Single Event Latchup The set of functional patterns were enhanced to check the occurrence of SEFIs Tests were composed of Static tests memory elements are exhaustively SEU tested Registers Caches DFF protected or not Dynamic tests The results of computation subject to SEUs in memory elements and SET in the logical elements with or without mitigation schemes are assessed The SEL test has been performed at a temperature of 125 C at maximum voltage and for a LET of 62 MeV mg cm there is no Single Event Latchup for AT697F for a fluence of 2 10 particles cm The Latchup cross section can be estimated to be lower than 5 10 cn The SEU tests show that the RHBD techniques applied in AT697F such as EDAC parity Triple Modular Redundancy TMR are working correctly Only few MBU have been observed at high LET The SEU low sensitivity is enhanced with good practises like cache occupancy management During all the tests no functional disruption has been found AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 26 AMEL y O E The SET tests show that the TMR technique and the clock skew mechanism allow a very good filt
4. 4 includes the following work packages WP 5 Detailed Test Plans WP 6 Manufacturing and Assembly of Engineering Devices WP 7 Electrical Characterisation and Validation WP 8 Contractor Internal Space Qualification WP 9 Radiation Characterisation Performed under CNES contract WPIO Evaluation Performed under CNES contract The details of these work packages can be found in 46 and in 47 AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 7 AMEL r O a 2 1 Reference documents The following documents can be found on the Data Package CD PHASE 3 1 WPI Technology Readiness Assessment Report Rev 2 0 ADF PL R0925 MLN 29 01 2008 2 AT697E design report V3 0 ADF DE R0786 ATA 12 08 2005 3 A T697F Specification V2 0 ADF PL R0927 MLN 31 08 2007 4 AT697E Development plan V1 1 ADF PL R0928 MLN 31 08 2007 5 Specification for the modification of the LEON2 FT VHDL model for the AT697F 10 10 2006 ES A TEC EDD 2006 74 ALRP issue rev 1 6 PCI interface improvements fixes to be implemented for AT697F flight model design ESA TEC EDM 001 05 RW Issue 3 11 12 2006 7 Report on the design issues reviewed during Roland Weigand visit in Nantes the 13th and 14th of December 2007 NR MLN_VRW_071214 14 12 2007 8 LEON2FT modifications for the AT697F Rev 1 2 Gaisler Research 14 02 2007 9 The LEON2 FT processor user s manual version 1 0
5. 7 01 NL FM and CNES Contract n 721 00 CNES 8286 00 Lot2 The overall development plan for the LEON2 FT has been divided in five phases see timeline Figure 1 in chapter 1 Phase 0 Preparatory work Phase 1 Validation of the LEON1 FT demonstrator Phase 2 Development of the LEON2 FT AT697E prototype After the completion of the first 2 Phases ATMEL has developed during the phase 2 a LEON2 FT AT697E prototype on 0 18 um CMOS technology to validate the design concept of fault tolerance to SEE induced error used in LEON2 FT All deliverables have been sent to agencies and are available since March 2006 Phase 3 Design of the AT697F flight device on the ATMEL rad hard CMOS 0 18 um Phase 4 Manufacturing Characterisation and Qualification of the AT697F flight device This summary report describes the activities and the results of phase 3 and 4 covering the period from March 2006 to the completion of the technical works in June 2012 all deliverables are available in July 2012 Both Phases are covered by the ESA Contract 19083 05 NL FM Call off order 002 Phase 3 Design of the AT697 Flight device also named AT697F The Phase 3 activities are split in 4 different work packages WPI Technology Readiness Assessment WP2 Preparation of the Qualification and the Industrialisation WP3 Specification and Development Plan WP4 Design Phase 4 Manufacturing Characterisation and Qualification of the AT697 flight device The Phase
6. 7E The AT697F processor has been made available to the European space community since 2011 The Design phase has been performed from March 2007 to May 2008 Following the ESA authorisation to proceed the manufacturing of the reticules has been launched in June 2008 engineering model packaged in MCGA and MQPF was made available for validation in October 2008 The validation characterisation and radiation tests have been performed from January 2009 to March 2012 and the results are very positive The AT697F is fully functional only the bugs known at the end the design phase are present The performance of the processor reaches the specification for a power consumption as low as 7 mW MHz The AT697F fully works over the whole bias and military temperature ranges The AT697F has been tested successfully up to a total dose of 300 Krad Si The AT697F is a SEU SET hardened processor The hardware TMR technique is very effective against SEU in the internal sequential logic and SET in the combinational logic network even at 100 MHz PLL enabled and with a natural Skew There are very few errors that escape mitigation by this technique There are not enough events to be able to evaluate the influence of the maximum Skew on the error rate There is no Single Event Latchup SEL at 125 C for a LET of 62 MeV mg cm2 with maximum voltage levels on core 1 95V and I Os 3 6V These TID and SEE test results have confirmed the high to
7. 9 16 1 Gaisler Research 15 03 2007 10 AT697F timing databook Rev 1 1 ADF DE R0603 MLN 30 04 08 11 AT697F SRAM timing analysis Rev 2 0 ADF DE R0600 MLN 31 03 08 12 AT697F SDRAM timing analysis Rev 2 0 ADF DE R0601 MLN 31 03 08 13 AT697F clock skew amp hold fixing analysis Rev 2 0 ADF DE R0604 MLN 31 03 08 14 AT697F Design flow Rev 1 1 03 06 2008 15 AT697F Testability approach Rev 0 1 20 05 2008 16 Meeting Report of R Weigand visit the 15 05 08 MLN VRW 080519 V11 20 05 2008 AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 8 AMEL T OO Se PHASE 4 17 D13 AT697F DesignReviewDocument v2 1 2008 06 06 ADF DE R0612 MLN V2 1 18 D14 AT697F DesignReport v2 0 2008 07 03 ADF DE R0611 MLN V2 0 19 DI15 AT697F TimingDatabook v1 1 2008 04 30 ADF DE R0603 MLN V 1 1 20 D16 AT697F SRAMTimingAnalysis v2 0 2008 03 3 1 ADF DE R0600 MLN V2 0 21 D16 AT697F SDRAMTimingAnalysis v2 0 2008 03 31 ADF DE R0601 MLN V2 0 22 D16 AT697F PCITimingAnalysis V 1 0 2008 03 03 ADF DE R0602 MLN V1 0 23 D16 AT697F SkewAndHoldAnalysis V 1 0 2008 03 31 ADF DE R0604 MLN V1 0 24 D17 AT697F PreliminaryDatasheet revC 2009 06 30 7703C AERO 25 D18 AT697F ElectricalCharacterisationTestPlan V2 0 2010 11 24 ADF PE R0821 MLN V2 0 26 D19 AT697F ValidationTestPlan v1 1 2010 12 10 ADF DE R0940 MLN V1 1 27 D20 AT697F ContractorInternalS
8. AMEL AT697F LEON2FT FM SPARC V8 space processor Summary Report Version 3 0 08 08 2012 Reference ADF MK R1011 MLN ESA Contract 19083 05 NL FM Call off order 002 CNES contract 721 00 8386 02 PROPRIETARY INFORMATION ALL INFORMATION DISCLOSED IN THIS DOCUMENT ARE CONFIDENTIAL AND FOR INTERNAL USE ONLY Atmel Nantes S A La Chantrerie BP 70602 44306 Nantes Cedex 03 France Tel 33 0 2 40 18 18 18 Fax 33 0 2 40 18 19 20 http www atmel com AMEL Sy Oo a Page left intentionally blank AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 2 AMEL E E 1 Abstract This document presents a summary of the activities performed and of the results obtained during the LEON2 FT Flight model development This LEON2 FT Flight model has been made available by ATMEL with the product name AT697F After the development of the AT697E LEON2 FT prototype processor under the ESA contract 15036 01 NL FM a new design phase for the AT697 flight model started under the ESA Contract 19083 05 NL FM Call off order 002 and the CNES contract 721 00 8386 02 started in July 2006 After a design phase of more than 2 years the design was released to fab in 2008 tape to fab The first silicon of AT697F LEON2 FT FM processor was available for the beta tester and for European Space community early 2009 After the characterisation and the radiation testing performed from 2009 to 2010 followed by the functional v
9. F DesignReport v2 0 2008 07 03 ADF DE R0611 MLN V2 0 D15 AT697F TimingDatabook v1 1 2008 04 30 ADF DE R0603 MLN V1 1 D16 AT697F SRAMTimingAnalysis v2 0 2008 03 31 ADF DE R0600 MLN V2 0 D16 AT697F SDRAMTimingAnalysis v2 0 2008 03 31 ADF DE R0601 MLN V2 0 D16 AT697F PCITimingAnalysis V 1 0 2008 03 03 ADF DE R0602 MLN V1 0 D16 AT697F SkewAndHoldAnalysis V 1 0 2008 03 31 ADF DE R0604 MLN V1 0 Customer oriented documents D17 AT697F Preliminary Datasheet revC 2009 06 30 7703C AERO D26 AT697F UpdatedDataSheet RevE 201 1 08 04 7703E AERO Preliminary SMD Specification 5962 07224 Rev C AT697F erratasheet draft2 AT697F Total ionizing Dose test report mtr110407 L2 6 AT697F ESCCSpecification V 1 1 2011 10 24 ESCC Spec No 9512 Validation and Characterisation related documents D18 AT697F HlectricalCharacterisationTestPlan V2 0 2010 11 24 ADF PE R0821 MLN V2 0 D19 AT697F ValidationTestPlan v1 1 2010 12 10 ADF DE R0940 MLN V1 1 D20 AT697F ContractorInternalSpaceQualificationTestPlan v1 1 2010 11 30 ADF PE R0822 MLN D22 AT697F EvaluationTestPlan v1 2 2010 10 22 ADF PL R0972 MLN V1 2 D23 AT697F ValidationTestBoard v1 4 2011 10 24 7740D AERO V1 4 D24a AT697F ElectricalCharacterisationTestReport v5 1 2010 11 25 ADF PE R0834 MLN V5 1 D24b AT697F T14 T17 Report v2 1 2010 11 25 ADF PE R0840 MIL V2 1 D25 AT697F ValidationTestReport v 1 2 2012 03 29 ADF DE R0941 MLN V1 2 Radiation related
10. IEW MEM NEUE CN npe 25 20 0 976 o 992 Di E1 22 8661 27x18 0 900 05x18 Ta 20 soo 6 222 Pe on os ox o0 rep are Lid connected to ground Figure 3 MCGA349 Mechanical Outline AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 12 AMEL 3 4 AT697F MQFP 256 package 256 LEAD MGFP F IM Pero em os 015 os o 010 014 362 Figure 4 MQFP256 Mechanical Outline AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 13 AMEL ay O ET 4 Phase 3 4 1 WPI Technology Readiness Assessment The objective of the WP1 was to demonstrate that the targeted technologies process library package and assembly the design technologies and tools the SEE hardening were suitable for the design manufacturing assembly verification and qualification of the flight version of the AT697 The preparation of the SEE test campaign was finalized in 2006W41 but technical problems with the UCL Louvain heavy ions beam prevented from doing the SEE test in W43 as expected The heavy ions test was finally done on the 10 of November 2006 at 23h first available slot proposed by UCL to ATMEL This SEE test was performed successfully The AT697E parts have been produced on two types of raw wafers similarly to what has been done during the evaluation of the AT58KRHA technology capability With AT697E parts produced with the raw wafers that are used for the ATCISRHA ASIC offer in
11. MEL and ESA With the support of ESA for the debugging of the simulations it has been possible to pass successfully all the simulations both at RTL level and on gate level netlist As planned the testability insertion jtag scan bist has been performed successfully A new netlist including the testability features the pll the structures for the clock tree and the skew insertion has been available in 2007w24 Simulations for the testability part have been added Functional and testability simulations have been successfully passed with no timing check on this new netlist in 2007w26 A document summarizing the status of the available netlists and the simulations passed on them has been provided to ESA ATMEL has passed formality checks the gate level netlists in August 2007 ATMEL has decided to include the spare cells in the gate level netlists as it was done for the LEON2 FT prototype During the 4 of July teleconference it has been agreed with ESA to start layout activities corresponding to WP4 2 on the last available netlist in order to get a first estimation of the performance of the circuit After several iterations the floorplan from AT697E was reused however as illustrated in Figure 7 the square shaped confinement blocking constraints for the standard cell area with a new generation of CAD tools were not necessary any more AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 15 AMEL SCC A complete Static Tim
12. alidation the evaluation and qualification performed in 2011 the first flight model was delivered to customer end of 2011 It is a first pass yield meaning no redesign has been necessary The AT697F is fully functional only one bug found at the very late stage of the design remains it was commonly agreed not to delay the design phase The AT697F fully works over the whole bias and military temperature ranges The AT697F has been tested successfully up to a total dose of 300 Krad Si The AT697F is a SEU SET hardened processor the error rate in space for the GEO orbit worst case has been calculated at one no correctable error for more than 100 years the Single Event Latch up tests at 70 MeV mg cn have been performed on other test vehicle in the same manufacturing process ATS58KRHA therefore only a test at 60 MeV mg cm2 at 125 C has been performed on AT697F The main milestones are shown in the timeline below 1998 I 1999 I 2000 I 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 AT697E 15 Feb 30 Oct Design work 10 Dec Functional Evaluation Design into Feb 2 Nov contract Kick off ATP phase 2 Updates of Tape out amp Radiation Alpha PROBA 2 ERNO box Launch of 15036 Phase 1 AT697E LEON2FT AT697E Testing Users amp ERNO box launch to ISS Proba 2 AT697F Design work 6 June Validation 25 April contract 4 July Updates of Tape out Test amp characterisation Eval
13. ality Some additional patterns have been added by ATMEL to improve the validation such as new test benches to test the Debug Support Unit DSU stuck at faults and transition delay faults TDF Memory BIST JTAG PLL SRAM interface to improve the timings characterization The AT697F characterisation has been performed on the military temperature range 55 C 125 C and for the whole bias range 1 65V 1 95V for the core 3V 3 6V for I Os The static parameters current consumptions input leakages output currents and dynamic parameters setup hold output delay have been measured in the above conditions 5 3 1 2 Application validation The validation report 34 presents the detailed activities and results obtained during the characterisation of the AT697F Manpower restrictions have added delay to work package 5 3 2 Main results 5 3 2 1 Electrical characterisation The AT697F characterisation done in both package MCGA and MQFP has been performed successfully in accordance with the characterisation test plan 25 The 10 MCGA349 amp 2 MQFPF 256 package parts tested are fully functional in the whole bias and temperature range 55 C 125 C Static parameters are in line with the datasheet for example the following table gives the standby Array and Buffer Current consumption AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 23 AMEL Sy O NNNM PARAM Type Spec Average Sigma Min
14. bilities with EDAC e Operating Range Voltages 3 3V 0 3V for I O 1 8V 0 15V for Core Temperature 55 C to 125 C e Clock 0 MHz up to 100 MHz e Power consumption less than 1W at 100 MHz e Performance at 100MHz SRAM with 2 wait states 85 MIPs Dhrystone 2 1 76DMIPS Whetstone Double precision 22 3 MWIPS 7 MFLOPS Whetstone Single precision 27 4 MWIPS 10 2 MFLOPS e Radiation performance Tested up to a total dose of 300 Krad Si according to the MIL STD883 method 1019 SEU error rate better than 1 E 5 error device day GEO Orbit AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 10 AMEL No Single Event Latch Up below a LET threshold of 70 MeV mg cm2 e Package LGA349 MCGA349 and MQFP256 e Development Kit including AT697 evaluation board AT697 sample 3 2 AT697F block diagram l Cache D D Cache p Figure 2 AT697F block diagram AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 11 ATMEL 3 3 AT697F MCGA 349 package MCGA 349 19 x 19 Pitch 1 287mm BOTTOM VIEW OOOOOOOOOOOOOO OOOOOOOOOOOOOOO OOOOOOOOOOOOOOO OOOOOOOOOOOOOO OOOOOOOOOOOOOO OOOOOOOOOOOOOO OOOOOOOOOOOOOO OOOOOOOOOOOOOO OOOOOOOOOOOO OOOOOOOOOOOO OOOOOOOOOOOCO OOOOOOOOOOOOOO OOOOOOOOOOOOOOO OOOOOOOOOOOOOOOOO OOOOOOOOOOOOOOO O O O O O O o O O O O O O O O O O O OOOOOOOOOOOOOOO OOOOOOODOOOOOOO uwoummztoTdmzrumxsr xzum m Accex TOP V
15. delivered to ATMEL by ESA the 14 of February 2007 A final version of the LEON2 FT model has been delivered by ESA the 17 of March 2007 A SDRAM improvement analysis document was delivered by ATMEL to ESA the 18 of June 2007 This document was commented by ESA the 20 of June 2007 A first version of the AT697F specification has been delivered to ESA the 7 of August 2007 together with a draft of the AT697F preliminary datasheet and erratasheet The second version of the AT697F specification and the version 1 1 of the AT697F development plan have been delivered to ESA the 31 of January 2008 following the ESA comments received in November 2007 A final update of these documents has been sent to ESA the 4 of February 2008 ESA has confirmed the 13 of March 2008 that these two documents are accepted 4 4 WP4 Design The two mains objective of the WP4 was to make the detailed design and the layout of the AT697F microprocessor taking into account the lessons learned with the AT697E prototype The design report 18 D14 AT697F DesignReport v2 0 2008 07 03 ADF DE R0611 MLN V2 0 gives details of the activities performed during the design phase and of the main problems met This section gives an overview of the overall tasks and schedule associated with this design phase After the delivery of the final LEON2 FT model by ESA synthesis trials and preliminary layouts have been performed with this final model with regular exchanges between AT
16. documents D21a AT697F TotalDoseTestPlan v 1 0 2008 09 26 ADF PL R0970 MLN V1 0 D21b AT697F SEETestDocuments v1 2 2010 12 09 ADF PL R1007 MLN V1 2 L1 2a AT697F TotalDoseTestReport v2 0 2009 11 16 ADF PE R0835 MLN V2 0 L1 2b AT697F SEETestReport v2 2 201 1 12 06 ADF PE R0842 MLN V2 2 L2 1 AT697F SEETestProgramSoftware v1 0 2010 12 16 zip Qualification related documents L2 2 CNES Precap Report 885247P 2 07 10 09 L2 3 CNES Hlectrical Acceptance L2 5 AT697F EvaluationReport v1 4 2012 03 07 ADF PE R1001 MLN rev1 4 L2 6 AT697F ESCCSpecification V 1 1 2011 10 24 ESCC Spec No 9512 L2 7 Process identification document PID PID0030 Rev B AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 29 AMEL SC Photographic documents have been delivered to ESA These photographic documents are Also included in the CD Picture of the AT697F packaged part MCGA and MQFP Picture of the AT697F packaged part without the cover Picture of the ATMEL AT697F evaluation board in the document Picture of the ATMEL AT697F mezzanine MCGA Board with IronWood socket AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 30 AMEL Sy OO a 7 Conclusion The flight version of the LEON2 FT processor AT697F benefit from the experience gained during the development of the LEON2 FT prototype AT697E The AT697F is based on the ATC18RHA library and correct all the bugs that were identified on the AT69
17. ecification and Development Plan The objective of the WP3 was to consolidate the specification of the AT697 and to provide the development plan ATMEL has received the 10 10 2006 from ESA a document presenting the specification of the modifications to be implemented on the LEON2 FT VHDL Model for the AT697F The preparation of this document was performed in close collaboration between ATMEL and ESA taking into consideration the feedback given by beta users of the AT697E AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 14 AMEL r O ae A very preliminary version of the new model leon2ft_r67 has been received by ATMEL the 27 10 2006 ATMEL has performed an analysis of this new model and first simulations with feedbacks to ESA The LEON2 FT 1 0 9 16 model has been received by ATMEL the 14 12 2006 included in a CD ROM Following some customer feedbacks ATMEL has proposed to ESA a modification of the LEON2 FT model to improve the 8 bit PROM boot when EDAC is activated A presentation has been made and sent to ESA the 19 of December 2006 Various exchanges between ESA and ATMEL have been made on the implementation of the 8 bit PROM boot with EDAC On the 7 of February 2007 ESA has notified ATMEL of its final choices which will be implemented in the new version of the LEON2 FT model The description of the modifications performed in the new version 1 0 9 16 1 of the LEON2 FT VHDL model and the associated user manual have been
18. ering of the SET in the combinational and sequential logic The proton test shows a very low sensitivity to energy of 63MeV A good correlation has been established between the SEU test results obtained on the ATCISRHA 0 18u m family and the ones obtained on AT697F The efficiency of the AT697F SEU and SET protections has been confirmed The influence of the skew and frequency has been assessed confirming that the maximum skew achieves a significant protection improvement against SEU and SET During all the SEU runs that have been performed during these test campaigns only a few residual uncorrectable errors have been detected The associated error rate in geostationary orbit has been determined to be better than 1 E 5 error device day and it can be concluded that the AT697F for space applications is a SEU SET hardened processor 5 5 3 Lessons learnt The first main board was inspected without any component in order to verify all the power lines at that time it has been observed that the board was twisting and could not be used for the components assembly The internal layer metal was incorrectly well balanced A new internal metal has been done and sent to the subcontractor in order to make a new main board The new main board fully assembled and the two mezzanines released were fully operational We have observed that the connector was not the expected one due to a mistake in the bill of material therefore the heat equipment could not be pr
19. ing Analysis has been performed and the timings reached for the various interfaces of the product have been studied Summaries of the results have been sent to ESA by mail the 16 of November 2007 for the CPU the SRAM the SDRAM and the PCI interface with an addition a study of the influence of the 50 pF load The four timing analysis have been presented by ATMEL during the teleconference of the 23 of November 2007 and the potential improvements have been discussed with ESA in particular for the SDRAM The problem of excessive buffer insertion during hold fix caused by the skew between the three clock trees which is deliberately created for SET protection was of particular attention A study of the impact of decreasing the value of the skew between the clocks on the SEE protection has been delivered to ESA the 23 of January concluding that the effect should be minor ATMEL and ESA agreed that the use of a skew of 2 3 of the one used on AT697E and the use of a 100 ps hold margin instead of the 250 ps standard in ATC18RHA is the best compromise in term of speed power consumption SEE protection ATMEL has been informed by ESA of a bug of the LEON2 FT model affecting the AT697F After some e mail exchanges a conference call has been held the 25 of January on that particular matter It has been agreed by ATMEL and ESA not to implement a correction of the model on AT697F as it would impact the planning of 1 5 month the bug being considered as no
20. lectrical characterization ESD Latch up and Reliability tests Die qualification test early failure rate 150 C 3 7v operating life test 150 C 3 7v Static Life Test 140 c Endurance 25 c Data Retention Wafer Level 250 C Data Retention Product Level 150 C and the Package qualification tests The Contractor Internal Space Qualification test Plan 27 has been sent to ESA in November 2010 The main results are presented with the WP10 5 5 WP 9 Radiation Characterisation 5 5 1 Summary of the activities This work package 9 is executed under CNES contract N 721 00 8286 02 The preliminary radiation test plans have been sent according to the work package 5 The documents AT697F total dose test plan 28 has been reviewed by ESA and CNES and has been accepted The Total ionizing dose has been performed from the 18 of November 2008 and the 5 of January 2009 The AT697F total dose test report 38 document has been sent 2009w7 and reviewed by Agencies The TID test last from November 2008 to 2009w2 The document AT697F SEE test plan 29 has been sent to and reviewed by agencies A new heavy ion test platform has been developed to the SEE tests This platform is made of three boards the main board which embeds all useful components to activate the DUT and to perform all tests software Two other boards mezzanine one for each type of package MCGA and MQFP used for heavy ion when attached to the main board and used for protons testing at
21. lerance of this product against radiation effects and its capability to answer to the needs of the space community The feedbacks from the customers that have already used the chip alpha customers early design starters are as well very positive The space community in general shows a very good interest in the AT697F ATMEL would like to thank the following ESA persons that have allowed carrying out this difficult but finally successful design of the AT697F microprocessor Andre L R Pouponnot TEC EDD Technical Officer Roland Weigand TEC EDM for his technical support AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 31
22. lue BIST Yellow JTAG n E Pan Ed EE J t d E d d Legend for ATFG97E PI E IU FPU caches AMBA ADD PCI MEM m DSU IF JTAG JTAG DSU SDRAM IF PCI PCI Req amp gnt PCI Figure 7 AT697F above and AT697E below floorplans AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 19 AMEL EEE 4 4 3 Lessons learnt The design of the AT697F has been performed during 14 months from mid March 2007 to mid May 2008 Even if the experience of the AT697E LEON2 FT prototype was useful and eased some AT697F design tasks a number of difficulties due to the complexity of the design implied a significant delay including Simulation debugging Artificial clock skew implementation External timing improvements The performances obtained at the end of the AT697F design phase are promising and fully in line with the initial objectives of the ESA contract 19083 05 NL FM The AT697F processor clock speed has been maintained at 100 MHz whereas the library maximum temperature is 145 C and not 100 C as it was for AT697E The artificial clock skew implementation and the hold margin have been improved The external interfaces speed has been significantly improved allowing to get a fully 100 MHz processor on SDRAM or SRAM interfaces A good collaboration with ESA has been noted all along the design phase with an important number of design follow up conference calls and two technical support visits of agenc
23. model NO Y FE Y o FE i Y Matrix Floorplan l d Physical Synthesis Placement Driven Scan Chains reordering max fanout violations fix Clock trees synthesis Post CTS optimisation routing SPEF 2 5D C RC extract emulate filling PrimTime Analysis Blocks placement matrix tri Back to FE definition Optimisation bonding 4 management 4 4 A Groups regions Power routing Figure 6 Design Flow i StarRCXT E Y PRIMETime STA DRC OK Ld t YES PRIMETIME Y FORMALITY t MODELSIM CELTIC Y VOLTAGESTORM PATFORM E J omm m CALIBRE Ls ASSURA OPC Lo MASKCOMPOSE Ld Y a GDSII Final SPEF 2 5D C RC extract with Metal filling SDF Generation Equivalence checking formal proof Back annotated simulation comparison Cross talk analysis IRdrop Power distribution analysis Test patterns check and generation GDSII file creation DRC LVS sizings OPC Rousset Frame generation Final Stream file for Mask shop AT697F summary report V3 0 08 08 2012 Page 18 ADF MK R1011 MLN 4 4 Main results The final place and route has given the chip view shown in the Figure 7 below in an 8 6 x 8 6 mm matrix Legend for AT697F Red IU Violet amod Green PCI Orange DSU Dark b
24. n critical Minutes of this conference call have been sent by ESA in a mail dated 25 01 08 An analysis of the impact of hold fixing on the final skew values between clocks has been sent to ESA the 1 of February 2008 This analysis has shown the improvement made in the hold fix correction method compared to the AT697E design phase The hold fixing does not reduce the final skew value between the clocks and thus the SET protection is not reduced by the hold fixing It confirmed that the choice made on the skew value 2 3 of the AT697E one is appropriate Various improvements of the timings on the interfaces SDRAM SRAM PCI have been performed The detailed timing results for the SDRAM SRAM and PCI interface have been sent to ESA the 4 of March 2008 After modifications the SDRAM interface performance was significantly improved For comparison before the optimisations the maximum frequency on the SDRAM interface at natural skew in worst case conditions was 74 MHz compared to 103 MHz after modifications Again for SRAM before the optimisations the maximum frequency on the SRAM interface with natural skew in worst case conditions was 62 MHz with 0 wait state compared to 78 MHz after modifications and 93 MHz with 1 wait state compared to 118 MHz after modifications These figures are based on a pin load of 50ps At higher loads as often observed in applications or with propagation delays on the board the performance might be lower The functio
25. nal simulations on the final netlist have been run successfully the 11 of April 2008 Additional simulations have been added before the Design Review in particular to increase the frequency and to get more data related to the memories and registers initialisation The formal proof has been passed successfully between the different available gate level netlists as well as the Power estimation IR drop and crosstalk tool which gave correct results DRC LVS tries have been performed resulting in minor usual layout modifications It has been decided to perform the clock modification on the register file to improve speed as it was done for AT697E allowing to gain around 2 MHz in term of performance A final static timing analysis has been performed and results sent to ESA the 13 of May 2008 The Design Review was held at ESA the 27 of May 2008 The following presentations were performed during this review ESA introduction including the overall plan and schedule of the Phase 3 ATMEL AT697F product development status including an overview of all the Phase 4 planned AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 16 AMEL Sy O a activities ATMEL AT697F Final Design Review summarizing the results obtained during the design phase with some encountered problems A short summary of the Final Design Review has been sent to ESA the 28 of May 2008 Following the Final Design Review ATMEL has re run some tools and ha
26. nd on Atmel Web site This board is commercialised by ATMEL as a development kit Figure 9 ATMEL AT697F evaluation board with MQFP256 mezzanine TU WW 5 m E zi z wur Figure 10 ATMEL AT697F evaluation board with MCGA349 mezzanine AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 22 AMEL r O a 5 3 WP 7 Electrical Characterisation and Validation 5 3 1 Summary of the activities The validation test plan 26 has been delivered and accepted by the agencies in December 2010 This document presents the validation strategy used by ATMEL to validate the AT697F processor The AT697F validation consists of two validation processes The first one uses industrial test equipment ASIC tester to characterise the processor while the second one uses application laboratory equipment to perform functional validation and benchmarking 5 3 1 1 Electrical characterisation The electrical characterisation report 32 presents the detailed activities and results obtained during the characterisation of the AT697F using the Credence Octet tester The Octet 800 has been used for the characterisation and the debugging and then all the test patterns have been reworked to be ported on an Octet 200 The portability has been more complex than expected which has delayed the overall characterisations Functional test patterns coming from the ESA test benches have been passed on the tester to validate the product function
27. nd substrate attach strength stud pull test Detailed results are reported in the CNES Electrical Acceptance Thermal Tests The purpose of these tests is to evaluate the behavior of the product subject to thermal constraints 10 parts have been tested and no weakness to thermal constraints has been identified Mechanical Tests The purpose of these tests is to evaluate the behavior of the product subject to mechanical constraints 10 parts have been tested and no weakness to mechanical constraints has been identified Endurance tests 1000h Read Out done successfully and internal Atmel qualification done ESCC qualification 3000h and all groups are done A final report has been sent to agency 43 AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 28 AMEL Sy amm 6 Deliverables Fifteen AT697F parts have been delivered to ESA during the Phase 4 WP7 and WP8 from December 2008 to November 2011 An AT697F Validation test board including the Board a MCGA mezzanine with socket and a MQFP mezzanine has been delivered to ESA in November 2010 All the following documents except the customer oriented ones written by ATMEL are ATMEL Proprietary and as such confidential These documents are included in the final CD ROM delivered to ESTEC at the end of this Phase 4 6 1 6 2 6 3 V1 0 6 4 6 5 Design related documents D13 AT697F DesignReviewDocument v2 1 2008 06 06 ADF DE R0612 MLN V2 1 D14 AT697
28. ns cs seacccoutusvanntevsvenuwnuntesdaweiuactubentheadiudndapiddsenusedecepRedsacutevassiands 21 5 2 WP 6 Manufacturing and Assembly of Engineering Devices sess 21 5 3 WP 7 Electrical Characterisation and Validation sese 23 5 4 WP 8 Contractor Internal Space Qualification eene 25 5 5 WP 9 Radiation Characterisation s 2200 ccsasetanrcnnsavetasndedacoessantenisseeaaabesesanndesdccivesustanaters 25 5 6 WP10 Ev alain RT 27 Deliverables isene een met 29 6 1 Design related documents s seesesseesseesseesseeerseetsstessetsstessetrsseeessresseessesseeesssresseesseesset 29 6 2 Customer oriented d CuUMENtS esris do Iit RI de PM qiu t eo PUn ARMES 29 6 3 Validation and Characterisation related documents eese 29 6 4 Radiation related COC WHMIS TNS secsi E E tue 29 6 5 Qualification related documents secssssseseeeeeeeeeee nennen nennen nennen nnn 29 Te CONCUSSION ses e 31 AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 5 AMEL rr O F TABLE OF FIGURES Fig r 1 AT697 Project Timeline M 3 Figure 2 or idle eniin c 11 Figure 3 MCGA349 Mechanical Outline auc oniin e eniin uite da Uo NO UAR d Mah I Od MM reu I 12 Pieure 4 MOPEP256 Mechanical Outline uir uie iui ee a obiret iuis BO ein pecias E E EE 13 Figure 5 AT697F final layout and a Chip integra
29. operly installed on the back side of the DUT The subcontractor used for AT697E test campaign was unable to complete the software development and the test of the board Therefore Atmel had decided to stop the subcontractor contract and handed the radiation testing activity over to iROC iROC had restart the board test and debug IROC had developed the software environment and the test which have been used during the heavy Ions and Protons test campaign The SEE tests have also shown that a careful initialisation of the processor and handling of the SEU protection mechanism is required in boot and application software to prevent accumulation of single errors to cause uncorrectable multiple errors This knowledge will need to be transferred to users in documentation example code and technical support 5 6 WP10 Evaluation 5 6 1 Summary of the activities ATMEL has used the engineering lot for the electrical characterisation and validation and for the evaluation to be performed in WP10 For the ATMEL internal space qualification performed in WP6 however the production lot has been used This allowed ATMEL to assess the product variability to the process All the tests performed are described in the Evaluation test plan 30 All the parts were coming from 8S5247P silicon lot date code 0942 All parts used for this evaluation have been previously tested by the production test area with the following flow Electrical measurements at room temperat
30. paceQualificationTestPlan v1 1 2010 11 30 ADF PE R0822 MLN V1 0 28 D21a AT697F TotalDoseTestPlan v1 0 2008 09 26 ADF PL R0970 MLN V1 0 29 D21b AT697F SEETestDocuments v1 2 2010 12 09 ADF PL R1007 MLN V1 2 30 D22 AT697F EvaluationTestPlan v1 2 2010 10 22 ADF PL R0972 MLN V1 2 31 D23 AT697F ValidationTestBoard v1 4 201 1 10 24 7740D AERO V1 4 32 D24a AT697F ElectricalCharacterisationTestReport v5 1 2010 11 25 ADF PE R0834 MLN V5 1 33 D24b AT697F T14 T17 Report v2 1 2010 11 25 ADF PE R0840 MIL V2 1 34 D25 AT697F ValidationTestReport v1 5 2012 08 06 ADF DE R0941 MLN V1 5 35 D26 AT697F UpdatedDataSheet RevE 201 1 08 04 7703E AERO 36 AT697F erratasheet draft2 37 Preliminary SMD Specification 5962 07224 Rev C 38 L1 2a AT697F TotalDoseTestReport v2 0 2009 11 16 ADF PE R0835 MLN V2 0 39 L1 2b AT697F SEETestReport v2 2 201 1 12 06 ADF PE R0842 MLN V2 2 40 L2 1 AT697F SEETestProgramSoftware v1 0 2010 12 16 zip 41 L2 2 CNES Precap Report 8S5247P 2_ 07 10 09 42 L2 3 CNES Electrical Acceptance 43 L2 5 AT697F EvaluationReport v1 4 2012 03 07 ADF PE R1001 MLN rev1 4 44 L2 6 AT697F ESCCSpecification V1 1 2011 10 24 ESCC Spec No 9512 45 L2 7 Process identification document PID PID0030 Rev B 46 Development of the LEON processor ESA Contract 19083 05 NL FM Call off order 002 47 Evaluation Spatial ESCC du microprocesseur AT697F CNES con
31. production no SEL has been detected at 70 MeV mg cm2 and high temperature 125 C The AT697F flight version should thus be SEL immune even at high temperature A first version of the complementary AT697E SEE test report has been delivered to ESA the 7 of December 2006 The Technology Readiness Assessment Report has been sent to ESA the 5 of February 2007 together with the ATCISRHA final evaluation report the Process Identification Document the qualification package and the design manual 4 2 WP2 Preparation of the Qualification and of the Industrialisation The overall objective of the WP2 was to prepare the qualification and the industrialisation of the flight version of the AT697 For that purpose Atmel made use of the AT697E prototype devices to perform tasks of quality conformance inspection and screening tests in accordance with the product specification The main objective was to procure flight models for the PROBA 2 mission launched in 2009 and still operating in orbit Following the PIND test the 9 MQ parts have been shipped to ESA in week 42 and received at ESTEC the 20 10 2006 The qualification test report the certificate of conformity and the product specification revision B have been sent to ESA the 23 10 2006 The WP2 summary report has been delivered to ESA the 10 11 2006 The final delivery of this document has been performed the 05 01 2007 This final delivery has been accepted by ESA the 08 01 2007 4 5 WP3 Sp
32. rocess received at Nantes end 2008w37 The probe test started a week later 2008w38 All probe test patterns passed successfully and are used on all wafers before assembly 30 part of AT697F engineering models in MCGA349 have been received beginning 2008w43 and 10 part AT697F engineering models in MQFPF256 have been received For electrical characterisation and validation test one new wafer will be sent to assembly 2008w48 A validation test board description has been sent to the agency 2008w45 ESA has reviewed the document and ATMEL pursuit to the manufacturing of two test boards 5 2 Main results The AT697F has been assembled in two different package one 349 pin MCGA and in one 256 pin MQFP Some slight timing discrepancies have been found but without any impact on the final specification these differences have been reported in 32 as well as in the DLA_SMD 37 25 mr Figure 8 ATMEL AT697F package parts AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 21 AIMEL T A validation test board including one mezzanine with an AT697F packaged in a MCGA 349 embedded in an Ironwood socket and one mezzanine with an AT697F packaged in a MPFQ256 have been sent to ESA in December 2010 This application board is shown in the Figure 9 and Figure 10 It implements ten AT60142F 4 Mbits SRAM developed under a CNES contract it can be seen with the MCGA and MQFP mezzanine The user manual of the ATMEL evaluation board can be fou
33. s clarified some items as requested during the FDR A new version of the AT697F Design Review Document containing the results of these final actions has been issued the 6 of June 2008 version 2 1 This document has been accepted by ESA and as a result the Final Design Review has been declared successful the 6 of June by ESA ATMEL has sent to ESA on one DVD the Final Design Review Database deliverable of the WP4 2 the 11 of June 2008 received the 12 of June by ESA AT697F Design Report has been issued by ATMEL the 9 of July 2008 This version has been approved by ESA the 10 of J uly 2008 Ld Figure 5 AT697F final layout and a Chip integrated j Lf fm ca mum M H WIE AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 17 ENEMIES OO A C E 4 4 1 Design flow The Figure 6 shows the design flow used during the design of the AT697F LEON2 FT RTL description VHDL VERILOG Test bench from ESA rtl simulation modelsim Design Compiler Synthesis MBist Scan JTAG insertion ATPG MentorDFTSUITE fault coverage i Bist Scan JTAG Design Compiler Synthesis Gate level MODELSIM simulation i i VERILOG Netlist Ne FE kHH A 4 StarRCXT pe A Y A STA DRC OK lel NO Y lt be YES Y m FE es Y pimtool p2def pads placement Y m COP Check pad Power Consumption Ll GENIBIS Chip IBIS
34. tached through 2 meters cable to main board to allow the main board to be far enough from the proton beam Three SEE test campaigns have been done two heavy Ion campaigns And one Protons campaign Heavy Ion Campaign on 8 of September 2010 at HIF UCL Heavy Ion Campaign on 20 of November 2010 at HIF UCL Protons Campaign on 29 of September 2010 at LIF UCL 5 5 Main results The main board and a mezzanine are shown below Figure 11 Assembled radiation test main board AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 25 AMEL e fO M a Figure 12 AT697F MQFPF256 mezzanine board The AT697F total ionising dose test report 38 and the AT697F Single Event Effects test report 39 present the detailed activities and results obtained during the radiation tests performed on the AT697F The AT697F total ionizing dose TID tests have been performed in two campaigns the first one was held on 10 parts from December to January 2009 up to 300 Krad Si and the second was held on 22 parts up to 300 Krad Si The parameters measured during the read outs and after annealing were all the DC and AC parameters mentioned in the datasheet The good results confirm the total ionizing dose radiation hardness shown on the ATC18RHA technology Three heavy ions Single Event Effects SEE test campaigns for the AT697F have been performed at the Universit Catholique de Louvain UCL Heavy Ion Campaign on 8 of September
35. ted eese 17 Fig re 6 D sigsn FIOW Me EE 18 Figure 7 AT697F above and AT697E below floorplans eese enne 19 Figure 8 ATMEL AT697F package parts esed viictice aiti ate leer au PAL Rr f SE TR PUPPI S NA On EUNTES 21 Figure 9 ATMEL AT697F evaluation board with MQFP256 mezzanine eee 22 Figure 10 ATMEL AT697F evaluation board with MCGA349 mezzanine see 22 Figure 11 Assembled radiation test main board suoi ire ab ei tet Repeat chien acia dapM ecd s ien da gask das 25 Figure 12 AT697F MQFPF256 mezzanine BOSrd a eee rici Eat to esses a diee unidos ede 26 AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 6 AMEL Sy O ME 2 Overview This document presents a summary of the activities performed and of the results obtained during the manufacturing and the qualification of the LEON2 FT flight device This flight device has been made available by ATMEL with the product name AT697F ESA has developed a new Sparc V8 microprocessor architecture called LEON2 FT that includes built in fault tolerance features to prevent erroneous operations from SEE Single Event Effects induced errors The flight version of the LEON2 FT AT697 has been implemented on the 0 18 micro CMOS process of ATMEL with the new radiation hardened libraries ATC18RHA that has been designed and characterised by ATMEL under ESA Contract n 1567
36. trat 721 00 8386 02 48 15 engineering devices 3 AT697E MQFP256 7 AT697F MCGA349 and 5 AT697F MQFP256 49 An Evaluation Board one MCGA mezzanine with socket one MQFP mezzanine 50 D31 AT697F ValidationTestProgram v1 2 2012 03 29 51 D35 AT697F SetOfPicture 52 A plot of Milanion 53 5 engineering devices for CNES Atmel Nantes S A La Chantrerie BP 70602 44306 Nantes Cedex 03 France Tel 33 0 2 40 18 18 18 Fax 33 0 2 40 18 19 20 http www atmel com AMEL y O Ae 3 Product description 3 1 AT697F LEON 2 FT features e High performance Low Power SPARC V8 32 bit microprocessor Based on the LEON2 FT model version 1 0 9 16 1 8 Register windows e Advanced architecture On chip Amba bus 5 stage pipeline 32 Kbytes 4 way associative Instruction Cache 16 Kbytes 2 way associative Data Cache e On chip Peripherals Memory Interface PROM controller SRAM controller SDRAM controller Timers Two 32 bit Timers Watchdog 32 bit Timer Two 8 bit UARTs Interrupt controller with 8 external programmable inputs 32 parallel I O interface 33 MHz PCI interface compliant with PCI 2 2 specification e Integrated 32 64 bit IEEE 754 Floating Point Unit e Fault tolerance by design Full Triple Modular Redundancy TMR EDAC protection Parity protection e Debug and test facilities Debug Support Unit DSU for trace and debug IEEE 1149 1 JTAG interface Four hardware watch points e 8 and 32 bit boot PROM Interface Possi
37. uation amp Final 19038 Kick off LEON2FT AT697F Total dose amp SEE testing qualification Presentation Figure 1 AT697 Project Timeline AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 3 AMEL Sy Oo a Page left intentionally blank AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 4 AMEL r Oo a TABLE OF CONTENTS MEE Gcr RERO 3 MES a PEE UU NE 7 2 1 Reterence documents arisera a e e E E E 8 3 Product description sei esque FE ernea E tes tan ER E on EV QI RAE 10 3 1 ATOOTE LEON2 FET feat r S 5 2 2 Epiat IE pee sa n E S pte YR ERR EEE EERE EE lA 10 3 2 ATO97F block diagram ossis ias oie preti meia auskon er ade Pi pus dire uade EE EET EE E TEREE 11 3 3 AT697F MCGA 349 package ici caiscisssscaadadssscates santdned ssavocdeaasvaded snaeavanasadvesd svanacen teavadedereus 12 ae AT697FMQFP 256 package 1 ccanieancessstenragouicatanstueatcanionteassceancamdanttioddapatoaniecsstedivandiuedd 13 4 0 meeee 14 4 1 WP1 Technology Readiness ASSeSSIBOTIE sies uae ri os dbceki m bea ripe E ope o Rte aUe uit 14 4 2 WP2 Preparation of the Qualification and of the Industrialisation 14 4 3 WP3 Specification and Development Plan sicsessececcdessacnasseeaeioeriieceesverseterviaenniseaepasnis 14 dd WPA b com e M 15 A Phaeton E E 21 5 1 WE 5 Detail d Test Pla
38. ure 25 C Electrical measurements at low temperature 55 C AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 27 AMEL OTe Electrical measurements at high temperature 125 C External visual inspection Dimension check Solder ability Resistance to solvents Terminal strength Bond strength Stud pull test 5 6 2 Main results The assembled parts have been tested to The CDM and HBM ESD to estimate the susceptibility to damage and degradation by exposure to electrostatic discharge Parts passed the 2000V level without any damage on I O 3 3v According to the CDM results the product is classified in Class 4 of the ESD association The Electrical latch up All parts tested show no sensibility to power injection at 25 C and at 125 C The Breakdown voltage The break down voltage test is used to test functionality after voltage or current stress All parts tested show no sensibility Electrical characterization Verification of functionality over an extended voltage range All Functional test patterns have been successfully passed in military temperature range Static and Dynamic parameters have been measured and correlated with the simulation results Construction Analysis Detailed results are reported in CNES Precap Report 885247P 2 07 10 09 SEM inspection micro sectioning with glassivation layer integrity Detailed results are reported in document SL209 8967 Bond strength a
39. y member at ATMEL premises The 6 of June 2008 ESA has authorized ATMEL to proceed with the manufacturing of the AT697F processor AT697F summary report V3 0 08 08 2012 ADF MK R1011 MLN Page 20 AMEL y OO AM A KA HTH n 5 Phase 4 5 1 WP 5 Detailed Test Plans 5 1 1 Summary of the activities After ESA authorisation to preceed after the acceptance of the work package 3 and 4 the main task of the work package 5 was to produce all documents describing the detailed test plans After several review the final documents were sent to agencies Electrical characterization test plan 25 D18 AT697F HlectricalCharacterisationTestPlan V2 0 2010 11 24 Validation Test Plan 26 D19 AT697F ValidationTestPlan v1 1 Contractor Internal Space Qualification test plan 27 D20 AT697F ContractorInternalSpaceQualificationTestPlan v1 1 2010 11 30 Preliminary Radiation test plan 28 and 29 D21a AT697F TotalDoseTestPlan v1 0 2008 09 26 D21b AT697F SEETestDocuments v1 2 2010 12 09 Preliminary Evaluation test plan 30 D22 AT697F EvaluationTestPlan v1 2 2010 10 22 5 2 WP 6 Manufacturing and Assembly of Engineering Devices 5 2 1 Summary of the activities Following the ESA authorisation to proceed the manufacturing of the reticles has been launched in 2008w24 followed by the start of the lot fabrication itself The lot was out of the fab 2008W36 and after the grinding p

Download Pdf Manuals

image

Related Search

Related Contents

C`FLOOR - Lafage.net  PIC18F87J72 Single-Phase Energy Meter Reference  DictStrab!01-Livre.indb  堆肥の熟度判定器 - 一般財団法人 畜産環境整備機構    Murs de refend en béton armé - École Polytechnique de Montréal  IMPORTANT Manuel d`installation et de réparation  Anleitung - CONRAD Produktinfo.  APLUS QUBIC USER MANUAL - produktinfo.conrad.com  Multibrackets 7350073730339 project mount  

Copyright © All rights reserved.
Failed to retrieve file